Laserfiche WebLink
amsey County <br />TCAAP Redevelopment Project <br /> <br />Monthly Report February/ March 2014 <br />www.tcaap.net <br />Winter Schedule <br />With warmer temperatures, February <br />found Bolander working much more <br />than in January when weather had <br />progress slowed to a crawl. Work on the <br />removal of building floor slabs and <br />foundations resumed in good order. We <br />have only the largest of slabs left to <br />remove: Buildings 101, 102, 103, 501, <br />502, and 503. Underground utility <br />removals continue despite the ground <br />frost. With the mini-thaw in early <br />March, the site is again abuzz with the <br />activity of a dozen large pieces of <br />Homeland Security circa 1948 <br />equipment. <br />Since we are 12 months into active construction, it is worth recapping our current progress. To date <br />Bolander has removed the following lineal feet of material from the site: 35,000' of fence; 40,000' of <br />railroad; 12,000' steam/condensate piping; and over 100,000' of water, gas, storm & sanitary sewer <br />piping. That equates to over 35 miles of material- enough to stretch from the site to downtown St. Paul, <br />then on to downtown Minneapolis, and back to the site. In addition, we have removed and stockpil <br />over 100,000 tons of concrete and asphalt for recycling. That is the weight of an average passenger <br />cruise ship and is actually less than a third of our anticipated total from <br />In all, active work on some 100 acres is complete and awaiting final soi. <br />Demolition and Remediation Update <br />The last building standing is #502 which is the large structure clos <br />production building on the site. Internal and external asbestos <br />cleared. The small areas remaining are concealed in such a way as to require remediation during <br />building demolition. All removal of regulated material inside the buildings is compleOther chemicals <br />