difficulties involved in proving in a legal or arbitration proceeding the actual loss suffered by Owner <br /> if the Work is not completed on time. Accordingly, instead of requiring any such proof, Owner and <br /> Contractor agree that as liquidated damages for delay, but not as a penalty; <br /> A. Substantial Completion: Contractor shall pay Owner$200.00 for each day that expires after <br /> the time specified in Paragraph 3.01 above for Substantial Completion until the Work is <br /> substantially complete, as duly adjusted pursuant to the Contract. <br /> B. Completion of Remaining Work: After Substantial Completion, if Contractor shall neglect, <br /> refuse, or fail to complete the remaining Work within the Contract Time for completion and <br /> readiness for final payment, as duly adjusted pursuant to the Contract, Contractor shall pay <br /> Owner$300.00 for each day that expires after such time until the Work is completed and ready <br /> for final payment. <br /> C. Liquidated damages for failing to timely attain Substantial Completion and final completion are <br /> not additive and will not be imposed concurrently. <br /> ARTICLE 4—CONTRACT PRICES <br /> 4.01 The Owner shall pay the Contractor for the performance of this Agreement according to the <br /> schedule of approximate quantities and unit prices as set out in the Contract Documents submitted <br /> by the Contractor on August 25, 2020, the aggregate of which is estimated to be$44,570.00. <br /> 4.02 The Contract shall include Schedule A items as provided on the Proposal Form. <br /> 4.03 Payment is based an amount equal to the sum of the extended prices, established for each <br /> separately identified item of Unit Price Work by multiplying the unit price times the actual quantity <br /> of that item completed and accepted by the Engineer. <br /> 4.04 The extended prices for Unit Price Work set forth as of the Effective Date of the Contract are based <br /> on estimated quantities. As provided in Paragraph 13.03 of the General Conditions, estimated <br /> quantities are not guaranteed, and determination of actual quantities and classifications are to be <br /> made by the Engineer. <br /> ARTICLE 5—PAYMENT PROCEDURES <br /> 5.01 Progress Payments: Owner shall make progress payments on account of the Contract Price on <br /> the basis of Contractor's Applications for Payment on or about the 10t" day of each month during <br /> performance of the Work as provided in Paragraph 5.02 below, provided that such Applications for <br /> Payment have been submitted in a timely manner and otherwise meet the requirements of the <br /> Contract. All such payments will be measured by the Schedule of Values established as provided <br /> in the General Conditions (and in the case of Unit Price Work based on the number of units <br /> completed)or, in the event there is no Schedule of Values, as provided elsewhere in the Contract. <br /> 5.02 Retainage: Prior to Substantial Completion, progress payments will be made in an amount equal <br /> to the percentage indicated below but, in each case, less the aggregate of payments previously <br /> made and less such amounts as Owner may withhold, including but not limited to liquidated <br /> damages, in accordance with the Contract. <br /> A. Ninety five(95) percent of Work completed (with the balance being retainage). If the Work has <br /> been 50 percent completed as determined by Engineer, and if the character and progress of <br /> the Work has been satisfactory to Owner and Engineer, then as long as the character and <br /> progress of the Work remain satisfactory to Owner and Engineer, there will be no additional <br /> retainage; and <br /> B. Fifty (50) percent of cost of materials and equipment not incorporated in the Work (with the <br /> balance being retainage). <br /> 5.03 Upon Substantial Completion, Owner shall pay an amount sufficient to increase total payments to <br /> Contractor to 100 percent of the Work completed, less such amounts set-off by Owner pursuant to <br /> Paragraph 15.01E of the General Conditions, and less 200 percent of Engineer's estimate of the <br /> value of Work to be completed or corrected as shown on the punch list of items to be completed or <br /> corrected prior to final payment. <br /> 2020 C1PP PROJECT AGREEMENT <br /> PW-20-0118 2 of 5 <br />