HomeMy WebLinkAbout4C, Resolution 2011-049 - Final Payment for the 2010 PMP to T.A. Schifsky and Sons,Tt
A DEN HILLS
Request for Council Action
Prepared By: Kristine Giga, Civil Engineer
Council Meeting Date: October 10, 2011
Resolution 2011 -049: Accepting Work Completed, Starting Two -Year Warranty and
Authorizing Final Payment for the 2010 Pavement Management Program to T.A. Schifsky
and Sons, Inc., in the Amount of $10,507.82
Budgeted Amount:
$1,102,000
Estimated Actual Amount:
$933,766.77
Funding Source:
PIR, Enterprise Funds, Special
Assessments
Recommendation:
Approve Resolution 2011 -049: Accepting the work completed, starting two -year warranty and
authorizing final paymentfor the 2010 Pavement Management Program to T.A. Schifsky and Sons, Inc.,
of North Saint Paul, Minnesota, in the amount of $10,507.82.
Supporting Documents:
1. Memorandum dated October 10, 2011 from Kristine Giga.
2. Application for Payment #6.
3. Resolution 2011 -049.
�I�N HILLS
MEMORANDUM
DATE: October 10. 2011
TO: Honorable Mayor and City Councilmembers
Patrick Klaers, City Administrator
FROM: Kristine Oiga, Civil Engineer
SUBJECT: 2010 Pavement Management Program- Payment #6 (Final Payment)
Background
The City of Arden Hills awarded T.A. Schifsky & Sons, Inc., of North Saint Paul,
Minnesota, the 2010 Pavement Management Program Project on May 10, 2010, for a
total contract amount of $779,799.67. Change Order #1 was approved simultaneously,
eliminating Janet Court from the project, reducing the contract amount to $731,630.59.
Discussion
This pay request includes $10,000 of retainage held during the construction of the
project, and some additional restoration work the contractor completed this spring as
directed by City Staff.
Financial Implications
The following breakdown shows the funding sources and amounts for Payment #6:
Funding Source
Amount
PIR
$ 7,243.49
Surface Water Management
$ 913.52
Sanitary Sewer
$ 1,114.28
Watermain
$ 1,236.53
Total
$ 10,507.82
The final contract amount was $752,707.99, which is 2.8% more than the original
contracted amount, or $21,077.40. This is due to the two change orders that were
City Council Meeting
\\ Metro- inet.us \ardenhills \PR &PW\ Engineering \Council_Actians\2011 \10 -10 -11 Memo_201 OPMP Payment #6_fnal.doc
Page 1 of 2
approved by the City Council during construction for a heavier roadway section on
Valentine Court and part of Valentine Avenue. Significant rain events created unusually
wet conditions. It was determined that it would be most time and cost - effective to
increase the roadway section rather than try to dry the in -place soils. A 4% contingency
was included in calculating the assessment rate; these additional costs are within the
contingency. The total engineering costs were 15% of the construction costs, or 5% less
than the estimated 20% of construction costs.
The following table shows final costs allocated to each of the funds, including
construction costs. WSB and Roseville engineering costs and overhead fees
(administrative, legal, etc.. as defined in the assessment policy).
Council Action Requested
Approve Resolution 2011 -049: Accepting the work completed, starting two -year
warranty and authorizing final paymentfor the 2010 Pavement Management Program to
T.A. Schifsky and Sons, Inc., of North Saint Paul, Minnesota, in the amount of
$10,507.82.
City Council Meeting
\\ Metro- inet.us \ardenhills \PR &PW \Engineering \Council_Actions \2011 \ 10 -10 -11 Memo_2010PMP_Payment #6_fnal.doc
Page 2 of 2
Budgeted
T.A. Schifsky
and Sons, Inc.
WSB &
Associates,
Inc.
