HomeMy WebLinkAboutAgenda
Mayor
:
Address:
Stan Harpstead
1245 West Highway 96
Arden Hills MN 55112
Councilmembers:
David Grant
Phone:
Brenda Holden
Agenda
651.792.7800
Fran Holmes
David McClung
Website:
October7, 2008
www.ci.arden-hills.mn.us
SpecialCity Council Meeting–7:30a.m.
City Vision
A strong community that values our unique environment, our fiscal soundness,
and our tradition as a desirable city in which to live, work, and play.
CALL TO ORDER
1.APPROVAL OF AGENDA
2.NEW BUSINESS
Motion to Amend the Contract with A.J. Spanjers Company, Inc and Wiss, Janey,
A.
Elstner for the Masonry Façade Repair Project at City Hall for a Revised Total Amount
Not to Exceed $308,372.50.
ADJOURN
Request for Council Action
Prepared By:Dave Scherbel, Building OfficialCouncil Meeting Date:October 7, 2008
Masonry Façade Repairs Project
Budgeted Amount:Actual Amount:Funding Source:
$244,790.00$ TBDEquipment Building and
Replacement Fund
Recommendation:
Motion to Amend the Contract with A.J. Spanjers Company, Inc and Wiss, Janey,
Elstner for the Masonry Façade Repair Project at City Hall for a Revised Total Amount
Not to Exceed $308,372.50.
Supporting Documents:
1.October6, 2008, Memo to the City Council
2.WJE’sreport detailing additional work
MEMORANDUM
Agenda Item 1.A
DATE:
October 6, 2008
TO:
Mayor and City Council,
Ron Moorse,City Administrator
FROM:
Dave Scherbel,Building Official
SUBJECT:
MasonryFaçadeRepairs Project
CC:
James Lehnhoff,Community Development Director
Background
On March 31, 2008, the City Council approved an amount not to exceed $244,790.00 for the
exterior repairs on the City Hall building. Of the approved amount, $23,000.00 was for Wiss,
Janey, Elstner (WJE), the project engineer. The remaining $221,790 was to A.J.Spanjers (AJS)
the masonry contractor. The approved amount included a $41,700 contingency for additional
repairs that could be used as needed during the project.
In the course of their work, the contractor and engineer haveencounteredadditionalissues
related to the current project and additional concernsthat were not anticipated but need to be
addressed. Due to the additional unforeseen issues,thetotalcost of the repairs will exceed the
approved contingency.
The City’s hired engineer has submitted the estimated costs for the additional repairs.The
estimates are divided into threeparts (see attachment for more detail):
x
Items 1 and 4 are additional costs related to the repairs already started and are needed to
complete the current repairproject.Cost: $32,482.50
x
Items 2 and 3 are unanticipated issues that were discovered during the course of this
repair project but are recommended by the City’s hired engineer.Cost: $65,000
x
Additional investigation and engineering.Cost: $8,000
\\Ahdocs1\ah\AHdata\Building\City Hall\Masonry Facade repairs\100608- CC Report - Masonry Facade repair.doc
1
Including engineering and inspections, the total cost of the additional repairs is $105,482.50,
which is $63,782.50 more than the approved contingency. Items 1 and 4 can be completed
without additional Council action because they can be covered by the existing contingency.
However,items 2 and 3 will cause the project to exceed the approved cost and contingency. If
the repairs for items 3 are delayed to 2009, AJS states that the cost would increase by $2,500.
TheCity’s buildingofficial, Dave Scherbel, and the project engineer from WJE, Brian Pashina,
will be in attendance to discuss the reason, cost, timing, pros, and cons of the additional repairs.
Mr. Scherbel is reviewing the project to determine if other options are available that may help
lower the cost.
Finally,this project is sensitive to the weather, and the contractor has expressed concern
regarding the application of a cleaning agent on the masonry once the area has been completed.
In order for the product to work correctly, the surface temperature needs to be above 50 degrees.
If the repairs described in items 2 and 3 are to move forward in 2008, approval is needed as soon
as possible to ensure that work can be completed before the weather changes.
FinancialImplications
Funding for this project is availablefromtheEquipment Building and Replacement Fund.This
fund was established during the 2008 budgeting process and City Hall repairs were budgeted in
the 2008-2012 CapitalImprovement plan from this fund.The City will be utilizing funds
received from the mediation settlement.
Requested Action
If the repairs described items 2 and 3 are approved, the motion would be as follows:
Motion to Amend the Contract with A.J. Spanjers Company, Inc and Wiss, Janey, Elstner for the
Masonry Façade Repair Project at City Hall for a Revised Total Amount Not to Exceed
$308,372.50.