HomeMy WebLinkAbout04-27-15-WS It
,- IQEN HILLS
Approved: June 8, 2015
CITY OF ARDEN HILLS, MINNESOTA
SPECIAL CITY COUNCIL WORK SESSION
APRIL 27, 2015
5:30 P.M. - ARDEN HILLS CITY COUNCIL CHAMBERS
CALL TO ORDER/ROLL CALL
Pursuant to due call and notice thereof, Mayor Grant called to order the special City
Council work session at 5:35 p.m.
Present: Mayor David Grant; Councilmembers Brenda Holden (arrived at 5:42
p.m.), Fran Holmes (arrived at 5:43 p.m.), Dave McClung, and Robert
Woodburn
Absent: None
Also present: City Administrator Patrick Klaers; Director of Finance and Administrative
Services Sue Iverson; Public Works Director Terry Maurer; Assistant City Engineer John
Anderson; Community Development Director Jill Hutmacher; City Planner Ryan Streff;
Associate Planner Matthew Bachler; Finance Analyst Dave Perrault; and City Clerk Amy
Dietl
1. AGENDA ITEMS
A. Rice Creek Commons (TCAAP)
Community Development Director Hutmacher stated that at the April 20, 2015, City Council
work session, staff believes that the City Council provided the following direction:
1. Adjust the density in the NB-1 Subdistrict to allow lot sizes of approximately 85 to 90 feet
wide by 150 feet deep;
2. Limit multi-family to 450 units and adjust acreage accordingly;
3. Combine the NT-1 and NT-2 Subdistricts with an allowed density range of 6 to 12 units
per acre;
4. Adopt the Town Center layout for Fit Test Option#2 which expands the retail area and the
green space along the pedestrian corridor, but adjust acreages and densities for the Town
Center and Neighborhood Transition Districts as noted above; and
ARDEN HILLS SPECIAL CITY COUNCIL WORK SESSION-APRIL 27, 2015 2
5. Allow the location of subdistricts in the Hill and Creek Neighborhoods to be moved
provided that it occurs at the time of plat application for the entire neighborhood and
provided that the proportional size of subdistricts do not change.
Community Development Director Hutmacher explained that the meeting objectives were as
follows:
1. Confirm City Council consensus direction on the results of the April 20, 2015, City
Council work session meeting.
2. Establish an approval schedule.
Community Development Director Hutmacher reported that staff provided a graphic that
compares the draft and revised land use plans with estimates of actual built unit yield. In most
cases, it is difficult to achieve maximum allowable units in an actual development plan due to
irregularly shaped parcels and the needs of roads, parks, and storm water infrastructure. The
revised land use plan chart reflects the City Council direction previously discussed.
Lot Sizes in the NB-1 Subdistrict - Michael Lamb, Kimley-Horn, provided information on lot
sizes in the NB-1 Subdistrict. A gross density of 2.75 units per acre would allow lot sizes of 90
feet by 151 feet, or 85 feet by 161 feet.
Limit of 450 Multi-Family Units - The City Council has heard from multi-family and senior
residential developers that those housing products are typically built at a density of approximately
40 units per acre. If multi-family units are limited to no more than 450, the acreage for multi-
family development should be reduced from 17 to 11.25 acres.
Adjustments to Town Center - Fit Test Option#2 adjusted the layout of the Town Center to allow
a larger green space along the pedestrian corridor and a larger retail area to allow for parking
required by a commercial mixed-use building. The Council supported this layout which removes
4.9 acres of residential development area. Of the remaining 49.6 acres for residential
development, staff proposes to allocate 11.25 acres for multi-family and 38.35 acres for
Neighborhood Transition.
Draft Approval Schedule - In order for private development to begin in 2017, the Spine Road, the
County Road H interchange, and trunk utilities need to be constructed in 2016. In order for that to
happen, final design work needs to begin by early summer. The City should not proceed to final
design of utilities without some sort of assessment agreement with Ramsey County, and Ramsey
County is not able to enter into an assessment agreement without an estimate of revenue from land
sales and fees. Much of the work that remains to be done rests on the completion of the TCAAP
Redevelopment Code (TRC).
Community Development Director Hutmacher stated that the following draft approval
schedule allows infrastructure design and construction to continue as planned.
Council provides direction on changes to TRC Work Session, May 11
Preliminary Approval of TRC Regular Meeting, May 26
Discussion of Comp Plan Amendment Work Sessions, June 8 & 15
ARDEN HILLS SPECIAL CITY COUNCIL WORK SESSION—APRIL 27, 2015 3
Public Hearings Planning Commission, July 8
Authorization to Submit to Met Council Regular Meeting, July 13
Final approval Regular Meeting, Nov 30
Community Development Director Hutmacher noted the following on the draft approval
schedule:
1. The Comprehensive Plan Amendment (CPA) cannot be completed until the TRC has been
at least preliminarily approved. Any changes to land uses or densities after the preliminary
TRC approval will require duplicative work on the CPA.