Roseville
13%
overhead
TOTAL
Roadway
$ 532,000
$ 507.165.04
$ 57,622.45
$19,948.87
$ 65.931.45
$ 650,667.81
Storm Sewer
$ 175,000
$ 68,714.80
$ 7,807.15
$ 2,702.83
$ 79,224.79
Sanitary Sewer
$ 20,000
$ 83,816.02
$ 9,522.91
$ 3,296.83
$ 96,635.75
Watermain
$ 75,000
$ 93.012.13
$ 10,567.74
$ 3,658.55
$ 107,238.41
State Aid
$ 300,000
Total
$1,102,000
$ 752307.99
$ 85,520.25
$29,607.07
$ 933,766.77
Council Action Requested
Approve Resolution 2011 -049: Accepting the work completed, starting two -year
warranty and authorizing final paymentfor the 2010 Pavement Management Program to
T.A. Schifsky and Sons, Inc., of North Saint Paul, Minnesota, in the amount of
$10,507.82.
City Council Meeting
\\ Metro- inet.us \ardenhills \PR &PW \Engineering \Council_Actions \2011 \ 10 -10 -11 Memo_2010PMP_Payment #6_fnal.doc
Page 2 of 2
Associates, .Inca
Owner: City of Arden Hills
1245 West Highway 96
Arden Hills, MN 55112
For Period: 2/5/2011 to 9/27/2011
Contractor: T. A. Schifsky & Sons, Inc.
2370 East Hwy. 36
North St. Paul, MN 55109
Pay Voucher
ARDH - 2010 Pavement Management Project
Client Contract No.:
Project No.: 01771 -02
Client Project No.:
Date: 9127/2011
Request No.: 6 & FINAL
Project Summary
1
Original Contract Amount
$779,799.67
2
Contract Changes - Addition
$23,858.06
3
Contract Changes - Deduction
($48,169.08)
4
Revised Contract Amount
$755,488.65
5
Value Completed to Date
$752,707.99
6
Material on Hand
$0.00
7
Amount Earned
$752,707.99
8
Less Retainage
$0.00
9
Subtotal
$752,707.99
10
Less Amount Paid Previously
$742,200.17
11
Liquidated Damages
$0.00
12
AMOUNT DUE THIS PAY VOUCHER NO. 6 & FINAL
$10,507.82
I HEREBY CERTIFY THAT A FINAL EXAMINATION HAS BEEN MADE OF THE ABOVE NOTED CONTRACT, THAT
THE CONTRACT HAS BEEN COMPLETED, THAT THE ENTIRE AMOUNT OF WORK SHOWN IN THE FINAL
VOUCHER HAS BEEN PERFORMED AND THE TOTAL VALUE OF THE WORK PERFORMED IN ACCORDANCE WITH,
AND PURSUANT TO, THE TERMS OF THE CONTRACT IS AS SHOWN IN THIS FINAL VOUCHER.
Recommended for Approval by:
WSB & Associates, Inc.
Approved by Contractor:
Construction Observer:
Approved by Owner:
T. A. Schifsky & Sons, Inc. City of Arden Hills
Specified Contract Completion Date: Date:
5/31 /2011
Comment:
Page 1
Project Material Status
Item
No.
