MEMORANDUM
DATE:September 19, 2011
TO:Honorable Mayor and City Councilmembers
Patrick Klaers,City Administrator
FROM:Terry Maurer, Public Works Director
Michelle Olson, Parks and Recreation Manager
SUBJECT:Valentine Park Improvement Update
Background
The Valentine Park Improvements were last before the City Council at the June 13, 2011
Meeting. For your information the council memo(Attachment A) and the minutes
(Attachment B) fromthe June 13, 2011 meeting are attached.
Since June a detailed drainage design relative to the neighborhood draining through the
park to Valentine Lake has been completed. It has been determined that a park and a
drainage system can co-exist on the property and can be constructed in such a manner as
to protect the park amenities and adjacent properties. In general this will be accomplished
by constructing a plateau at approximately elevation 882 which will contain the park
amenities and parkinglot. This area will still be almost two feet below the lowest home
opening adjacent to the park which is at elevation 883.91. The remaining park property
will be used for a detention pond, rain garden sized to accommodate a large portion of the
neighborhoods requirement when the streetsare reconstructedand a large grass area.
At the June 13 meeting there was a question about where to place the park amenities; on
the western side of the park nearer the adjacent homes or the east side of the park nearer
the street. Attached are two conceptual drawings (Attachment C) showing the same park
amenities, detention pondand rain garden. Staff is looking for direction on the general
layoutof the park/drainage improvements.
A more specific cost estimate has been prepared by design item since the final layout has
not been finalized yet. The cost estimates is as follows:
City Council Meeting
\\Metro-inet.us\ardenhills\PR&PW\Parks\Memos\Council Memos\091911ValentineParkMemo.doc
Page 1of 3
Valentine Park Improvement Cost Estimate
Demolition, site preparation and erosion protection
$21,000
measures
Site grading, pond construction, rain garden, storm
$165,000
drainage facilities
Parking lot (curb/gutter and pavement)$50,000
Playstructure and swing set$60,000
Half court basketball area$15,000
Picnic shelter(16’X16’)$35,000
Tree play area$35,000
Concrete path to tree play area$32,000
Furnishings (picnic tables, bike rack, trash receptacles,
$32,000
foot bridge, portable restroom screen)
Landscaping (shade, ornamental and coniferous trees,
$31,500
rain garden plantings, turf establishment)
Bituminous(8’)trail from Glenview to Old Hwy 10and
$45,000
along Old Hwy 10 to Cty Road E2
18”play area curbing$11,500
Mobilization$15,000
$65,760
Engineering (12%)
construction contingency$50,000
ESTIMATED TOTAL PROJECT COST$663,760
The CIP programmed amount for these improvements is $310,000; $50,000 for a play
structure and $260,000 for the park development. The $260,000 amount was from the
February 2008 WSB Drainage Analysis Report. The $260,000 amount has never been
verified or adjusted since February 2008.
From the above preliminary cost estimate there are certainly some costs that could be
reduced or eliminated such as the tree play area ($35,000), the concrete pathway leading
to the structure for ADA compliance ($32,000) andeither of the bituminous trailsaround
the park perimeter($45,000).Staff will also be looking for additional funding from Rice
Creek Watershed District for the rain garden and the DNR for the trails included in the
concept.
City Council Meeting
\\Metro-inet.us\ardenhills\PR&PW\Parks\Memos\Council Memos\091911ValentineParkMemo.doc
Page 2of 3
The next step after the City Council gives direction on the park layout would to have a
staff hosted meeting in the park where residents could view various pieces of the concept
relative to their homes. Staff would also immediately proceed to final design and bidding
documents while also perusing outside possible funding opportunities.
Council Action Requested
Staff is asking for Council to review the project budget and provide direction on park
layout.
City Council Meeting
\\Metro-inet.us\ardenhills\PR&PW\Parks\Memos\Council Memos\091911ValentineParkMemo.doc
Page 3of 3
A
Attachment :
June 13, 2011 Memo regarding Valentine Park Improvements
MEMORANDUM
DATE:
June 13, 2011
TO:
Honorable Mayor and City Councilmembers
Patrick Klaers, City Administrator
FROM:
Michelle Olson, Parks and Recreation Manager
Terry Maurer, Public Works Director
SUBJECT:Valentine Park Improvements
Background
In 2008, WSB was hired by the City to conduct a drainage analysis of the Valentine Park
Area. The purpose of this study was to identify sources of flooding in Valentine Park and
to provide solutions that would reduce or eliminate the flooding. The City Council
retained Bolton and Menk, Inc. to render a “second opinion” on the WSB study. Staff
presented the findings to the City Council and PTRC at meetings in December 2010.
