<br />Capital Improvement Plan
<br />City of Arden Hills, Minnesota
<br />
<br />2010 thru2014
<br />
<br />Contact Engineer
<br />Department Street Department
<br />
<br />Project #
<br />
<br />Type Maintenance
<br />Useful Life
<br />
<br />Project Name Nursery HilllWyncrest/ Arden View PMP (2011)
<br />
<br />Category Streets: Reconstruction
<br />Priority nJa
<br />
<br />Total Project Cost $1,670,000
<br />
<br />Description
<br />
<br />Reconstruction:
<br />Amble Road (Hamline - dead end)
<br />
<br />I
<br />
<br />Mill and Overlay:
<br />Wyncrest Ct from Hamline to Wynridge Drive
<br />Wyncrest Ct Wynridge Drive to cuI de sac
<br />Wyncrest Lane from Wyncrest Ct to Wynridge Drive
<br />Wynridge Drive from Wyncrest Ct to cuI de sac
<br />Nursery Hill Lane from Hamline to 713' east
<br />Nursery Hill Lane from Nursery Hill Ct to 393' north
<br />Nursery Hill Court from Hursery Hill Lane to cuI de sac
<br />Dellwood St from Nursery Hill Ct to Amble Dr
<br />
<br />Full depth mill:
<br />Arden View Court from Arden View Drive to cuI de sac
<br />Arden View Drive- North from Hamline to Arden View Dr.
<br />Arden View Drive- South from HamIine to Arden View Dr.
<br />Arden View Drive- Arden View to 761' e. of Royal Hills
<br />
<br />Justification
<br />
<br />I
<br />
<br />Amble Road 2005 PCI = 69, 2008 PCI = 62, projected 201 1 PCI = 33
<br />
<br />Wyncrest Court 2005 PCI = 53, 2008 PCI = 48, projected 201 J PCI = 15
<br />Wyncrest Court 2005 PCI = 76,2008 PCI = 66, projected 20] 1 PCI = 38
<br />Wyncrest Lane 2005 PCI = 79, 2008 PCI = 69, projected 2011 PCI = 43
<br />Wynridge Drive 2005 PCI = 79, 2008 PCI = 65, projected 20ll PCI= 38
<br />Nursery Hill Lane 2005 PCI = 85,2008 PCI = 59, projected 2011 PCI = 49
<br />Nursery Hill Lane 2005 PCI = 89, 2008 PCI = 79, projected 2011 PCI = 56
<br />Nursery Hill Court 2005 PCI = 69,2008 PCI = 67, projected 201 I PCI = 41
<br />Dellwood St 2005 PCI = 85, 2008 PCI = 79, projected 2011 PCI = 56
<br />Arden View Court 2005 PCI= 62, 2008 PCI = 60, projected 2011 PCI= 3]
<br />Arden View Drive- North 2005 PCl= 65, 2008 PCI = 62, projected 2011 PCl = 34
<br />Arden View Drive- South 2005 PCI= 73, 2008 PCI= 55, projected 2011 PCI = 24
<br />Arden View Drive 2005 PCI= 56, 2008 PCI= 53, projected 2011 PCI = 22
<br />
<br />Project must Ineet Rice Creek Watershed District requirement. The project is projected to make storm sewer improvements as determined to
<br />improve water quality of Karth Lake and sanitary sewer improvements to COITect any 1&1 deticiencies.
<br />Watermain in Arden View Townhomes has a continous history ofwatennain breaks (25 watennain breaks in 30 years). Due to the location of
<br />watennain (between townhomes, under private drives, etc.) this watennain is a good candidate for lining, however, lining is still a relatively new
<br />technology and is expensive. Given the number of underground utilities in the area, open trench replacement would also be expensive. It is
<br />recommended to replace the sections of watennain under the public streets as part of the PMP, and pursue a separate watennain project for the
<br />relnaining watermain segments.
<br />
<br />Prior
<br />162,500 I
<br />
<br />Total
<br />
<br />Expenditures
<br />Construction/Ma intenance
<br />
<br />2010
<br />1,426,000
<br />
<br />1,426,000
<br />
<br />2011
<br />81,500
<br />
<br />81,500
<br />
<br />2012
<br />
<br />2013
<br />
<br />2014
<br />
<br />Total
<br />1,507,500
<br />
<br />1,507,500
<br />
<br />Total
<br />
<br />Produced Using the Plan-it Capital Planning Sofm'are
<br />
<br />17Jursday,. June 11. 2009