Item
_
Description
Units
Unit Price
Contract
Quantity
Quantity to
Date
Current
Quantity
Amount to
Date
Schedule A - Street Improvements
1
2021.501
MOBILIZATION
LUMP SUM
$28,500.00
1
1
0
$28,500.00
2
2101.605
CLEARING AND GRUBBING
ACRE
. $7,210.00
0.75
0.92
0
- $6,633.20
3
2104.501
REMOVE WATER MAIN
LIN FT
$3.09
730
716
0
$2,212.44
4
2104.501
REMOVE SEWER PIPE (STORM)
LIN FT
$5.15
255
219
0
$1,127.85
5
2104.501
REMOVE SEWER PIPE (SANITARY)
LIN FT
$2.06
1405
1501
0
$3,092.06
6
J 2104.501
REMOVE SANITARY SERVICE PIPE
LIN FT
$2.06
800
275
0
$566.50
7
2104.501
REMOVE MANHOLE (SANITARY)
LIN FT
$30.90
75
44.2
0
$1,365.78
8
2104.501
REMOVE CONCRETE CURB AND GUTTER
LIN FT
$1.65
250
312.5
0
$515.63
9
2104.503
REMOVE RETAINING WALL
SQ FT
$6.18
120
90
0
" $556.20
10
2104.505
REMOVE CONCRETE PAVEMENT
SQ YD
$2.06
445
347.2
0
$715.23
11
2104.505
REMOVE BITUMINOUS PAVEMENT
SQ YD
$1.03
9620
10175.7
0
$10,480.97
12
2104.505
REMOVE CONCRETE VALLEY GUTTER
SQ YD
$4.12
15
45.9
0
$189.11
13
2104.509
REMOVE HYDRANT ASSEMBLY
EACH
$154.50
7
6
0
$927.00
14
2104.509
REMOVE GATE VALVE & BOX
EACH
$103.00
10
7
0
$721.00
15
2104.509
REMOVE STRUCTURE (STORM)
EACH
$309.00
4
3
0
$927.00
16
2104.509
REMOVE GATE VALVE BOX
EACH
$51.50
1
4
0
$206.00
17
2104.511
SAWING CONCRETE PAVEMENT (FULL DEPTH)
LIN FT
$2.06
260
295.5
0
" $608.73
18
2104.513
SAWING BITUMINOUS PAVEMENT (FULL DEPTH)
LIN FT
$1.29
1170
347.25
0
" $447.95
19
2104.523
SALVAGE CASTING
EACH
$103.00
16
16
0
, $1,648.00
20
2104.601
SALVAGE AND REINSTALL LANDSCAPE STRUCTURES
LUMP SUM
$2,060.00
1
1
0
" $2,060.00
21
2104.602
SALVAGE AND REINSTALL MAIL BOX
EACH
$56.65
32
32
0
$1,812.80
22
2104.603
ABANDON WATER MAIN
LIN FT
$1.03
420
420
0
$432.60
23
2105.501
COMMON EXCAVATION (P)
CU YD
$8.03
6000
5960
0
$47,858.80
24
2105.507
SUBGRADE EXCAVATION (EV)
CU YD
$9.27
600
746.4
0
$6,919.13
25
2105.522
SELECT GRANULAR BORROW (CV)
CU YD
$9.27
600
585.4
0
$5,426.66
26
2105.525
TOPSOIL BORROW (LV)
CU YD
$9.27 `
1250
1080.7
40
$10,018.09
27
2105.601
DEWATERING
LUMP SUM
$0.01
1
1
0
$0.01
28
2105.604
GEOTEXTILE FABRIC TYPE!
SQ YD
$2.06
315
288
0 :
$593.28
29
2105.604
GEOTEXTILE FABRIC TYPE IV
SQ YD
$6.17
25
45
0
$277.65
30
2105.607
1 1/2" CLEAR ROCK
TON
$12.36
150
326.33
0
$4,033.44
31
2211.501
AGGREGATE BASE CLASS 5 'TON
$9.50
5300
6114.01
0
$58,083.10
32
2232.501
MILL BITUMINOUS SURFACE
SQ YD
$0.90
11600
7350
0
$6,615.00
33
2331.603
SAWED /SEALED JOINT
LIN FT
$1.85
2200
2000
0
$3,700.00