On January 31, 2011 the City Council approved a process with a tentative schedule on how
to proceed with park improvements in conjunction with needed drainage enhancements.
The staff memo presented is attached for your review (Attachment A).
Public Input
Hoisington Koegler Group Inc. (HKGi) was retained to lead the park improvement process.
Apublic open house was held on April 7, 2011 at City Hall from 6:00-7:30 p.m. A total of
233 residents were mailed invitations and it was posted on the City website. An online
survey wasavailable for all residents to give input on potential improvements. 53
residents completed the survey either online or at the open house. 28 people signed in at
the open house. Attached are the results of the online survey (Attachment B) and
comments received at the open house (Attachment C) for review. Existing conditions and
two concepts (Attachment D) were shown at the open house with different park
improvements. The concepts were shown with thevarious options of amenities and
improvements to thepark.It was clear to the residents that the final concept could be a
combination of the two concepts. The amenities and park features were the focus versus
the design and layout of the park. The design and layout cannot be decided until surveys
and drainage analysis is done. The concepts shown were only to demonstrate the general
area where amenities maypossiblygo.
PTRC Recommendation
HKGi attended the April 19, 2011 Parks Trails and Recreation Committee (PTRC) Meeting
to discuss the open house findings. Paul Paige from HKGi presented a summary of the
\\Metro-inet.us\ardenhills\PR&PW\Parks\Memos\Council Memos\06132011 Valentine Park
Improvements.doc
2
findings (Attachment E). He provided a revised draft concept based on feedback from
residents (Attachment F)in orderto give the PTRC a concept to comment and make
suggestions and changes to.The features included on this plan were:
Grass play area
Playground with swings
Half court basketball court
Small picnic shelter
Small informal tree play area
Interpretive signage along interior walking path
Small 10 stall parking lot
Portable restroom enclosure and a bike rack
Rainwater gardens
Bio-swale and footbridge
Stormwater pond to mitigate flooding issues
Adiscussion took place on the various comments and results from the open houseand the
potential improvements to the park.Minutes from that meeting are attached for Council
review (Attachment G). The PTRC discussed the inclusion ofan open grass play area
versus a formal ag-lime baseball field. This would eliminatethe inclusion of a winter ice
rink. The majority of the residents who attended the open house preferred a grass field to
an ag-lime baseball field, even if that meant eliminating the ice rink. The PTRCconsensus
was that the rink is small,underutilized and other parks are close by that can provide
pleasure skating. In particular, Cummings Park is a pleasure rink (no hockey rink)that has
a beautiful facilityand would be quiet for families to avoid the broomball and hockey
users.
After reviewing the information, the PTRC made a motion to recommendinclusion of all
of the elements on the draft concept plan with the addition of:
Drinking Fountain
Trails along park perimeters that extendand connect north/south to County Road
E2 and east/west to Glenview Ave.
The motion carried unanimously.
The PTRC recommended keeping the small informal tree play area in the concept.
However, they listed this structure as a low priority due to concerns about this area being
out of site and closer to residents. The comments on this play areaat the open house were
mixed but seemed fairly positive. However, since the PTRC meeting, the neighbor closest
to that structure has indicated they would not be in favor of the tree play area due to its
secluded location and proximity to his house.
HKGi revised the draft concept plan to include the recommendation from the PTRC and
this is included for Council review (Attachment H).
\\Metro-inet.us\ardenhills\PR&PW\Parks\Memos\Council Memos\06132011 Valentine Park
Improvements.doc
3
Budget
The 2011 CIP has a total of $310,000 for improvements to Valentine Park. Staff may have
the opportunity to seek drainage improvement grant fundingthrough Rice Creek Watershed
District. The next round for applications for this will be sometimein Marchof2012.The
survey work and drainage plans will determine exact placement of park features and also
project costs. The next step in the process would be to authorize staff to move into plan
preparation. Once the plans, specifications and budget information is complete, it will be
brought back to the PTRC and neighbors for review and then to the City Councilfor
consideration to authorize staff to go out for bid.
