<br />Application for Payment: Itemization
<br />Schedule: A-WATER MAIN .
<br /> Unit Contract Contract To-Date To~Date
<br />No. Item Unit Price Quantity Amount Quantity Amount
<br />1 MOBILIZATION LS $5,500.00 1.00 $5,500.00 1.00 $5,500.00
<br />2021.501
<br />2 ABANDON 8' DIP IN CASING LF $2.50 100.00 $250.00 0.00 $0.00
<br />2104.501
<br />3 REMOVE EXISTING 8" DIP WATER MAIN LF $2,50 1,260.00 $3,150.00 1,168.00 $2,920.00
<br />2104.501
<br />4 DIRECTIONAL BORE 8' PEP WATER MAIN LF $29.50 170,00 $5,015.00 0.00 $0.00
<br />2503.541
<br />5 3/4' PVC WATER SERVICE LF $31.50 60.00 $1,890,00 5.00 $157.50
<br />2503.603
<br />6 3/4' PVC SERVICE WITH CURB STOP EA $1,575.00 1,00 $1,575.00 1.00 $1,575,00
<br />2503.603
<br />7 6' PVC WATER MAIN LF $50,00 10.00 $500,00 10.00 $500,00
<br />2503.603
<br />8 8' PVC WATER MAIN LF $29.50 1,120.00 $33,040.00 1,168.00 $34,456,00
<br />2503,603
<br />9 DIP FITTINGS/WRAPPED LS $4,DO 500.00 $2,000.00 500.00 $2,000.00
<br />2504.602
<br />10 INSTALL HYDRANT /6" GATE VALVE EA $4,200,00 1.00 $4,200.00 1.00 $4,200.00
<br />2504.602
<br />11 CONNECT TO EXISTING EA $2,625.00 2.00 $5,250.00 2,00 $5,250.00
<br />2504.602
<br />12 TRAFFIC CONTROL LS $2,100,00 1.00 $2,100.00 1.00 $2,100.00.
<br />2563.601
<br />13 BALE CHECK EA $0.01 50.00 $0,50 0.00 $0.00
<br />2573.501
<br />14 SOD WITH 4' TOPSOIL SY $0.01 1,110.00 $11.10 0.00 $0.00
<br />2575.501
<br />15 SILT FENCE LF $2.00 200,DO $400.00 0.00 $0.00
<br />2575_502
<br />16 SEEDING WITH MULCH AC $1.00 0,60 $0.60 0.00 $0.00
<br />2575.505
<br /> Subtotal: $64,882.20 $58,658.50
<br />Schedule: B - SANITARY SEWER RELINING
<br /> Unit Contract Contract To-Date To-Date
<br />No. Item Unit Price Quantity Amount Quantity Amount
<br />1 MOBILIZATION LS $1,330,00 1.00 Sl,330.00 1.00 $1,330,00
<br />2021.501
<br />2 10' VCP RELINE LF $26,00 1,380.00 $35,880.00 1,378.00 $35,828,00
<br />0000.000
<br />3 12' VCP RE-LlNE LF $26,00 600.00 $15,600.00 612.00 $15,912.00
<br />0000.000
<br />4 REMOVE MANHOLE STEPS EA $50,00 35.00 $1,750.00 15.00 $750,00
<br />2104.509
<br />5 INSTALL MANHOLE STEPS EA $Bl,OO 35.00 $2,835.00 0.00 $0,00
<br />2503.602
<br />6 REBUILD MANHOLE INVERT EA $1,100.00 3.00 $3,300.00 0.00 $0.0.
<br />2506.602
<br />7 ADJUST RINGS AND CASTING EA $525.00 9,00 $4,725.00 9,00 $4,725.00
<br />2506.602
<br /> Page 3 of 5