HomeMy WebLinkAbout2B, Valentine Park Drainage Analysis Review EN HILLS
Request for Council Review
2B
Prepared By: Terry Maurer,Public Works Director Worksession Date: December 20,2010
Valentine Park Drainage Analysis Review
Discussion Topic:
WSB's Valentine Park Drainage Analysis dated February 2009 has been reviewed by Bolton and Menk.
In addition staff will present survey information gathered regarding properties adjacent to Valentine Park
and information received from Rice Creek Watershed. Staff will be seeking direction on how to proceed
with the 2011 CIP programmed improvements in Valentine Park.
Supporting Documents:
1. Memorandum dated December 20, 2010 from Terry Maurer and Kris Giga
2. Review Letter dated November 2, 2010 from Bolton and Menk, Inc.
EN HILLS
MEMORANDUM
DATE: December 20, 2010
TO: Honorable Mayor and City Council Members
Patrick Klaers, City Administrator ,yam
FROM: Terry Maurer, Public Works Director 1� p
Kris Giga, Civil Engineer
SUBJECT: Valentine Park Drainage Review
Background
In February 2009, WSB prepared the Valentine Park Drainage Analysis in anticipation of a
future park improvement project. Valentine Park historically has been periodically inundated
when Valentine Lake's water level rises in spring snow melt or after large rainfall events. The
WSB analysis was undertaken to better understand the options available for investment in the
park given the periodic flooding from Valentine Lake. When the analysis was presented to the
City, neighborhood concerns regarding its conclusions led to the City Council directing staff to
have another consultant review the analysis and render a professional opinion regarding its
conclusions.
Discussion
Staff solicited quotes and Bolton& Menk, Inc. (BMI)was retained to perform the review of the
February 2009 WSB drainage analysis. BMI's letter dated November 2, 2010 summarizing their
findings is attached. The summary of BMI's findings is that the inputs into the drainage model
are accurate, and the conclusions in the WSB report appear to be appropriate. They do question
the Normal Water Level (NWL) in the WSB report of 875.5 versus the Ordinary High Water
Level (OHWL) they received from the DNR of 878.8. BMI also suggests the drainage model be
rerun after a determination is made regarding which is the appropriate elevation so the City will
have an accurate representation of a storm event.
Staff also had Roseville's surveyor determine the lowest opening on the homes adjacent to the
park. The lowest opening was determined to be a walk-out patio door at elevation 8839. BMI's
review determined that the DNR's highest recorded lake level is 881.1. Industry standards would
have the lowest opening elevation a minimum of 2' above the highest flood elevation. The above
information indicates that there is 2.8' between the highest flood elevation and the lowest
City Council Meeting = -
11Metro-inetlardenhillslAdmin\CouncillAgendas&Packet Information12010112-20-10 WorksessionTacket Information112-
20 ValentineParkDrainageReview.doe
Page 1 of 2
opening. This would indicate that filling of the park to raise improvements out of flood danger
should have no adverse effects on adjacent properties if proper drainage is included in the design.
Staff met with Rice Creek Watershed (RCW)to discuss the outflow from Valentine Lake. RCW
staff provided information regarding which portions of the outflow are controlled by the DNR,
and which portions are controlled by the Wetland Conservation Act.
Finally, staff met with Mr. Don Messerly to get an historic perspective on the park flooding.
Staff also shared briefly with Mr. Messerly our findings from the overall analysis and our general
thoughts about improvements to the park including drainage.
At the workshop, staff will provide a detailed presentation of these findings. Staff will be looking
for direction from the Council on how to proceed with the programmed 2011 CIP improvements
to the park.
City Council Meeting
11Metro-inetlardenhillslAdminlCounciIlAgendas&Packet Information120IO112-20-10 WorksessionTacket Information112-
20 ValentineParkDrainageReview.doc
Page 2 of 2
• E-3C�L.T41'�.,I �. M �N K , ! Nam®
• Consulting Engineers &Surveyors
12224 NicolletAvenue•Burnsville,MN 55337
Phone(952)$90-0509 o Fax(952)690-3065
www,bolton-menk.com
November 2, 2010
Mr.Terry Maurer, P.E.
