-TURNKEY PROJECT TIMELINE- <br />➢Entire Building HVAC Solution <br />▪Contract execution by December 2nd <br />▪Project Implementation begins December 9th <br />▪Cooling Project Start Up & Commission Date April 13th <br />▪Heating System Logistics and Coordination May 4th <br />▪Building Heating System Shutdown and Demo May 18th <br />▪Heating Equipment Installation June 1st <br />▪Coordinate Domestic Hot Water Cutover Week of June 29th <br />▪Heating System Start Up & Commissioning July 20th <br />▪Full Project Completion and System Training Week of August 3rd <br />Project Total……….. $ 470,110 <br />**Includes 5% combined efficiency reduction**