Council Action Requested
Motion to authorize staff to move into design and budgeting analysis for Valentine Park
improvements based on the draft concept plan recommended by the PTRC.
\\Metro-inet.us\ardenhills\PR&PW\Parks\Memos\Council Memos\06132011 Valentine Park
Improvements.doc
B
Attachment :
June 13, 2011 Council Meeting Minutes
Approved:July 25, 2011
CITY OF ARDEN HILLS, MINNESOTA
REGULAR CITY COUNCIL MEETING
JUNE 13, 2011
7:00 P.M. -ARDEN HILLS CITY COUNCIL CHAMBERS
CALL TO ORDER/ROLL CALL
Pursuant to due call and notice thereof, Mayor David Grantcalled to order the regular City
Council meeting at 7:00p.m.
Present:
Mayor David Grant;Councilmembers Fran Holmes, Brenda Holden,Ed
Werner and Nicholas Tamble.
Absent:
None.
Also present
: City Administrator Patrick Klaers; Community Development Director Jill
Hutmacher; City Planner Meagan Beekman; Civil Engineer Kristine Giga; Parks and
Recreation Manager Michelle Olson; Public Works Director Terry Maurer; and Recording
SecretaryTina Borg.
PLEDGE OF ALLEGIANCE
1.APPROVAL OF AGENDA
MOTION:Councilmember Holden moved and Councilmember Tamble seconded a
motion to Approve the Agenda as presented.The motion carried
unanimously (5-0).
2.PUBLIC INQUIRIES/INFORMATIONAL
A.Recognition of Girl Scout Gold Award Recipient Ann Lindberg
Mayor Grant
stated Ann Lindberg, an Arden Hills Girl Scout, was recently named a Girl Scout
Gold Award recipient.
Ms. Ann Lindberg
explained her project involved collecting 100 children’s books as donations,
organizing the reading and recording of 50 books, making a CD of the recorded books, and then
donating the books and CD’s, as well as five portable CD players, to a small community library in
Shadow Lake Wisconsin where her grandparents live. She explained the Gold Award was the
equivalent to the Boy Scout’s Eagle Scout Award and includes 60-hours of community service.
ARDEN HILLS CITY COUNCIL –June 13, 20112
2.A.Recognition of Girl Scout Gold Award recipient Ann Lindberg (continued)
Mayor Grant
presented Ann Lindberg with a Certificate from the City and thanked her for her
community service.
B.TCAAP/Stadium Update
Community Development Director Jill Hutmacher
stated Staff has been in contact with
Ramsey County Staff regarding local financial issues and possible new legislation. All parties are
waiting to see whether a special legislative session will be called prior to the end of June. New
information available this afternoon was the County and the Vikings had obtained funding for a
portion of the transportation costs. They were requesting the State provide additional fundingfor
reversible lanes that could be used by commuters on weekdays. This was all the information
available at this time since it was just announced.
Mayor Grant
asked if this would provide an opportunity to alleviate congestion on I-35W.
Community Development Director Hutmacher
stated this proposal would include an extra
lane on I-35W during rush hour and game times.
Public Works Director Terry Maurer
stated Ramsey County sent an exhibit in regardto
transportation possibilities to the City today. It is not detailed at this time and Staff has not had an
opportunity to review this exhibit.
PUBLIC
Mayor Grant
opened the Public Inquiries/Informational at 7:08 p.m.
Ms. Nisha Shah
, 1706 Valentine Avenue, Arden Hills, stated that she was opposed to the
proposed park improvements at Valentine Park that removed the ice-skating rink and the baseball
field. The baseball field is one of the few places nearby to play and the ice-skating rink is one of
the only recreational ice rinks in the City. The other ice rinks in the City are used forhockey
which makes it difficult for recreational skaters and beginners to skate at those facilities.
Mr. GreggLarson
,3377 N Snelling Avenue, Arden Hills, stated the City had sent a letter to the
County in regardto the Stadium proposal several months before notifying residents that a Stadium
was even being considered. He stated he is against a Stadium on the TCAAP property and this is
not what the residents had envisioned for this property. He stated the Council is acting
inappropriately in how they are handling the release of information to the residents. He stated the
City needs to hold public meetings and communicate with residents regarding the potential
Stadium use on the TCAAP property.