2. Any changes to the draft CPA should be made prior to public hearing notices being posted
which would occur on approximately June 24 according to the draft schedule above.
Mayor Grant thanked staff for the recap and asked the Council for comments. He inquired if the
Council could support the May 26th approval date.
Community Development Director Hutmacher explained that the proposed approval schedule
hinged on the May 26th approval date.
Councilmember Woodburn asked why there was so much time between the authorization to
submit to the Met Council and final approval of the TRC.
Community Development Director Hutmacher commented that there was a 60-day required
review process for adjacent municipalities, along with a 60-day review for Met Council. This
equated to 120 days between when the Council approves the submittal of the document to the Met
Council and when the Met Council can grant approval.
Further discussion ensued regarding the approval process.
Mayor Grant provided comment on the approval process and noted that the Fit Test completed
by the County created delays.
Councilmember Holden explained that it was going to be difficult for her to make 5:30 p.m.
work sessions in June. She stated that she would not be able to attend the June 81h work session.
Mayor Grant asked what Council action would be required on June 8th and 15th
Community Development Director Hutmacher reported that the Council would be discussing a
Comprehensive Plan Amendment which would require consensus and direction to staff, but no
Council action is required on June 8th or 15tH
Councilmember Holden questioned how the Council would address comments at the Public
Hearing given the fact that it would be held after the TRC was granted preliminary approval.
Community Development Director Hutmacher stated that staff did not anticipate significant
changes as a result of the Public Hearing as the City has been holding public hearings at regular
City Council meetings on a monthly basis to allow for comments on the TRC.
ARDEN HILLS SPECIAL CITY COUNCIL WORK SESSION—APRIL 27, 2015- 4
Mayor Grant reviewed the May and June meeting schedule and explained that the important
meeting dates that would require four votes would be May 26th, July 13tH and November 30th.
Mayor Grant recessed the special City Council work session at 6:00 p.m.
Mayor Grant reconvened the special City Council work session at 6:45 p.m.
Mayor Grant questioned if the Council was available to attend a special work session to further
discuss the TRC.
Councilmember Holden was in favor of holding a special Saturday work session.
Mayor Grant asked if the Council was available to hold a special work session on Saturday, May
2nd He indicated that he would be available.
Councilmember McClung stated that he was not available on May 2nd
Councilmember Holden and Councilmember Holmes were both available.
Councilmember Woodburn was available.
Mayor Grant questioned what time the Council would like to meet.
The Council was in favor of meeting on Saturday, May 2 n at 9:00 a.m.
City Administrator Klaers inquired what the Council planned to discuss at this meeting, in order
for staff to be fully prepared.
Mayor Grant anticipated that the Council would further review and discuss the TRC based on
the comments made on April 20th
Community Development Director Hutmacher commented that she would not be available on
May 2nd
Mayor Grant stated that staff could be in attendance, but he wanted to have this be the final
discussion the Council had on the TRC. He requested that staff ask the County how they would
define a"good job".
Councilmember McClung wanted to better understand what level of flexibility was required in
order to achieve 1450 units within the TRC.
2. COUNCIL COMMENTS AND STAFF UPDATES
Councilmember Holden requested that in the future, the County provide their information to the
Council prior to meetings versus providing the Council with handouts at meetings.
ARDEN HILLS SPECIAL CITY COUNCIL WORK SESSION—APRIL 27, 2015 5
ADJOURN
Mayor Grant adjourned the special City Council work session at 6:54 p.m.
I
Amy Dietl David Grant
City Clerk Mayor
It'
-4 DEN HILLS
Request for Special City Council Work Session
A special meeting may be called by the Mayor or by any two Councilmembers.
Reason for meeting: 1. Rice Creek Commons (TCAAP)
Requested Date: 4/27/15
Requested time: 5:30 PM
Open meeting X Closed meeting
Signature of person(s) making request:
hm4 • 2�
4 / 22 15
Mayor or Council Member Date
Council Member Date
-This section to be completed by City staff-
Date meeting to be held: 4/27/15
Time of meeting: 5:30 PM
Location: City Hall
All necessary posting and notices have been completed.
Signature of City Jerk Date
City of Arden Hills + 1245 West Highway 96 * Arden Hills,MN 55112-5743
Phone 651-792-7800 * Fax 651-634-5137 * www.cityofardenhills.org