--TURNKEY PROJECT TIMELINE-¾Entire Building HVAC SolutionƒContract execution by December 2ndƒProject Implementation begins December 9thƒCooling Project Start Up & Commission Date April 13thƒHeating System Logistics and Coordination May 4thƒBuilding Heating System Shutdown and Demo May 18thƒHeating Equipment Installation June 1stƒCoordinate Domestic Hot Water Cutover Week of June 29thƒHeating System Start Up & Commissioning July 20thƒFull Project Completion and System Training Week of August 3rdProject Total……….. $ 470,110**Includes 5% combined efficiency reduction**