Mayor Grant
closed the Public Inquiries/Informational at 7:16p.m.
ARDEN HILLS CITY COUNCIL –June 13, 20113
3.APPROVAL OF MINUTES
A.May 2, 2011, Special City Council Meeting
B.May 9, 2011, Regular City Council Meeting
C.May 9, 2011, Executive Session Meeting
D.May 16, 2011, City Council Work Session Meeting
MOTION:Councilmember Holden moved andCouncilmember Holmes seconded a
motion to Approve the May 2, 2011, Special City Council Meeting minutes,
the May 9, 2011, Regular City Council Meeting minutes, the May 9, 2011,
Executive Session Meeting minutes, and the May 16, 2011, City Council Work
Session Meeting minutes as presented. The motion carried unanimously (5-0).
4.CONSENT CALENDAR
A.Motion to Approve Consent Agenda Item –Claims and Payroll.
B.Motion to Approve Amending Section 3.0 B.1 of the Final Planned Unit
Development (PUD) Permit for the Traverse Business Center to Extend the
Building Permit Deadline for Phase I and II to July 30, 2014, and the Final PUD
Deadline for Phase III to July 30, 2015.
C.Motion to Authorize the Purchase of Used 2001 Sterling Dump Truck with Plow
and De-icing Equipment from Ramsey County for $30,000 Plus Sales Tax and
Authorization to Repaint the Truck to Match the Rest of the City Fleet.
D.Motion to Adopt Resolution 2011-028; Approving Mn/DOT Agreement No.
98490R and Authorizing the Mayor and City Administrator to Execute the
Documents Regarding I-694/TH 51 Interchange Project.
E.Motion to Adopt Resolution 2011-029, Designating Depositories and Corporate
Authorizations and Adopt Resolution 2011-030, Transfer of Funds by Telephonic
Instructions.
MOTION:Councilmember Holmes moved and Councilmember Holden seconded a
motion to approve the Consent Calendar as presented and to authorize
execution of all necessary documents contained therein. The motion carried
unanimously (5-0).
5.PULLED CONSENT ITEMS
None.
6.PUBLIC HEARINGS
A.Annual National Pollutant Discharge Elimination System (NPDES) Public
Meeting
Civil Engineer Kristine Giga
statedthatas of March 10, 2003, the Minnesota Pollution Control
Agency (MPCA) required all cities within the seven county Metro Regionto apply for a General
ARDEN HILLS CITY COUNCIL –June 13, 20114
6.A.Annual National Pollutant Discharge Elimination System (NPDES) Public Meeting
(continued)
Storm Water Permit (Small Municipal Separate Storm Sewer Systems, or MS4 permit) as part of
Federal National Pollutant Discharge Elimination System (NPDES) requirements. In order to
comply with federal regulations, municipalities were required to develop a Storm Water Pollution
Prevention Plan (SWPPP) that focuses on ways the municipality will reduce the amount of
sediment and pollutionentering the surrounding water bodies. The SWPPP includes six
minimum control measures that need to be addressed by the City. Each measure is aimed at
reducing the amount of pollution entering water bodies through various methods such as public
outreachand education, regulatory ordinances, and physical structures constructed as a part of the
storm water sewer system. Every year the City is required to hold a public meeting on the
SWPPP. The City is also required to submit an annual report to the MPCA documenting the
accomplishments of the previous year. She reviewed the accomplishments of the previous year
and the2011goals for the Council.
Councilmember Holden
asked Civil Engineer Giga if information received from Rice Creek
Watershed District wasin the City’s Newsletter.
Civil Engineer Giga
stated as the information was received from Rice Creek WatershedDistrict
it was forwarded to the Newsletter for publication.
Mayor Grant
opened the Public Hearing at 7:28 p.m.
Mayor Grant
closed the Public Hearing at 7:29p.m.
7.NEW BUSINESS
A.Zoning Code Amendment –School Uses in the R1 District
City Planner Meagan Beekman
stated in January 2011, the City Council approved a number of
amendments to the City’s Zoning Code. The purpose of these amendments was to incorporate the
TCAAP Zoning Regulations into the rest of the Code. In doing so, it was necessary to amend
Section 1320.05 of the Zoning Code, which indicates which land uses are allowed in each district.
