Laserfiche WebLink
Capital Projects –Sewer Fund <br />•Sewer fund does not have sufficient cash to pay for <br />projects without external borrowing <br />25 <br />Projects Project <br />Number 2018 2019 2020 2021 2022 <br />EXISTING INFRASTRUCTURE PROJECTS <br />Sewer Lining/Rehabilitation 09-Sew-002 200,000 400,000 400,000 <br />Reconstruct Lift Station 11 10-Sew-003 <br />Future PMP 18-Str-005 400,000 400,000 <br />Indian Oaks/Floral Dr PMP - 2018 PMP 18-Str-065 50,000 <br />Lift Stations 125,000 125,000 <br />Actual CIP (2017 Dollars)2017 375,000 525,000 400,000 400,000 400,000 <br />Percent Inflation 3%3%3%3%3% <br />Inflated Project Costs 386,250 556,973 437,091 450,204 463,710 <br />Total Projects to be Bonded for:5-Year Term 0 0 0 0 0 <br />10-Year Term 450,000 0 1,100,000 0 900,000 <br />15-Year Term 0 0 0 0 0