34
2350.501
TYPE LV 4 WEARING COURSE MIXTURE (B)
TON
$58.00
2245
1730.14
0
$100,348.12
35
2350.502
TYPE LV 3 NON WEARING COURSE MIXTURE (B)
TON
$58.50
1010
948.11
0
$55,464.44
.36
2350.503
TYPE LV WEARING COURSE MIXTURE FOR DRIVEWAYS
SQ YD
$12.88
600
643.6
0
$8,289.57
37
2357.502
BITUMINOUS MATERIAL FOR TACK COAT
GALLON
$1.91
1445
825
0
$1,575.75
-38 .2411.618
MODULAR BLOCK RETAINING WALL
SQ FT
$30.90
120
175
0
$5,407.50
39
2504.602
ADJUST GATE VALVE AND BOX
EACH
$180.27
8
6
0
$1,081.62
40
2506.522
ADJUST FRAME & RING CASTING ( SANITARY)
EACH
$257.50
10
10
0
$2,575.00
41
2506.522
ADJUST FRAME & RING CASTING ( STORM)
EACH
$257.50
2
0
0
$0.00
42
2511.501
RANDOM RIPRAP CLASS III
CU YD
$72.10
25
40.9
0
$2,948.89
43
2531.501 "CONCRETE
CURB & GUTTER DESIGN B618
LIN FT
$8.60
5225
5194.5
0
$44,672.70
44
2531.507
6" CONCRETE DRIVEWAY PAVEMENT
SQ YD
$37.08
445
350
0
$12,978.00
45
2531.603
7" CONCRETE VALLEY GUTTER
LIN FT
$20.60
65
102
0 "
$2,101.20
46
2531.603
CONCRETE CURB & GUTTER, SURMOUNTABLE
LIN FT
$14.42
250
259
0
$3,734.78
47
2531.603
CONCRETE RIBBON CURB
LIN FT
$12.88
115
102.5
0
$1,320.20
48
2540.602 -MAIL
BOX (TEMPORARY)
EACH
$8.24
32
28
0
$230.72
49
2563.601 .TRAFFIC
CONTROL
LUMP SUM
$1,004.25
1
1
0
$1,004.25
50
2564.531
SIGN PANELS TYPE C
SQ FT
$29.87
15
15.25
0
$455.52
Page 2
Item
No.
Item
Description
Units
Unit Price
Contract
Quantity
Quantity to
Date
Current
Quantity
Amount to
Date
51
2564.602
SALVAGE AND REINSTALL SIGN
EACH
$51.50
16
8
0
$412.00
52
2571.501
CONIFEROUS TREE 8' HT B &B
.TREE
$437.75
4
0
0
$0.00
53
2571.502
DECIDUOUS TREE 2.5" CAL B &B
TREE
$463.50
4
0
0
$0.00
54
2571.507
PERENNIAL - #1 POT
PLANT
$14.42
180
0
0
$0.00
55
2573.502
SILT FENCE, TYPE HEAVY DUTY
LIN FT
$1.34
850
547
0
$732.98
56
2573.530
STORM DRAIN INLET PROTECTION
EACH
$92.70
24
` 11
0
$1,019.70
57
2573.602
TEMPORARY ROCK CONSTRUCTION ENTRANCE
EACH
$515.00
2
2
0
$1,030.00
58
2573.603
BIOROLL
LIN FT
$6.18
50
` 175
0
$1,081.50
59
2575.502
SEED MIXTURE 310
POUND
$20.60
30
45
0
$927.00
60
2575.505
SODDING TYPE LAWN
SQ YD
$2.21
6100
8888.7
62
$19,644.03
61
2575.523
EROSION CONTROL BLANKETS CATEGORY 3
SQ YD
$0.98
1500
110
0
$107.80
62
2575.550
PLANT BEDDING MATERIAL
CU YD
$25.75
150
190
0
$4,892.50
63
2575.604
MULCH MATERIAL TYPE 6
SQ YD
$3.09
40
0
0
$0.00
Totals For Section Schedule A - Street Improvements:
$483,306.98
Schedule B - Storm Drainage Improvements
64
2104.521
SALVAGE PIPE CULVERT
LIN FT
$10.30
20
