Laserfiche WebLink
Municipal Consent Process <br /> Mn/DOT—HPDPIScoping <br /> Basic Process <br /> 1_ Mn/DOT submits the final layout to the City with a letter requesting City approval of the layout. <br /> 2. The City holds public hearing within 60 days of Mn/DOT's submittal 60 days J. <br /> and gives a 30-day(minimum) public notice of the hearing. <br /> Mn/DOT presents the layout at the public hearing -- <br /> 3. The City Council passes a resolution approving!disapproving the layout <br /> (within 90 days of public hearing). <br /> If after 90 days from the public hearing the City has not passed a 90 days <br /> resolution disapproving the layout, the layout is deemed approved <br /> 4. If the City approves, Mn/DOT can proceed with the project. <br /> 5. If the City disapproves, Mn/DOT'S options are- <br /> * Make the changes requested by the City(if any) <br /> a Refer the layout to an Appeal Board <br /> o Stop the project <br /> a Modify the project so municipal consent is not required <br /> o Prepare a new final layout and start the MC process over from beginning <br /> Before Appeal: Total Maximum time = 150 days <br /> Appeal Process <br /> 1. Mn/DOT notifies the City that it is appealing. <br /> 2. An Appeal Board of three persons is established- <br /> * Mn/DOT appoints a member Undefined time to <br /> o The City appoints a member establish appeal board <br /> o Third member selected by mutual agreement between the City& MnIDOT. <br /> If they cannot agree, MnIDOT requests the MN Chief.justice to select. <br /> The Chief Justice appoints third member within 14 days of Mn/DOT's request. 14 days <br /> 3. Mn/DOT refers the final layout to the Appeal Board. Undefined time <br /> 4. The Appeal Board holds a hearing (within 30 days of receiving final layout from Mn/DOT). <br /> The City and Mn/DOT each present their case 30 days <br /> 5. The Appeal Board makes its recommendation(within 60 days of the hearing): 60 days <br /> o Approval, or <br /> o Approval with modifications, or <br /> o Disapproval of the final layout Maximum for Appeal Process = 104 days+ <br /> (plus time to establish appeal board,etc.) <br /> 6. If the Board approves, Mn/DOT can proceed with the project. <br /> 7. if the Board disapproves, or approves with modifications, Mn/DOT's options are: <br /> o Make recommended modifications (if any), and proceed with the project <br /> o Stop the project <br /> o Modify the project so municipal consent is not required <br /> o Prepare a new final layout and start the MC process over from beginning <br /> o If it is an Interstate Highway project, Mn/DOT may proceed with the project using <br /> the layout that was not approved(and sends a report to the City and the Appeal <br /> Board stating the reasons for doing so). <br /> TOTAL Possible Time = 254 days+ <br /> NOTE: If final construction plans contain changes to access, capacity, or right-of-way from the layout approved by the <br /> City, Mn/DOT resubmits the changed portion of the plans to the City for approval. (City has 60 days to approve).This <br /> holds whether municipal consent was obtained through the basic MC process or through the appeal process. <br />