As part of this process, other amendments to the Code were made that were not directly related to
the TCAAP zoning regulations. One of these amendments included a revision to the Land Use
Chart to allow higher education uses in the R1 District with an approved Planned Unit
Development (PUD). The reason the Code was amended to allow higher education uses in the R1
District was because Northwestern College is located in the R1 District. As future phases of
Northwestern College’s Master PUD are implemented, or amendments to the Master PUD are
necessary, it is important that the City’s regulations be in line with the actions being taken by the
City Council. By approving a Master PUD for Northwestern College in 2007, and allowing other
educational uses in the R1 District as conditional uses, the Council has historically determined
that educational uses are in keeping with the purpose of the R1 District under certain
circumstances. A recent review of the Zoning Regulations made Staff aware of a discrepancy
between the language of the Code and the intention of the January 2011 amendments. Staff is
recommending a Zoning Code Amendment that would add special regulations for school uses in
ARDEN HILLS CITY COUNCIL –June 13, 20115
7.A.Zoning Code Amendment –School Uses in the R1 District (continued)
the R1 District, and specify a minimum lot size for these uses, as well as define what would
comprise a campus. The Planning Commission reviewed this application and held a public
hearing at their June 6, 2011, meeting. The Planning Commission unanimously recommended
approval of the proposed changes.
Councilmember Werner
asked what other communities allowed for educational uses in the R1
District.
City Planner Beekman
stated the uses for the R1 District vary depending on the community.
Arden Hills is unique because educational uses were already present when the District was
established. The uses for theR1 District were written around the uses that were already in the
District, including higher education. Colleges and higher education facilities are dealtwith
differently by each community.
Councilmember Holden
asked if there was any place within the R1 District that had 10 acres or
more wherea higher education facility could be established.
City Planner Beekman
stated she was not aware of any property within the R1 District that was
10or more acres. If someone wanted to build a higher education facility within the District on
less than 10 acres theywould have to go through the variance process or a PUD process. She
explained a higher education use would have to go through a PUD process regardless. She
explained that BethelUniversityoperates under a CUP and is in its own district. Northwestern
College operates under a PUD and is part of the R1 District. If higher education is removed from
theLandUse Chart of permitted uses inthe R1 District, Northwestern College would become a
non-conforming property which would affectany additional updates, construction, or changes that
might occuron the property.
Councilmember Holden
asked if Northwestern College could be made into its own district
similar to BethelCollege.
City Planner Beekman
stated this would be one method,but Northwestern College would need
to be involved in thatdiscussion. It is possible to include Northwestern College in the same
district as BethelUniversity. The City had discussed this in the past but the benefits with
Northwestern College being in the R1 District are the regulations in the R1 District are more
restrictive and the City has more control over development. The City could also look at writing
the Code and Ordinance to be more restrictive in the R1 District similar to the changes that were
made to accommodate the old Holiday Inn site and the redevelopment of thatsite.
Councilmember Holden
stated she would like to have the City look into this option further for
future consideration. She also stated the City should increase the minimum amount of acres
required for the current amendments.
City Planner Beekman
stated 10 acres was chosen because this is the smallest parcel that could
accomplishthe intention ofcode amendments. The minimum parcel size could be increased if the
Council decides to make this change.
ARDEN HILLS CITY COUNCIL –June 13, 20116
7.A.Zoning Code Amendment –School Uses in the R1 District (continued)
MOTION:Councilmember Holden moved and Mayor Grant seconded a motion to
approve Ordinance 2011-005 in Planning Case 11-013 to Amend Section
1320.04, Subd.1, and Add Section 1320.075 to the Zoning Code to Regulate
School Uses in the R1 District, as presented in the June 13, 2011, Report to the
City Council.
Councilmember Holden
stated she would like to have this change in place now and have Staff
continue to look at options for Northwestern Collegesuch asmaking it its own district or
including it in the BethelUniversityDistrict.
City Planner Beekman
statedthe Ordinance would not be legal until it was published.
MOTION:Councilmember Holden moved and Mayor Grant seconded a motion to
amend the motion to include Approving the Publication of a Summary of
Ordinance 2011-005. The motion carried unanimously (5-0).
Mayor Grant
agreed with Councilmember Holden that the Cityshould move forward with this
amendment at this time.
The amended motion was called to a vote.
The motion carried unanimously (5-0).
8.UNFINISHED BUSINESS
A.Valentine Park Improvements
Parks and Recreation Manager Michelle Olson
stated in 2008, WSB was hired by the City to
conduct a drainage analysis of the Valentine Park Area. The purpose of this study was to identify
sources of flooding in Valentine Park and to provide solutions that would reduce or eliminate the
flooding. On January 31, 2011,the City Council approved a process with a tentative schedule on
how to proceed with park improvements in conjunction with needed drainage enhancements.
Hoisington Koegler Group Inc. (HKGi) was retained to lead the park improvement process. A
public open house was held on April 7, 2011. Existing conditions and two concepts were shown
at the open house with different park improvements. The amenities and park features were the
focus versus the design and layout of the park. The design and layout cannot be decided until
surveys and drainage analysis are done. The concepts shown were only to demonstrate the general
area where amenities maybe located. Paul Paige,from HKGi,presented a summary of the open
house findings and a revised draft concept based on feedback from residents to the Parks, Trails,
and Recreation Committee(PTRC). After reviewing the information, the PTRC made a motion to
recommend inclusion of all of the elements on the draft concept plan with the addition of a
drinking fountain and trails along park perimeters that extend and connect north/south to County
Road E2 and east/west to Glenview Avenue. The 2011 Capital Improvement Plan includesa total
of $310,000 for improvements to Valentine Park. Staff may have the opportunity to seek drainage
improvement grant funding through Rice Creek Watershed District. The next round for
applications for this grant will be some time in March 2012. The survey work and drainage plans
ARDEN HILLS CITY COUNCIL –June 13, 20117
8.A.Valentine Park Improvements (continued)
will determinetheexact placement of park featuresas well asproject costs. The next step in the
process willbe to authorize Staff to move into plan preparation. Once the plans, specifications
and budget are completed,this proposalwill be brought back to the PTRC and neighbors for
review and then to the City Council for consideration to authorize Staff to go out for bid. She
explained that prices have not been determined for the amenities at this timebut will be
determined as part of the plans and specifications.
Mayor Grant
asked if the retention ponds would have standing water and if it was anticipated
there would standing wateryear round.
Public Works Director Maurer
stated the residents have expressed they do not want to have
standing water in the park. It is important to get to the design phase so that the drainage issues
can be identified and possible solutions investigated. The idea is to have ponding areas for
drainage during heavy rainfalls that would drain off and then begenerally dry.
Mayor Grant
asked if the trail depicted on the concept plan was included in the budget.
Public Works Director Maurer
stated theinternaltrail is part of the concept. The trail around
the perimeter wasrecommended by the PTRC and is not included in the project budget.
Mayor Grant
stated the addition of a drinking fountain would requirethatthe park have water
service and at this time it does not. He asked how much it would be to run a water line and
maintain the drinking fountain.
Public Works Director Maurer
stated this has not been fully analyzed at this time. It is included
in the list of amenities to be priced and looked into further.
Parks and Recreation Manager Olson
stated the PTRC had included the drinking fountain
because this may be the only opportunity the City has to add this amenity. If the cost is too high
the PTRC will evaluate it further.
Mayor Grant
stated the budget may cover the cost of adding a drinking fountain but he did not
see a big enough benefit in it to justify the cost. He suggested that once the project costs have
been identified,each item should be evaluated to be sure it makes sense.
Councilmember Holden
asked if the ball fields had any scheduled leagues that play at this
location. She asked if the City had a shortage of baseball fields or soccer fields.
Parks and Recreation Manager Olson
stated there are games scheduled for this field but they
have been moved due to the current conditions of the park. The City does have enough baseball
fields and the open green space in the concept plan can be used as a soccer field if needed.
ARDEN HILLS CITY COUNCIL –June 13, 20118
8.A.Valentine Park Improvements (continued)
Councilmember Holden
stated she was not in favor of the tree house feature in the concept plan.
It is located tooclose to the homes in this area and it presents a high liability to the City. She also
stated the concept plan does not include any features for adults which she would like to see
included.
Public Works Director Maurer
stated the park would have the trail and park benches but Staff
could look at other amenities for adults as well.
Councilmember Holden
asked about the trail that goes around the park to the woodedarea with
the proposed tree house. She expressed concernabout includingthe water fountain.
Parks and Recreation Manger Olson
stated that this trail was ADA compliant and had to go
from the parking lot to the park amenities to allow access. If there was not a tree house or other
play area or amenity in the corner then there did not need to be a trail in this area
Councilmember Werner
stated the proposed shelter was small. He asked if there would be a fee
charged for this shelter. He also asked what the surface material would be for the basketball
court.
Parks and Recreation Manager Olson
stated this shelter would be added to the City’s fee
schedule and this would be reviewed by the City Council. The basketball court would be
constructed of bituminous with an acrylic overcoat similar to the other basketball courts in the
City
Councilmember Werner
stated he is not in favor of the tree house feature. This structure
presents a liability risk to the City.
Parks and Recreation Manager Olson
stated the tree house was a feature meant to tie in that
area of thepark and make it feel like it is part of the park. The play structureis made of recycled
material to make it look like natural wood. It would be low maintenance.
MayorGrant
stated he did not agree with the location of the tree house structure.
Public Works Director Maurer
stated the amenities and locations are only suggestions at this
time and the tree house structure was placed in the corner in order to utilize more of the park.
Mayor Grant
asked where the storm water ponds would be located. He also asked how much
elevation change was included in the plan.
Public Works Director Maurer
stated the pondswould be located around the perimeter of the
park. The plan includes an elevation increase of a couple of feet but this will be determined based
onthe drainage needs of the park.
Councilmember Holmes
stated the main concern is getting the drainage problems resolved in the
park.
ARDEN HILLS CITY COUNCIL –June 13, 20119
8.A.Valentine Park Improvements (continued)
Public Works Director Maurer
stated the drainage would be resolved with the design stage of
planning. This will provide the information needed to determine what will be needed for the
drainage.
Councilmember Holmes
suggested the proposed parking lot be moved so when you come into
the park rather than taking a right into the parking area,a person would take a left. The park
amenities could then be moved to the other sidewhich would keep them away from the homes.
The amenities would be closer to the lake so when parents are watching their children at the park
they can look at the lake.
Public Works Maurer
stated the neighborhood did provide input regarding the location of the
park amenities. The residents had requested a half basketball court in order to reduce the noise
and some of the play areas were moved further from the homes. If the park amenities were
moved,theywould be closer to the road, which could be a problem for smaller children. The
design phase will look at the drainage and how to best utilize the green space and where to put the
amenities. He suggested having the project move into the design phase and then bring a couple of
concept plans to the residents to consider. Once the drainage has been resolved,the potential
location for amenities can be determined. He suggested having an open house in thepark so
residents could see where in the park the amenities could be located. He emphasizedthatat this
time the design phase would be needed in order to determine what would need to be done to
resolve the drainage issues and once this is determined thelocation and types of amenities can be
finalized.
MayorGrant
asked when construction would take place.
Public Works Director Maurer
stated construction could start later this summer and be
completed the following summer or construction could be donein 2012. It would be better for the
residents to do the construction in the spring of 2012 since the residents do not use the park in the
spring due to the flooding.
Councilmember Holden
stated she would like to see some form of play area in the shadedarea
of the park for the kids. She does not like the tree house concept but would like to see something
in this area of the park.
Councilmember Holden
asked what the interpretive signs were.
Public Works Director Maurer
stated the signs would integrate the drainage facilities into the
park and make it feel like part of the park.
Councilmember Holden
stated the signs for the Elmer L. Anderson signs were already damaged.
Parks and Recreation Manager Olson
stated she was aware of damage to the Ramsey County
sign and has been working with the signvendor and Ramsey County on this.
Councilmember Holden
stated the other ice rinks in the City have hockey players on them and
this does make it difficult for recreational and beginner skaters to enjoy the rink.
ARDEN HILLS CITY COUNCIL –June 13, 201110
8.A.Valentine Park Improvements (continued)
Parks and Recreation Manager Olson
stated the rink at Cummings Park is a recreational rink
and is only for pleasure skating with no broomball or hockey allowed. Users do not overwhelm
this rink. Valentine Park and Cummings Park have the only rinksrestricted to pleasure skating
use at this time and if the rink is not replaced at Valentine Park then Cummings Park would be the
only pleasure skatingrink in the City.