0
0
$0.00
65
2104.523
SALVAGE CONCRETE APRON
EACH
$154.52
1
0
0
$0.00
66
2501.515
18" RC PIPE APRON WITH TRASH GUARD
EACH
$732.93
2
2
0
$1,465.86
67
2501.515
27" RC PIPE APRON WITH TRASH GUARD
EACH
$1,205.67
2
2
0
$2,411.34
68
2501.571
INSTALL PIPE CULVERT
LIN FT
$18.13
20
0
0
$0.00
69
2501.573
INSTALL CONCRETE APRON
EACH
$257.50
1
0
0
$0.00
70
2502.521
4" PVC PIPE DRAIN
LIN FT
$13.99
250
10
0
$139.90
71
2502.541
6" PERF PE PIPE DRAIN
LIN FT
$6.90
2500
2200
0
$15,180.00
72
2502.601
6" PVC PIPE DRAIN CLEANOUT
EACH
$255.65
5
4
0
$1,022.60
73
2503.541
15" RC PIPE SEWER DESIGN 3006 CLASS V
LIN FT
$27.96
390
353
0
$9,869.88
74
2503.541
18" RC PIPE SEWER DESIGN 3006 CLASS III
LIN FT
$31.37
35
35
0
$1,097.95
75
2503.541
21" RC PIPE SEWER DESIGN 3006 CLASS III
LIN FT
$30.90
170
170
0
$5,253.00
76
2503.541
27" RC PIPE SEWER DESIGN 3006 CLASS III
LIN FT
$42.89
• 40
40
0
$1,715.60
77
2503.602
CONNECT TO EXISTING STORM SEWER
EACH
$257.50
3
0
0
: $0.00
78
2503.602
CONNECT INTO EXISTING DRAINAGE STRUCTURE
EACH
$412.00
1
1
0
$412.00
79
2506.501
CONSTRUCT DRAINAGE STRUCTURE DESIGN 48 -4020
LIN FT
$474.83
32
39.88
0
$18,936.22
80
2506.501
CONSTRUCT DRAINAGE STRUCTURE DESIGN 60 -4020
LIN FT
$290.23
7
8.7
0
$2,525.00
81
2506.502
CONSTRUCT DRAINAGE STRUCTURE DES SPECIAL (2'X3' CB)
EACH
$555.25
6
5
0
$2,776.25
82
2506.516
CASTING ASSEMBLY (STORM)
EACH
$537.20
10
11
0
$5,909.20
Totals For Section Schedule B - Storm Drainage Improvements:
$68,714.80
Schedule C - Water Main Improvements
83
2504.601
TEMPORARY WATER SERVICE
LUMP SUM
$3,090.00
1
1
0
$3,090.00
84
2504.602
CONNECT TO EXISTING WATER MAIN
EACH
$866.51
8
7
0
$6,065.57
85
2504.602
1" CORPORATION STOP
EACH
$193.71
14
14
0
$2,711.94
86
2504.602
6" GATE VALVE AND BOX
EACH
$954.58
7
7
0
$6,682.06
87
2504.602
12" GATE VALVE AND BOX
EACH
$2,247.09
2
3
0
$6,741.27
88
2504.602
12 "X12" WET TAP
EACH
$4,838.95
1
0
0
$0.00
89
2504.602
1" CURB STOP & BOX
EACH
$215.94
14
13
0
$2,807.22
90
2504.602
HYDRANT ASSEMBLY
EACH
$2,563.73
7
6
0
$15,382.38
91
2504.602
6" GATE VALVE BOX
EACH
$289.02
1 -
4
0
$1,156.08
92
2504.603
1" TYPE K COPPER PIPE
LIN FT
$20.59
450
587
0
$12,086.33
93
2504.603
6" WATER MAIN -DUCT IRON CL 52
LIN FT
$35.94
140
148.5
0
$5,337.09
94
2504.603
6" WATER MAIN -PVC C900
LIN FT
$14.71
540
565
0
$8,311.15
95
2504.603
12" WATER MAIN -PVC C900
LIN FT
$26.52
480 !
473
0
$12,543.96
96
2504.603
HYDRANT EXTENSION
LIN FT
$623.97
7
2
0
$1,247.94
Page 3
Item
No.
