<br /> <br />Feasibility Report Page 22 <br />Snelling Avenue North and County Road E - Street and Utility Improvements <br />City Project Number PW 20-0100 DRAFT <br /> <br />6. PROJECT SCHEDULE <br />The following project schedule is proposed for improvements to Snelling Avenue North from <br />County Road E to Trunk Highway 51. <br /> <br />City Council reviews Draft Feasibility Report ...................................... December 21, 2020 <br />and Provides Direction Regarding Assessments <br /> <br />City Staff Sends Mailing and Provides Recorded ..................................... February 1, 2021 <br />Presentation for 2nd Round of Public Engagement <br /> <br />City Council Accepts Feasibility Report ....................................................... April 12, 2021 <br />and Orders Public Improvement Hearing <br /> <br />City Council Conducts Public Improvement Hearing .................................... May 24, 2021 <br />And Orders Plans and Specifications <br /> <br />City Council Approves Plans and Specifications .......................................... January 2022 <br />And Authorizes Ad for Bid <br /> <br />City Opens Bids and Computes Assessments .............................................. February 2022 <br /> <br />City Council Accepts Bids and Orders ........................................................ February 2022 <br />the Assessment Hearing <br /> <br />City Council Conducts Assessment Hearing ................................................... March 2022 <br />And Awards the Construction Contract <br /> <br />Begin Construction ............................................................................................. May 2022 <br /> <br />Complete Construction .............................................................................. November 2022 <br /> <br />City Certifies Assessments to County ....................................................... November 2022 <br /> <br />Record Plan Completion ..................................................................................... May 2023 <br /> <br />Warranty Inspection .................................................................................. September 2025 <br />(2 years Following Substantial Completion) <br /> <br />