<br /> <br /> <br /> <br /> <br /> <br /> EXHIBIT C <br /> <br /> <br /> <br /> Descri,ption of Work Time Frame <br /> <br /> Engineering Walkout 0-6 months <br /> Engineering Design 2-8 months <br /> Commerce Permitting Day 75 <br /> Fiber Optic Cable and Node Installation 11-16 months <br /> Amplifier Replacement 12-24 months <br /> Passive Equipment Replacement 18-36 months <br /> 5ystem Balancing and Proof-of-Performance 36 months <br /> Activation in Phases; Completion By November 30, 2000 <br />