Councilmember Holden
asked if fencing would be required around the ponds.
Public Works Director Maurer
stated this has notyetbeen determined yet. Once the design
phase is complete,Staff will have a better understanding of what is needed and will make
recommendations to the Council.
Councilmember Tamble
asked who would be taking part in the design.
Public Works Director Maurer
stated Roseville Staff would be involved in the design including
the analysis of the topography. This is more of an engineering project than a park project because
of the drainage issues that need to be resolved.
Councilmember Tamble
stated he liked the overall park plan. The storm water issues are on the
eastern side of the park and the concept plan has all of the park amenities onthe western side. He
stated he would be interested in assisting with the layout.
Mayor Grant
stated he would like to seeinformation onthe cost of the amenitiesearly in the
planning process.
It was the consensus of the Council to look at different options for the tree house play set.
Public Works Director Maurer
stated the Council could approve moving the project into the
design phase. Staff could then bring the amenities costs and potential locations to the Council for
review and Staff could then work up different concept plans for the park layout. These plans
could then be brought to the residents for their review and input.
MOTION:Councilmember Holden moved and Mayor Grant seconded a motion to
Authorize Staff to Move Into Design and Budgeting Analysis for Valentine
Park Improvements;and When the Drainage Design is 60% Completed Staff
will Provide a Cost Analysis ofthe Park Amenities and Concept Plans to the
City Council Prior to BeingPresented at a Neighborhood Meeting. The
motion carried unanimously (5-0).
9.COUNCIL COMMENTS & STAFF UPDATES
Councilmember Tamble
stated the information packet provided to the Council on Valentine
Park was well done and provided good information.
ARDEN HILLS CITY COUNCIL –June 13, 201111
9.Council Comments & Staff Updates (continued)
Councilmember Werner
stated the residents have had an opportunity to provide input regarding
Valentine Park and this has been appreciated.
Councilmember Holmes
requested Staff to be sure the March 21, 2011,letter from the City to
Ramsey County regarding the Vikings Stadium concerns is placedon the City’s website.
Councilmember Holmes
stated there isstillan opening on the Planning Commissionand
applications are on the City’s website. She also stated she will not be able to attendthe July 18
work session meeting.
MayorGrant
stated the U.S.Department of Commerce sent information about the census and
how to get information about the community and surrounding communities.
Mayor Grant
stated the MN Rural Water Association sent a letter to the City with educational
opportunities for Staff. The City also received a letter from the Met Councilon MCES.
Mayor Grant
thanked the Operations and Maintenance Staff for all their work in making the
City’s flower gardens look good. They look considerably better than last year. He asked Staff to
continue to look through the plantings and addressany plants that need to be replaced.
Mayor Grant
asked if the City maintained the garden on Lexington Avenue and County Road E.
Parks and Recreation Manager Olson
stated Northwestern College had been maintaining the
garden until the end of the school year. The garden has not been maintained since.
MayorGrant
stated he would like this garden to look nice and asked Staff to look into having
this garden maintained and the grass mowed on the property. He also thanked Parks and
Recreation Manager Olson for following up on the issues at 1960 County Road E2.
Councilmember Holden
asked to whom dead trees in the City should be reported and if the dead
trees on the Presbyterian Homes property had been reported.
Parks and Recreation Manager Olson
stated dead trees could be reported to her and she would
have the Forester take care of these.
Councilmember Holden
asked how many sump pumpinspections were remaining.
Public Works Director Maurer Terry
stated sump pumpinspections were scheduled to be
completed by the fall of this year.
MayorGrant
asked Staff to update the information of the City’s website concerning ash borer
disease and other links that may be helpful for residents.
ARDEN HILLS CITY COUNCIL –June 13, 201112
ADJOURN
MOTION: Councilmember Holmes moved and Mayor Grant seconded a motion to
adjourninto a work session. The motion carried unanimously (5-0).
Mayor Grant
adjourned the Regular City Council Meeting at 8:53p.m.
____________________________________________________
Patrick KlaersDavid Grant
City AdministratorMayor
C
Attachment :
Conceptual Drawings of Park Improvements