Laserfiche WebLink
APPENDIX B - OPINION OF PROBABLE COST <br />OPINION OF PROBABLE COST - Single Lane Roundabout <br />Feasibility Study <br />Snelling Avenue North at County Road E <br />Arden HIlls, Minnesota <br />Project Number PW-21-0100 <br />Item No. Item Unit Unit Price Est. Quantity Total Price <br />1 MOBILIZATION LS - 1 75,000.00$ <br />2 TRAFFIC CONTROL LS - 1 50,000.00$ <br />SUBTOTAL - MOBILIZATION AND TRAFFIC 125,000.00$ <br />ENG. DESIGN, ADMIN, CONTINGENCY (37%)46,250.00$ <br />TOTAL - MOBILIZATION AND TRAFFIC 171,250.00$ <br />3 CLEARING EACH $315.00 5 1,575.00$ <br />4 GRUBBING EACH $135.00 5 675.00$ <br />5 SAWING BITUMINOUS PAVEMENT LIN FT $3.00 120 360.00$ <br />6 REMOVE BITUMINOUS PAVEMENT SQ YD $3.00 4,330 12,990.00$ <br />7 REMOVE BITUMINOUS TRAIL SQ YD $5.00 200 1,000.00$ <br />8 REMOVE CONCRETE CURB & GUTTER LIN FT $3.50 1,650 5,775.00$ <br />9 REMOVE CONCRETE SIDEWALK SQ FT $1.75 95 166.25$ <br />10 COMMON EXCAVATION CU YD $16.00 3,100 49,600.00$ <br />11 SELECT GRANULAR BORROW CU YD $22.00 1,700 37,400.00$ <br />12 AGGREGATE BASE, CLASS 5 TON $18.00 1,275 22,950.00$ <br />13 BITUMINOUS MATERIAL FOR TACK COAT GAL $3.25 217 705.25$ <br />14 TYPE SP 9.5 WEARING COURSE MIXTURE (2,B)TON $85.00 175 14,875.00$ <br />15 TYPE SP 12.5 WEARING COURSE MIXTURE (2,B)TON $75.00 600 45,000.00$ <br />16 TYPE SP 12.5 NON-WEARING COURSE MIXTURE (2,B)TON $75.00 600 45,000.00$ <br />17 6-INCH CONCRETE WALK - PEDESTRIAN RAMP SQ FT $14.00 200 2,800.00$ <br />18 8-INCH CONCRETE PAVEMENT SQ FT $20.00 2,750 55,000.00$ <br />19 TRUNCATED DOME SQ FT $59.00 170 10,030.00$ <br />20 CONCRETE CURB & GUTTER, DESIGN B618 LIN FT $18.00 2,850 51,300.00$ <br />21 CONCRETE CURB & GUTTER, DESIGN SURMOUNTABLE LIN FT $20.00 460 9,200.00$ <br />22 STRIPING & SIGNAGE LS - 1 50,000.00$ <br />23 STABILIZED CONSTRUCTION ENTRANCE EACH $2,200.00 1 2,200.00$ <br />24 ROW & EASEMENTS LS - 1 125,000.00$ <br />25 EROSION CONTROL AND RESTORATION LS - 1 60,000.00$ <br />SUBTOTAL - STREET IMPROVEMENTS 603,602$ <br />ENG. DESIGN, ADMIN, CONTINGENCY (37%)223,333$ <br />TOTAL - STREET IMPROVEMENTS 826,934$ <br />26 REMOVE WATER MAIN LIN FT 6.30$ 775.00 4,882.50$ <br />27 REMOVE WATER SERVICE PIPE LIN FT 5.00$ 20.00 100.00$ <br />28 REMOVE HYDRANT AND GATE VALVE ASSEMBLY EACH 480.00$ 1.00 480.00$ <br />29 REMOVE GATE VALVE & BOX EACH 175.00$ 3.00 525.00$ <br />30 REMOVE CURB STOP & BOX EACH 105.00$ 1.00 105.00$ <br />31 2-INCH RIGID INSULATION SQ YD 34.50$ 20.00 690.00$ <br />32 TEMPORARY WATER SERVICE LS -$ 1.00 5,000.00$ <br />33 INSTALL HYDRANT, GATE VALVE AND 6-INCH DIP CL 52 ASSEMBLY EACH 5,900.00$ 1.00 5,900.00$ <br />34 1" CORPORATION STOP EACH 195.00$ 1.00 195.00$ <br />35 12" GATE VALVE & BOX EACH 4,000.00$ 4.00 16,000.00$ <br />36 1" CURB STOP AND BOX EACH 400.00$ 1.00 400.00$ <br />37 ADJUST GATE VALVE BOX EACH 258.00$ 4.00 1,032.00$ <br />38 CONNECT TO EXISTING WATERMAIN EACH 1,000.00$ 3.00 3,000.00$ <br />39 1" TYPE K COPPER PIPE LIN FT 40.00$ 80.00 3,200.00$ <br />40 DUCTILE IRON FITTINGS - EXPOXY COATED LBS 7.25$ 1050.00 7,612.50$ <br />41 6" WATERMAIN DUCTILE IRON CL 52 LIN FT 45.00$ 15.00 675.00$ <br />42 12" WATERMAIN DUCTILE IRON CL 52 LIN FT 70.00$ 760.00 53,200.00$ <br />102,997$ <br />PRELIM. ESTIMATING CONTINGENCY 38,109$ <br />WATER TOTAL OPC ESTIMATE 141,106$ <br />MOBILIZATION AND TRAFFIC <br />STREET IMPROVEMENTS <br />WATER SYSTEM <br />Snelling Avenue at County Road E <br />Intersection Improvements <br />WATER SUBTOTAL <br />Page 1 of 2