Item
Description
Units
Unit Price
Contract
Quantity
Quantity
to Date
Current
Quantity
.Amount to
Date
97
2504.604
4" POLYSTYRENE INSULATION
SQ YD
$29.57
40
22.4
0
$662.37
98
2504.608
DUCTILE IRON FITTINGS
POUND
$2.41
3500
3397
0
$8,186.77
Totals For Section Schedule C - Water Main Improvements:
$93,012.13
Schedule D - Sanitary Sewer Improvements
99
2503.601
SANITARY SEWER BYPASS PUMPING
LUMP SUM
$0.01
1
1
0
$0.01
100
2503.602
CONNECT TO EXISTING SANITARY SEWER
EACH
$530.45
15
11
0
$5,834.95
101
2503.602
CONNECT TO EXISTING MANHOLES (SAN)
EACH
$1,030.00
5
4
0
$4,120.00
- 102
2503.602
CONNECT TO EXISTING SANITARY SEWER SERVICE
EACH
$168.34
23
17
- 0
$2,861.78
103
2503.602
8 "X4" PVC WYE
EACH
$211.52
23
17
0
$3,595.84
104
2503.603
4" PVC PIPE SEWER - SDR 26
LIN FT
$16.39
250
121
0
$1,983.19
105
2503.603
TELEVISE SANITARY SEWER
-LIN FT
$1.03
3000
2474
0
$2,548.22
106
2503.603
8" PVC PIPE SEWER - SDR 35
LIN FT
$24.19
1405
1501
0
$36,309.19
107
- 2506.511
RECONSTRUCT SANITARY MANHOLES
LIN FT
$200.73
30
33.4
, 0
$6,704.38
108
2506.516
CASTING ASSEMBLY (SANITARY)
EACH
$631.66
13
11
0
$6,948.26
109
-2506.602
CHIMNEY SEAL (EXTERNAL)
EACH
$298.44
23
21
0
$6,267.24
110
2506.603
CONST 48" DIA SAN SEWER MANHOLE
LIN FT
$149.65
46
44.39
0
$6,642.96
Totals For Section Schedule D - Sanitary Sewer Improvements:
$83,816.02
Change Order 1
111
2021.501
MOBILIZATION
LUMP SUM
($28,500.00)
0.11.
0
0
$0.00
112
2104.501
REMOVE SEWER PIPE (SANITARY)
LIN FT
($2.06)
80
0
0
$0.00
113
2104.501
REMOVE SANITARY SERVICE PIPE
LIN FT
($2.06)
60
0
0
$0.00
114
2104.501
REMOVE CONCRETE CURB AND GUTTER
-LIN FT
($1.65)
185
0
0
$0.00
115
2104.505
REMOVE BITUMINOUS PAVEMENT
SQ YD
($1.03)
200
0
0
$0.00
116
2104.509
REMOVE STRUCTURE (STORM)
EACH
($309.00)
1
0
0
$0.00
117
2104.513
SAWING BITUMINOUS PAVEMENT (FULL DEPTH)
LIN FT
($1.29)
150
0
0
$0.00
118
2104.602
SALVAGE AND REINSTALL MAIL BOX
EACH
($56.65)
2
0
0
$0.00
119
2105.507
SUBGRADE EXCAVATION (EV)
CU YD
($9.27)
50
0
0
$0.00
120
2105.522
SELECT GRANULAR BORROW (CV)
CU YD
($9.27)
50
0
0
$0.00
121
2105.525
TOPSOIL BORROW (LV)
CU YD
($9.27)
15
0
0
$0.00
122
2211.501
AGGREGATE BASE CLASS 5
TON
($9.50)
70
0
0
$0.00
123
2232.501
MILL BITUMINOUS SURFACE
SQ YD
($0.90)
3500
0
0
$0.00
124 -
2350.501
TYPE LV 4 WEARING COURSE MIXTURE (B)
TON
($58.00) -
385
0
0
$0.00
125 ;
2350.502
TYPE LV 3 NON WEARING COURSE MIXTURE (B)
TON
($58.50)
25
0
0
$0.00
126
2357.502
BITUMINOUS MATERIAL FOR TACK COAT
GALLON
($1.91)
320
0
0
$0.00
127
2506.522
ADJUST FRAME & RING CASTING ( SANITARY)
EACH
($257.50) -
2
0
0
$0.00
128 :2506.522
ADJUST FRAME & RING CASTING ( STORM)
EACH
($257.50)
2
0
0
$0.00
129
2531.603
CONCRETE CURB & GUTTER, SURMOUNTABLE
LIN FT
($14.42)
185
0
0
$0.00
130
2540.602
MAIL BOX (TEMPORARY)
EACH
($8.24)
2
0
0
$0.00
131
2563.601
TRAFFIC CONTROL
LUMP SUM
($1,004.25)
0.1
0
0
$0.00
132
2573.530
STORM DRAIN INLET PROTECTION
EACH
($92.70)
4
0
0
$0.00
133
2575.505
SODDING TYPE LAWN
SQ YD
($2.21)
100
0
0
$0.00
134
2104.521
SALVAGE PIPE CULVERT
LIN FT
($10.30)
20
0
0
$0.00
135
2104.523
SALVAGE CONCRETE APRON
EACH
($154.52)
1 -
0
0
$0.00
136
2501.571
INSTALL PIPE CULVERT
LIN FT
($18.13)
20
0 .
