<br />DATE: April 9, 2018
<br />
<br />TO: Honorable Mayor and City Councilmembers
<br />David Perrault, City Administrator
<br />
<br />FROM: Sue Polka, Public Works Director/City Engineer
<br />
<br />SUBJECT: 2018 Street and Utility Improvement Project Bids/Assessment Roll
<br />
<br />Budgeted Amount: Actual Amount: Funding Source:
<br />$3,300,000 $3,340,400 Assessments, PIR, Utility Funds
<br /> Council Should Consider
<br />
<br />Adopting Resolution 2018-027 Declaring Costs to be Assessed and Ordering the Preparation of
<br />the Proposed Assessments and Calling for a Public Hearing on the Proposed Assessments for the
<br />2018 Street and Utility Improvement Project.
<br />
<br />Background/Discussion
<br />
<br />As per Council direction, bids were opened on Thursday, March 29, 2018 for the 2018 Street and
<br />Utility Improvement Project, which includes Indian Oaks Court, Indian Oaks Trail, West Floral
<br />Drive, James Circle, Gale Circle, Norma Circle, Wedgewood Drive, Brueberry Lane and
<br />Parkshore Lane. There were a total of 8 bids received. The following list provides the bidder’s
<br />name and their total bid. A full bid tabulation is attached as Attachment A.
<br />
<br />Northwest Asphalt, Inc. $2,491,595.86
<br />T.A. Schifsky & Sons, Inc. $2,559,109.29
<br />Forest Lake Contracting, Inc. $2,594,555.90
<br />Park Construction Co. $2,613,637.30
<br />Northdale Construction Co., Inc. $2,628,143.42
<br />Arnt Construction, Inc. $2,716,004.10
<br />Ryan Contracting Co. $2,781,840.90
<br />C.S. McCrossan Construction, Inc. $3,127,871.52
<br />
<br />The low bid of $2,491,595.86 received from Northwest Asphalt, Inc. compares favorably with
<br />the construction engineer’s estimate which is $2,686,970.00. Further analysis of the low bid;
<br />adding overhead and dividing it into the cost for the reconstruction and reclamation
<br />neighborhoods results in the following total project costs: