Full Project Schedule <br />•April 2024: Project Kickoff and Online Survey Development <br />•April/May 2024: Perform and Complete Public Involvement Process <br />•May 2024: Finalize Online Survey Report <br />•May 28th, 2024: Present Final Report Findings at Work Session to Council <br />•June 2024: Take Selected Scope of Work and Amend PSA for Design and Construction <br />•July/August 2024: Concept Design with Updated Cost Estimates; Host Open-House <br />•August/September 2024: PTRC and City Council Involvement and Final Cost Estimates <br />•Fall 2024: Lock in Purchase of Play Equipment <br />•February/March 2025: Bid <br />•April 2025: Award Construction Contract <br />•Summer/Fall 2025 Construction