0
$0.00
137
2501.573
INSTALL CONCRETE APRON
EACH
($257.50)
1
0
0
$0.00
138
2503.602
CONNECT TO EXISTING STORM SEWER
EACH
r
($257.50)
2
0
0
$0.00
139 '2506.502
CONSTRUCT DRAINAGE STRUCTURE DES SPECIAL (2'X3' CB)
EACH
($555.25)
1
0
0
$0.00
140
2503.602
CONNECT TO EXISTING SANITARY SEWER
EACH
($530.45)
2
0
0
$0.00
141
2503.602
CONNECT TO EXISTING MANHOLES (SAN)
EACH
($1,030.00)
2
0
0 .
$0.00
142
2503.602
CONNECT TO EXISTING SANITARY SEWER SERVICE
EACH
($168.34)
2
0
0
$0.00
Page 4
Itern No.
Item
Description
Units
Unit Price
Contract Quantity
Quantity to Date
Current Quantity
Amount to Date
143
2503.602
8 "X4" PVC WYE
EACH
($211.52)
2
0
- 0
$0.00
144
2503.603
4" PVC PIPE SEWER - SDR 26
LIN FT
($16.39)
20
0
0
$0.00
145
2503.603
TELEVISE SANITARY SEWER
LIN FT
($1.03)
200
0
0
$0.00
146
2503.603
8" PVC PIPE SEWER - SDR 35
LIN FT
($24.19)
80
0
0
$0.00
147
2506.516
CASTING ASSEMBLY (SANITARY)
EACH
($631.66)
1
0
0
$0.00
148
2506.602
CHIMNEY SEAL (EXTERNAL)
EACH
($298.44)
3
0
0
$0.00
Totals For Change Order 1:
$0.00
Change Order 2
149
2105.507
SUBGRADE EXCAVATION (EV)
CU YD
$9.27
265
265
0
$2,456.55
150
2105.604
GEOTEXTILE FABRIC TYPE V
SQ YD
$1.55
1866
1866
0
$2,892.30
151
2211.501
AGGREGATE BASE CLASS 5
TON
$9.50
265
265
0
$2,517.50
Totals For Change Order 2:
$7,866.35
Change Order 3
152
2105.601
EXCAVATION SPECIAL 1
LUMP SUM
$6,500.00
1
1
0
$6,500.00
153
2105.604
GEOTEXTILE FABRIC TYPE V
SQ YD
$1.55
3334
3334
0
$5,167.70
154
2211.501
AGGREGATE BASE CLASS 5
TON
$9.50
375
375.
0
$3,562.50
155
94715
5% PRIME CONTRACTOR MARKUP
LUMP SUM
$761.51
1
1
0
$761.51
Totals For Change Order 3:
$15,991.71
Project Totals:
$752,707.99
Page 5
Project Payment Status
Owner: City of Arden Hills
Client Project No.:
Client Contract No.:
Project No.: 01771 -02
Contractor: T. A. Schifsky & Sons, Inc.