Public Works Director
City of Arden Hills
Arden Hills, MN 55112
RE: Engineering Review for Valentine Park Drainage Analysis
City of Arden Hills,Minnesota
Mr. Maurer:
We have reviewed the drainage analysis prepared by WSB&Associates on February 9,2009 for the
Valentine Park sub-watersheds of the City of Arden Hills (City). In addition, we performed a site visit on
September 22, 2010 to compare the hydrologic model assumptions with the existing conditions observed
within the Valentine Park sub-watersheds.
The drainage analysis,completed by WSB,provided three options for mitigating the localized flooding
within Valentine Park. Per our scope of services we reviewed: "Option#1 —Maintain Park Facilities with
Improved Drainage and Storm Water Treatment", found on page 8 of the drainage analysis,the data and
results of the XPSWMM model, the practicality of the proposed stormwater system layout,and the
apparent cost to value relationship of the overall improvements. Bolton &Menk, Inc. only reviewed the
XPSWMM model results. The model itself was not provided for review.
THE XPSWMM MODEL
Based on the hydrologic model information that was provided in the drainage analysis it appears that the
model parameters and assumptions were properly identified using the standard of care appropriate for an
analysis of this type and scale_ When we compared the model assumptions with the existing conditions
observed within the sub-watersheds it appears that the existing conditions are accurately reflected in the
hydrologic model.
The model identified localized flooding within the Glenview Avenue and the Crystal Avenue drainage
networks for the 5-, 10-,and 100-yr, 24-hr storm events. This flooding was identified in the report, but
we believe it is important to note that given that the area has been identified in the City's Pavement
Management Program(PMP) for reconstruction, there are options available to the City,within the PMP,
that will have a significant impact on downstream(Valentine Park)flooding.
It is widely accepted that on urban sites,controlling stormwater at the source is more efficient,cost-
effective,and sustainable than the alternative,end of pipe treatment. The City has the opportunity to
implement street reconstruction Best Management Practices(BMPs)such as reduced pavement width,
biofiltration, bioinfiltration, and other means of volume control and water quality in the PMP that would
significantly reduce the downstream flooding at Valentine Park and meet the Rice Creek Watershed
District abstraction requirements. This approach would be similar to Option#3 in the drainage analysis
accompanied with additional hydrologic model evaluation.
City of Arden Hills
November 2,2010
Page 2
Finally, the hydrologic model that has been created for this project is a powerful tool that the City can and
must utilize to efficiently evaluate the downstream effects of various BMPs installed in the upper sub-
watersheds. The goals of this analysis would be reduced downstream flooding in Valentine Park,and
increased water quality for stormwater flowing to Valentine Lake.
DRAINAGE ANALYSIS
The conclusions drawn in the drainage analysis appear appropriate given the input parameters,storm
events modeled,and the results of the model.
During our site visit we observed lake water approximately 15-in to 20-in deep in the Snelling Avenue
36"RCP culvert extending into the park,adjacent to the parking area,and backing up the park outlet ditch
approximately 25-ft. This water level roughly corresponds to a lake elevation of 877.0. This elevation is
approximately 1.5-ft higher than the stated Normal Water Level(NWL). This elevated lake water level
creates a"tail water"condition at the culvert that increases the localized flooding within Valentine Park-
One discrepancy we identified during the site visit may be related to the condition of the outlet for
Valentine Lake. The report states that a recent lake level of 879.0,recorded on 10/14/08,is higher than
the stated NWL of 875.5 likely due to beaver dams,within the lake's outlet channel,which have since
been removed. We understand that the City and Ramsey County currently monitor and maintain the
lake's outlet channel condition. We recommend that effort continue in order to keep the lake's outlet
channel clear of debris and invasive species and control the Ordinary High Water Level(OHWL).
It is our understanding that the 875.5 elevation was obtained from the Rice Creek Watershed District.
