Capital Projects –Storm Water Fund <br />•Storm Water fund has sufficient cash to pay for projects. <br />33 <br />Projects Project <br />Number 2018 2019 2020 2021 2022 <br />EXISTING INFRASTRUCTURE PROJECTS <br />Storm Pond Maintenance 09-Storm-001 50,000 <br />Storm Water Inlet/Outlet Repairs 13-Storm-001 25,000 <br />Storm Water BMP Study/Construction 17-Storm-001 <br />Old Snelling Ave PMP w/ Bridge Reconstruction 17-Str-004 50,000 <br />Future PMP 18-Str-005 200,000 200,000 <br />Indian Oaks/Floral Dr PMP - 2018 PMP 18-Str-065 350,000 <br />Surface Water Project (Undetermined)18-Storm-001 200,000 <br />Actual CIP (2017 Dollars)2017 550,000 125,000 200,000 0 200,000 <br />Percent Inflation 3%3%3%3%3% <br />Inflated Project Costs 566,500 132,613 218,545 - 231,855 <br />Total Projects to be Bonded for:5-Year Term 0 0 0 0 0 <br />10-Year Term 0 0 0 0 0 <br />15-Year Term 0 0 0 0 0