Contract Changes
No.
Type
Date
Description
Amount
CO1
Change
Order
5/10/2010
Modified quantities as part of project award.
p p
($48,169.08)
($
CO2
Change
Order
7/9/2010
Modify the road section on Valentine CT to include geotextile fabric, 4"
additional depth of Subgrade Excavation, and 4" additional depth of aggregate
base material.
$7,866.35
CO3
Change
Order
8/4/2010
Modify the road section of Valentine Avenue between Valentine Crest Road
and Snelling Avenue to 10" of Class 5 Aggregate Base and Geotextile Type 5
Fabric underlayment.
$15,991.71
Change Order Totals:
($24,311.02)
Payment Summary
No.
From
Date
To Date
Payment
Total
Payment
Retainage
Per
Payment
Total
Retainage
Total
Payment +
Retainage
Work
Certified Per
Payment
Total Work
Certified
1
5/24/2010
6/20/2010
$102,540.97
$102,540.97
$5,396.89
$5,396.89
$107,937.86
$107,937.86
$107,937.86
2
6/21/2010
7/15/2010
$246,418.81
$348,959.78
$12,969.41
$18,366.30
$367,326.08
$259,388.22
$367,326.08
3
7/16/2010
8/13/2010
$163,538.42
$512,498.20
$8,607.29
$26,973.59
$539,471.79
$172,145.71
$539,471.79
4
8/14/2010
10/1 /2010
$181,851.80
$694,350.00
$9,571.15
$36,544.74
$730,894.74
$191,422.95
$730,894.74
5
10/2/2010
2/4/2011
$47,850.17
$742,200.17
($26,544.74)
$10,000.00
$752,200.17
$21,305.43
$752,200.17
FINAL
FINAL &
2/5/2011
9/27/2011
$10, 507.82
$752,707.99
$10 000.00.
( )
$ 0.00
$ 752 707.99
$507.82
$ 8
7
$ 52,707.99
Payment Totals:
$752,707.99
$0.00
$752,707.99
_$752,707.99
Project Summary
Material On Hand:
Total Payment to Date:
Total Retainage:
Total Amount Earned:
$0.00
$752,707.99
$0.00
$752,707.99
Original Contract:
Contract Changes:
Revised Contract:
$779,799.67
($24,311.02)
$755,488.65
Page 6
AIWNHILLs
CITY OF ARDEN HILLS
COUNTY OF RAMSEY
STATE OF MINNESOTA
RESOLUTION NO. 2011-049
A RESOLUTION ACCEPTING WORK COMPLETED AND AUTHORIZING FINAL
PAYMENT FOR THE 2010 PAVEMENT MANAGEMENT PROGRAM
WHEREAS, pursuant to a written contract signed with the City on May 10, 2010 for the
2010 Pavement Management Program, T. A. Schifsky & Sons, Inc., of North Saint Paul,
Minnesota, has satisfactorily completed the improvements associated in accordance with such
contract to the following streets;
Valentine Crest Road, from Valentine Avenue to cul de sac,
Valentine Avenue, from Lake Valentine Road to Old Highway 10,
Valentine Court, from Valentine Avenue to cul de sac,
Katie Lane, from Cleveland Avenue to 1272 feet south,
Katie Court, from Katie Lane to cul de sac,
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF ARDEN HILLS,
MINNESOTA: That the work completed under said contract is hereby accepted and approved;
and
BE IT FURTHER RESOLVED: That the City Administrator is hereby directed to issue a
proper order for the final payment of such contract, taking the contractor's receipt in full; and
BE IT FURTHER RESOLVED: That the two year warranty period as specified in the contract
shall commence on October 10, 2011.
ADOPTED BY THE CITY COUNCIL OF THE CITY OF ARDEN HILLS THIS
10th DAY OF OCTOBER, 2011.
David Grant, Mayor
ATTEST:
Patrick Klaers, City Administrator