Laserfiche WebLink
<br /> . <br />DEC-09-1998 18:39 BRW 612 370 1378 P.04/04 <br />Mr. Brian Fritsinger , <br />December 9, 1998 e <br />Page 4 <br /> price agreed to for importing additional material was is $4.50 (the original contract <br /> cubic yard unit price for importing material was 55.90). It is the opinion ofthc City <br /> Engineer that the unit prices for the additional earthwork associated with the <br /> unsuitable soils are well below industry averages and represent a competitive "dirt <br /> market" which existed during the winter of 1998. The combined cost of these work <br /> items is approximately $86,000,00 <br />Rf!cnmmendation <br />The Arden Hills City Engineer recommends Council approve Change Order #4 thereby <br />increasing the contract amount by $182,973.53 from $954,076.50 to $ 1,137,050.03. <br /> e <br />File 37951 002 8001 <br />l.HWP1)l)OS\AR:~IIlNHIJ.\[t.I.T.li:WAY\(1~.MnM e <br /> TOTAL P.04 <br />