COUNTY RD E (B-2 DISTRICT) IMPLEMENTATION PLAN <br /> If Council decides to advance the Phase I Concept,the following general tasks will need to be initiated: <br /> • Complete preliminary design <br /> • Garner more detailed input from property owners directly affected by the proposed improvements <br /> • Refine cost estimates <br /> • Initiate cost participation approach <br /> The following is a possible schedule for the implementation of the Phase I Concept improvements: <br /> • January 2013—June 2013: complete feasibility study <br /> • June 2013—December 2013: complete final design <br /> • January 2014—March 2014: complete project bidding and assessment proceedings <br /> • May 2014—September 2014: construction <br /> Prepared by:Bolton&Menk,Inc. <br /> Project No.T16.104355 County Rd E(8-2 District)Implementation Plan-Page 8 <br />