<br /> <br /> <br /> <br /> 2 <br />The clearing and grubbing and dewatering items can often be difficult to estimate because they are specialized <br />items. Often, the clearing and grubbing estimates can get relatively high because simple removals can be <br />determined to be difficult because of site restrictions not foreseen by anyone who is not used tree removal. <br />Dewatering cost estimates fluctuate from project to project because the contractor will try to low bid that unit price <br />and risk the timing of the project and the elevation of the high water. Sometimes, they have very efficient and <br />effective ways of constructing the design under high water levels as well. <br /> <br />Upon further examination of the apparent low bid, the bid provided by Pember Construction was found to be <br />responsive and not materially unbalanced. <br /> <br />Staff recommends Council accept the bids, awarding the contract to Pember Construction for the 2021 Hamline <br />Avenue and Shorewood Drive Improvement projects, City Project PW-20-0103. <br /> <br />HR GREEN, INC <br /> <br /> <br /> <br />Jordan Horejsi, PE <br />Project Manager <br />