Laserfiche WebLink
•Planning Case 18-014 –Planned Unit Development Approved May 22, 2019 & Amended April 27, 2020. <br />•PUD requires the safety improvements on Lake Valentine Road to address traffic and increased pedestrian <br />crossings between the school building and the north parking lot to be completed prior to the 2021-2022 <br />school year. <br />•Phase 1 safety improvements, installed in 2020, included installation of a pedestrian traffic signal system, <br />crosswalk markings, temporary painted center median, curb ramps and sidewalk pedestrian routes to the <br />front of the school. <br />•Phase 2 was scheduled for construction in 2021 in order to provide time to potentially acquire additional <br />property from the State of Minnesota. <br />•The School District has been unsuccessful the past 2 years in obtaining an easement or acquisition of land. <br />The Applicant believes this option is no longer feasible and is preparing an alternate design. <br />Background