Background <br />•Planning Case 18-014 –Planned Unit Development Approved May 22, 2019 & Amended April <br />27, 2020. <br />•PUD requires the safety improvements on Lake Valentine Road to address traffic and <br />increased pedestrian crossings between the school building and the north parking lot to be <br />completed prior to the 2021-2022 school year. <br />•Phase 1 safety improvements, installed in 2020, included installation of a pedestrian traffic <br />signal system, crosswalk markings, temporary painted center median, curb ramps and <br />sidewalk pedestrian routes to the front of the school. <br />•Phase 2 was scheduled for construction in 2021 in order to provide time to potentially acquire <br />additional property from the State of Minnesota. <br />•The School District has been unsuccessful the past 2 years in obtaining an easement or <br />acquisition of land. The Applicant believes this option is no longer feasible and is preparing an <br />alternate design.