Site <br />Preparation <br />Update <br />Design team has updated site <br />grading from 2018 design to better <br />balance site <br />Includes site preparation for <br />entirety of site <br />Generally, all material remains on <br />site and site is balanced <br />Total earthwork reduced by <br />~800,000 Cu. Yds <br />Earthwork Costs 50% higher than <br />2018 <br />Updated design and market cost <br />increases generally balance <br />estimated costs to be in-line with <br />2023 estimate (and current CIP)