Arden Hills City Hall Mechanical Assessment 2020 <br /> Several inline fans were observed. All appeared to be in good condition with 5-10 years expected life <br /> remaining. <br /> There are several variable air volume boxes with hot water reheat coils installed. All the observed boxes <br /> and coil were in good condition with at least 5-10 years expected life remaining. <br /> Most of the observed ductwork& insulation were in good condition. There was some damaged <br /> insulation on a combustion air duct in the mechanical room. There was also a piece of return duct in the <br /> basement where the internal lining had fallen and was obstructing the duct. <br /> { { <br /> r <br /> Auxiliary Heating Systems <br /> There were (2) hot water cabinet unit heaters in the building, at the main and employee entrances. <br /> Both appeared to be in good condition with at least 5-10 years expected life remaining. <br /> --------------- <br /> 8 Page <br />