Karth Lake Runoff Control <br />Change Order and Unit Price Modifications Summary <br /> <br />Change Order No. 1 – Additional Existing Manhole <br />Cost: $5506.20 <br />Summary: Before construction began, a previously buried manhole was discovered after a rain event. <br />Due to this manhole, the storm sewer design was modified. The cost for the work was determined via <br />unit prices summarized in the table below. <br />Item Unit Qty Unit Price Cost <br />Salvage 18" CPP LF 33 $ 33.15 $ 1,093.95 <br />48" Storm Manhole EA 1 $ 2,725.00 $ 2,725.00 <br />Install Salvaged 18" CPP LF 33 $ 38.25 $ 1,262.25 <br />Remove Catch Basin EA 1 $ 425.00 $ 425.00 <br /> Total $ 5,506.20 <br /> <br />Change Order No. 2 – Built in Frame Casting <br />Cost: $505.00 <br />Summary: A metal frame was constructed for the inlet structure located at the top of the hill to allow <br />the high flow castings to sit securely in the manhole, while still allowing the removal of the castings if <br />the interior of the structure ever needed to be accessed. Cost was determined via material cost. <br /> <br />Change Order No. 3 - Changes to Unit Price Items <br />Cost: $2,830.25 <br />Remove Bituminous Pavement – Additional 27 SY – limits of the removal at the top of the hill extended <br />to allow improved forming of new concrete and promote drainage. <br />Aggregate Base – Additional 30 CY – with expanded paving limits, additional aggregate base required. <br />36”x22” Arch RC Storm Pipe – Additional 6 LF – an unexpected fiber line encountered during <br />construction conflicted with planned manhole location. Manhole shifted, requiring additional pipe. <br />Random Rip Rap Class III – Additional 12 CY – additional riprap placed at top of hill to protect hillside <br />from erosion in 5-year storm event. <br />Erosion Control Blanket – Additional 25 SY – additional erosion control blanket placed to ensure proper <br />establishment of new seeding. <br />