3.4.2. County Site Clearance. County is responsible for causing the County Site <br /> Clearance to take place, using its own resources and any other resources that may become <br /> available through the development process. County Site Clearance will take place in a phased, <br /> orderly manner, consistent with the TCAAP Master Plan. County may elect to expedite the <br /> County Site Clearance, and will use its good faith efforts to complete the County Site Clearance <br /> in accordance with the goals for the phasing and timing thereof set out in the TCAAP Master <br /> Plan, or upon agreement of the Parties if the Master Plan has not then been approved by the <br /> Parties. <br /> 3.4.3. County Public Improvements. County will construct the Spine Road at <br /> County expense and coordinate the relocation and installation of private utilities (the "County <br /> Public Improvements") with City's installation of trunk utilities as part of its allocated elements <br /> of the Public Improvements. The TCAAP Master Plan will provide further specificity as to the <br /> desired schedule and goals for completing the respective elements of the Public Improvements <br /> described therein. <br /> 3.4.4. Off-site Transportation Improvements; Private Utilities. County has the <br /> responsibility for causing the off-site transportation improvements and associated private utilities <br /> element of the Public Improvements to be constructed. It is the Parties' the intent that the Public <br /> Improvements be constructed in accordance with a desired schedule and goal for completion set <br /> forth in the TCAAP Master Plan, and that in all instances to be timely constructed and phased to <br /> provide adequate transportation facilities for the New Development as it occurs. <br /> 3.4.5. Maintenance Plan. County will develop and implement a maintenance <br /> plan for its elements of the Public Improvements. <br /> 3.4.6. County Remediation. County will complete the County Remediation as <br /> described in the OTP and Lease. <br /> Section 3.5. City Implementation Responsibilities. City will complete its obligations and <br /> responsibilities to assist in the implementation of the TCAAP Master Plan as described in this <br /> Section 3.5. <br /> 3.5.1. AUAR. City has the legal authority as the responsible governmental unit <br /> ("RGU"), and financial responsibility for the development of the AUAR. City will coordinate <br /> the results of the AUAR with City's comprehensive plan and the development of the TCAAP <br /> Master Plan in order to guide the New Development as outlined in the TCAAP Master Plan. <br /> City will exert its best efforts to complete the AUAR within eighteen (18) months of the <br /> effective date of this Joint Agreement, and to complete the TCAAP Master Plan within six (6) <br /> months of the adoption of the AUAR, but not later than twenty-four (24) months of the effective <br /> date of this Joint Agreement for completion of the AUAR and the Master Plan. <br /> 3.5.2. City Public Improvements. City has responsibility for the construction of <br /> the City Public Improvements. City shall have the oversight authority to insure that <br /> Remediation, Site Clearance, developer installed improvements such as water mains, storm and <br /> sanitary sewer, new private utilities and other identified public amenities element of the Public <br /> 15 <br />