Prepared By: Terry Maurer, Public Works
Director Council Meeting Date: January 30, 2012
Adopt Resolution 2012-004 Awarding the Reconstruction of Lift Station #13 to
Minger Construction in the Amount of $194,250
Budgeted Amount: Actual Amount: Funding Source:
$385,000 $194,250 - Construction Sanitary Sewer Utility Fund
$28,100 - En ineerin
Recommendation:
Staff recommends that Council adopt Resolution 2012-004 Awarding the Reconstruction of Lift Station
#13 to Minger Construction of Chanhassen, Minnesota, in the amount of $194,250.
..................................... . .
. ..................._...............................:......._............................................................._.............:.............................................:.......:......._............:...............................................................................................................:..............
Supportin� Documents:
L Memorandum dated January 30, 2012, from Terry Maurer, Public Works Director.
2. Page 62 of the Capital Improvement Plan (CIP).
3. Bid evaluation from Bolton and Menk.
4. Bid tabulations taken on December 6, 2011.
5. Resolution 2012-004.
�
EN HILLS
MEMORANDUM
DATE: January 30, 2012
TO: Honorable Mayor and City Councilmembers
Patrick HIaers, City Administrator
FROM: Ter Maurer, Public Works Director �
rY
SUBJECT: Lift Station #13 Reconstruction Bids
Background
The 2011 Capital Improvement Plan (CIP) included a sanitary sewer item to rebuild lift
stations 11 and 13. Lift Station #11 is located at 1861 Highway 96 which is the main
entrance to the manufactured home park. That lift station was dropped from the project
because of the US 10/Hwy 96 Grade Separation Project planned for 2013 which may
affect the existing lift station. Lift Station #13 is located at the intersection of Karth Lake
Drive and Pleasant Drive. The CIP item, a copy of which is attached, prograinmed
$385,000 for the reconstruction of both lift stations. .
Seth Peterson of Bolton and Menk was hired to provide engineering services for the
reconstruction. The project was bid on Tuesday, December 6, 2011. The bid also
included four alternate items for various upgrades at lift stations 2, 5, 7 and 8. After the
bid opening the alternative bid items were evaluated and it was decided that they were
too costly and there was a more cost-effective method of getting this work done so only
the base bids are being considered for award. There were a total of eight bids received.
The following table contains the bidder and their base bid for the reconstruction of lift
station # 13.
City Council Meeting
P:�Admin\Council�Agendas & Packet Information�2012\01-30-12 Reg Mtg�Packet Information\1-30-12LiftStationl3Bids.doc
Page 1 of 2
The lowest responsive/responsible bidder is Minger Construction from Chanhassen in the
amount of $194,250. Attached is a memo from Project Engineer Seth Peterson
recommending award to Minger Construction. I have also worked with Pat Minger at
another City and always found his work to be excellent.
Council Action Requested
It is recommended that the City Council adopt attached Resolution 2012-004 Awarding
the Reconstruction of Lift Station #13 to Minger Construction of Chanhassen, Minnesota,
in the amount of $194,250.
City Council Meeting
P:�Admin\Council�Agendas & Packet Information�2012\01-30-12 Reg Mtg�Packet Information\1-30-12LiftStationl3Bids.doc
Page 2 of 2
����nprovement Plan
.�ty of Ar�� �s� M��esota
roject # t0-Sew-4�3
•roject Name Reconstruct Lift Stations 11 and 13
Department Sanitazy Se�ver D��aM�ent
Coataci Public Works Duec�or
Priority n�a
-ry� Itnprovement
UseCu1 Life
Categan U�tt��' �P�O��ements
2011 thru ZQ15
Z'otai Project Cost: $385,OOU
�gCf��i1�II
?roject to replace lift staEions �� f �g ut be nstaf ed} The�ne � pumpi s and p�eDrwould be compatible w"►it► th other�l4 lift stations focateda�
v��, Pumps and electricai panels o
.hroughout the City.
EngineeringlDesign alreaciy eompleted, ho�vever, a review should be completed to ensure no design modifications are needed.
- 201i -
L�ft Station # t 1 mav be impacted bv �.h�- HiQhwav i0/County Rd 96
scheduled for
JUSiil�c�uavu
The lift stations are over 40 years otd and in need of rep[acement_
2012 2013 2Q14 2015 �o�d'
Expenditures 2011 yp,ppp
Planning/Design 10.000 375,000
Cons4ruction/Maintenance 375,OOd
385,000
Total 385=000
2012 2013 2014 2015 Total
Funding Sources 20t 1 38�,ppp
Sanitary Sewer Utifity Fund 385,000 3�,000
Total 385,000
Budget Impact/Other j -
Pump xepair costs should decrease as a result of this pro�ect.
Wednesday. November F0, 2010
Produced Using ihe Plan-It Cap�tal Plamm�$ Solh�'a�e ( 2
o��N � ��z
m �
� `t:
� I n��C'!] ��'C 1��C ��
BO L�TON 8�. M� N K, I N C�
Consuiting Engineers & Surveyors
12224 Nicollet Avenue • Burnsville, MN 55337
Phone (952) 890-0509 • Fax (952) 890-8065
www.bolton-menk.com
BID EVALUATION FOR
LIFT STATION IMPROVEMENTS
CITY OF ARDEN HILLS, MINNESOTA
Eight (8) bids were received for the construction of the Lift Station Improvements project. The base bid
for this project is for removal and replacement of lift station 13. There were four (4) add alternate items
for pump and electrical work at lift stations 2, 5, 7 and 8. The base bid numbers for lift station 13 ranged
from $194,250 to $366,500 as shown in the attached Bid Tabulation. The Engineer's estimate for the
project was $270,000. The apparent low, responsive and responsible bidder was Minger Construction,
Inc. of Chanhassen, Minnesota.