However,the watershed district now recommends that Valentine Lake water level data be obtained from
the Minnesota Department of Natural Resources(Mn/DNR). Our review of current Mn/DNR lake data
conflicts with the elevations listed in Figures 3 and 4 of the drainage analysis and presumably the values
entered into the hydrologic model (see Figure 1). According to Mn/DNR the OHWL of Valentine Lake is
878.7, the highest recorded water level is 881.1 taken on 07/03/78,and the latest reading taken on
10/01/10 was 879.58. The Mn/DNR defines the OHWL as:
...an elevation delineating the highest water level that has been maintained for a sufficient
period of time to leave evidence upon the landscape,commonly the point where the natural
vegetation changes from predominantly aquatic to predominantly terrestrial."
The Mn/DNR makes no mention of a NWL of 875.5,and in general does not use that term. In addition,
the lowest elevation recorded for the lake during the past 10 years was approximately 876.7 during the
summer of 2002. We have included the Mn/DNR water level graph showing Lake Valentine water Ievels
from the year 2000 to 2010(see Figure 1), which identify the elevation of 878.7 as the overall average
elevation of the lake. We recommend that the lake OHWL and the 100-yr high water(881.1)level,as
recorded by the Mn/DNR, be utilized to calibrate the XPSWMM model as a verification of the model's
accuracy_
FA-CivillARDRU16120645\T16.120645 Report RevieW_FINAL.dorx
City of Arden Hills
November 2,2010
Page 3
Valentine — 62007100
679.75
6 $76.5
� 4,J
Ui
877.25
676
2001 2002 200 2004 2005 2006 2007 2008 2009 2010
Figure L -Valentine Lake Water Level Graph(Jan 2000—Nov 2010)
We understand that based on data that the City has collected on lowest structure opening for the
residences adjacent to Valentine Park, the lowest opening recorded was 883.92,effectively three feet -
above the 100-yr high water level(HWL)of Valentine Lake. The state minimum for lowest opening
above HWL's is two feet. We believe that the current standard of three feet of free board provides an
acceptable level of safety for residences adjacent to water bodies within the City.
The tail water condition at the Snelling Avenue culvert that was identified in the drainage report as a
"...contributing factor to the flooding in the park"may be mitigated,in part,with the installation of a tidal
valve on the culvert outlet within Valentine Lake. If this approach is considered,the City will need to
coordinate with,and obtain approvals from,the Mn/DNR and the Rice Creek Watershed District prior to
installation. Although, if the average lake surface elevation is 878.7,no amount of mitigation with water
quality and volume control BMPs in the Valentine Park sub-watershed areas will address the localized
flooding in the park. This observation is based solely on the recorded OHWL of Valentine Lake and the
ground surface elevation of Valentine Park. A tidal valve may represent a cost effective solution that
would isolate the tail water effect created by the current OIIWL of Valentine Lake while still allowing the
Valentine Park sub-watersheds to discharge through the culvert.
PROPOSED STORMWATER SYSTEM LAYOUT
The stormwater system layout identified in Option#1 appears to have been configured in the appropriate
manner given the space constraints and park programming identified during the public meeting and
recommended by the Park,Trails,and Recreation Committee.
F:1_CiviHARDMT1 6 1 206451T]6.120645 Report Review_FINAL.docx
City of Arden Hills
November 2,2010
Page 4
When designing a stormwater treatment train,the most efficient use of space and money dictates that the
rate control pond be the first BMP in the train. It has the capacity to absorb the incoming peak flows and
discharge water in a more controlled manner. All of the BMPs downstream of the rate control pond can
then be designed based on the discharge rate of the pond and not the incoming peak flow rates,thereby
increasing efficiency and decreasing required space.
The recommendations included adding fill material to Valentine Park to bring the mean elevation up from
approximately 880.0 to 882.0. According to the XPSWMM model,those two feet of fill would protect
the park amenities from flooding up to the 100-yr storm event. One alternative that was not evaluated in
the drainage analysis was adding less fill to the park to protect it from a smaller storm, i.e. a 10-, 20-, or
50-yr storm and accept more frequent localized flooding as a result of construction cost savings.
