The extension requests do not change or extend any other part of the Final PUD permit. <br />Recommendation <br />Staff recommends approving the amendment to Section 3.0 Subd B.1 of the Final Planned Unit <br />Development Permit for the Traverse Business Center to extend the building permit deadline for <br />Phase I and II to July 30, 2014, and the Final PUD permit for Phase III to July 30, 2015. <br />Options <br />1.Approve the proposal as submitted. <br />2.Deny the application with reasons for denial. <br />3.Table for additional information. <br />Attachments <br /> <br />A. Final Planned Unit Development Permit <br />B. May 20, 2011, Letter from CMK Arden Holdings/Chesapeake <br />C. Amendment No. 3 to the Final Planned Unit Development Permit <br />City of Arden Hills <br />City Council Meeting for June 13, 2011 <br />C:\DOCUME~1\MEAGAN~1.BEE\LOCALS~1\Temp\ELF20110609_100416\06-13-11 - Regular Meeting - Traverse Extenstion 3 - Memo.doc <br />Page 2 of 2 <br /> <br />