Five of the eight bidders were below the engineer's estimate and three were above the estimate. The low
bidder is approJcimately 28 percent below the engineer's estimate. There were 4 add alternate items and
each bidder provided a cost for each add item. Award of the project is based on the base bid price for lift
station 13 and any or all add items could be accepted or rejected from the low base bidder. Since Minger
Construction is the low base bidder, their add alternate items can be evaluated. Based on the costs of the
add alternate items it is our recommendation that the City reject all of the add alternate items and
reconsider these at a some future time.
Based on the base bid numbers the bid documents did not contain any wording or ambiguities so as to
force the Contractors to build in additional contingencies. Based on the relative tight bidding and very
competitive bids we feel the speciiications were not restrictive to force a non-competitive bid situation.
Therefore, we feel that the bids received were competitive and responsive and re-bidding of the project
would not provide any cost savings.
Minger Construction, Inc., out of Chanhassen, Minnesota, is a reputable contractor that has previous
experience with projects similar in scope and size. Bolton & Menk, Inc. has worked with Minger
Construction, Inc. on multiple projects in the past with good success. Based on their experience and
qualifications, along with their acceptable bid price, we recommend that the City of Arden Hills consider
awarding the Lift Station Improvements base bid with no add alternates to Minger Construction, Inc. in
the amount of $194,250.
Respectfully submitted,
BOLTON & MENK, INC.
�c.'������
Seth A. Peterson, P.E.
Project Manager
\�netrosouthl\G�ARDH�M21103347\I_Correspondence�Bid Eval.doc
DESIGNING FOR A BEITER TOMORROW
Bolton & Menk is an equal opportunity employer
BID TABULATION
Lift Station Improvements
City of Arden Hills, MN
BMI Project No. M21.103347
Bids Taken: Tuesday, December 6, 2011
Time: 10:00 a.m.
Addendum(s): #1-11/30/2011
BIDDERS TOTAL PROJECT BID PRICE ADD ITEMS BID BOND ADD.
A = $ 73,955
1. Minger Construction, Inc. B=$ 88,900
2471 Galpin Court Ste 110 $194,250 Y Y
Chanhassen, MN 55317 C=$ 17,925
D = $113,320
A = $ 87,360
2. Penn Contracting, Inc. B—$100,800
13025 Central Avenue NE $223,360 Y Y
Ste 200 C = $ 17,250
Blaine, MN 55434
D = $157,200
A=$71,300
3. Magney Construction B=$ 83,500
1401 Park Road $225,800 Y Y
Chanhassen, MN 55317 C=$ 19,100
D = $103,200
A = $100,000
4. CC5 Contracting, Inc. B=$105,000
2090 Pike Lake Drive #2 $250,000 Y Y
New Brighton, MN 55112 C=$ 20,000
D = $146,000
A = $ 76,000
?
5. C. W. Houle, Inc. B=$ 88,000
1300 West County Road 1 $251,000 Y Y
Shoreview, MN 55126 C=$ 26,000
D = $123,000
A = $135,000
6. Lametti & Sons, Inc. B=$155,000
16028 Forest Blvd. North $293,700 Y Y
Hugo, MN 55038 C=$ 32,700
D = $243,700
A = $ 85,000
7. PCiRoads, LLC B=$ 87,000
14123 — 42"d Street NE $339,000 Y Y
St. Michael, MN 55376 C=$ 19,000
D = $109,000
A = $ 76,000
8. Geislinger and Sons B=$ 80,000
511 Central Avenue South $366,500 Y Y
Watkins, MN 55389 C=$ 18,000
D = $120,000
Solton & Menk, Inc.
CONSULTING ENGINEERS & SURVEYORS
Mankato - Fairmont - Sleepy Eye - Burnsville - Willmar - Chaska — Ramsey — Maplewood - Brainerd, MN
Ames, IA
�
�,R .�EN�HII,LS
CITY OF ARDEN HILLS
COUNTY OF RAMSEY
STATE OF MINNESOTA
RESOLUTION NO. 2012-004
A RESOLUTION AWARDING THE LIFT STATION #13 RECONSTRUCTION
PROJECT
WHEREAS, pursuant to advertisement for bids for the improvement of the Lift
Station #13 Reconstruction Project, bids were received on Tuesday, December 6, 2011, at 10:00
a.m., opened, and tabulated according to the law, and the following bids were received
complying with the advertisement:
AND WHEREAS, it appears that Minger Construction, Inc., of Chanhassen, Minnesota, is
the lowest responsible bidder at the tabulated price of $194,250.00;
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF ARDEN
HILLS, MINNESOTA:
1. The Mayor and City Administrator are hereby authorized and directed to enter into a
contract with Minger Construction, Inc., of Chanhassen, Minnesota, for $194,250.00 in
the name of the City of Arden Hills for the above improvements according to the plans
and specifications thereof heretofore approved by the City Council and on file in the
office of the City Administrator.
2. The City Administrator is hereby authorized and directed to return forthwith to all
bidders the deposits made with their bids, except that the deposits of the successful bidder
and the next lowest bidder shall be retained until contracts have been signed.
ADOPTED BY THE CITY COUNCIL OF THE CITY OF ARDEN HILLS THIS 30tn
DAY OF JANUARY, 2012.
David Grant, Mayor
ATTEST:
Patrick Klaers, City Administrator