We do not believe that additional fill within Valentine Park will ultimately affect the OHW or the HWL
of Valentine Lake. The area of the park proposed to be raised is very small when compared to the overall
surface area of Valentine Lake. This can be evaluated within the XPSWMM model to provide a
reasonable prediction of the change,if any. In addition the most current FEMA Flood Insurance Study
(.tune 2010)lists a 500-yr high water elevation for Valentine Lake of 881.3.
A second possible alternative would include modifying the PMP to incorporate volume control and water
quality at the source,as described above, and then address the remaining flooding problem,if any, at
Valentine Park through future hydrologic model evaluations.
COST TO VALUE RELATIONSI41P VALUE OF THE IMPROVEMENTS
The OPTION#1 stormwater management treatment train appears to have been appropriately sized,the
proposed park elevation corresponds to the modeled 100-yr storm event,and the cost estimate included in
Appendix C appears reasonable for the identified improvements.
As mentioned above, there may be a more cost effective solution to the Iocalized flooding experienced at
Valentine Park. The solution will require additional time to be realized as the PMP improvements are -
constructed.
It is very likely the most cost-effective solution will require a combination of integrating volume control
and water quality BMPs into the PMP in the upper Valentine Park sub-watersheds. Based on the results
of the XPSWMM model, implementing source control BMPs into the Glenview Avenue and Crystal
Avenue sub-watersheds may have the greatest impact in reduced localized street flooding and
downstream flooding within Valentine Park.
Once the volume of stormwater flowing from the upper sub-watersheds to Valentine Park is reduced,the
Valentine Lake outlet continues to be monitored and maintained by the City and Ramsey County,and the
OHWL of the lake is verified at the appropriate elevation,the hydrologic model should be modified to
reflect these improvements. With a revised and updated model the City can verify the need,if any,of
additional park improvements to alleviate localized flooding.
CONCLUSIONS
There may be additional cost savings available to the City to address the localized flooding at Valentine
Park. Portions of the approach will require additional time to evaluate,model, plan,and implement,but a _
number of the possibilities are straight-forward and simple, i.e. monitor the condition of the outlet of
F:1_CiviIV"ffiT1 6 1 2 05451T16.120645 Report Rcview_F1NAL.docx
City of Arden Hills
November 2,2010
Page 5
Valentine Lake or evaluate the installation of a tidal valve on the Snelling Avenue culvert.
However, if lake levels,as recorded by Mn/DNR,are accurate,the implementation of upstream BMPs
will have a reduced benefit at Valentine Park. The addition of fill material to the park, to effectively raise
the park out of the floodplain of Valentine Lake, becomes the primary solution to reduce localized
flooding within the park.
Our recommended next steps for further investigation of the Valentine Park flooding issues and potential
mitigation efforts include the following:
• Continued monitoring of the condition of the Valentine Lake outlet
• Review Valentine Lake surface elevations(i.e. NWL,HWL,and OHWL)relative to any potential
outlet modifications
• Identify likely BMP improvements in the Valentine Park upper sub-watersheds
• Update XPSWMM model with Mn/DNR OHWL level as well as potential BMP improvements in
the Glenview Avenue and Crystal Avenue sub-watersheds
• Utilize the Mn/DNR 100-yr HWL and the FEMA 500-yr HWL to calibrate the XPSWMM
model.
• Use the model as a tool to review multiple possible solutions to mitigate the Valentine Park and
upper sub-watershed flooding
• Based on model predictions select the best volume control and water quality BMPs and locations
that result in decreased park and street flooding
The City may want to account for a public comment period associated with the volume control and water
quality BMPs in the upper Valentine Park sub-watersheds. If the BMPs are on or near private property it
has been our experience that property owner buy-in is essential to project success. If the BMPs are in the
city Right-of-Way it will be less of an issue,but getting public acceptance remains an important part of a
successful project.
Bolton&Menk is available to discuss possible alternatives and assist with planning and modeling if
needed.
Sincerely,
BOLTON&MENK, INC.
Douglas Carter,P.E., LEED AP
Water Resources Engineer
cc: Marcus Thomas, P.E.,Bolton&Menk, Inc.
File
F:1_Civil\ARDMT161206451T16.120645 Report Review_FINAL.docx