HomeMy WebLinkAbout04-27-15-WSAGENDA ITEMS
Rice Creek Commons - TCAAP
Community Development Staff
MEMO.PDF, ATTACHMENT.PDF
COUNCIL/STAFF COMMENTS
ADJOURN
Mayor:
David Grant
Councilmembers:
Brenda Holden
Fran Holmes
Dave McClung
Robert Woodburn
Special City Council
Work Session Agenda
April 27, 2015
5:30 p.m.
City Hall
Address:
1245 W Highway 96
Arden Hills MN 55112
Phone:
651 -792 -7800
Website :
www.cityofardenhills.org
City Vision
Arden Hills is a strong community that values its unique environmental setting, strong residential
neighborhoods, vital business community, well -maintained infrastructure, fiscal soundness, and our
long -standing tradition as a desirable City in which to live, work, and play.
CALL TO ORDER
1.
1.A.
Documents:
2.
Page 1 of 2
DATE: April 27, 2015
TO: Honorable Mayor and City Councilmembers
Patrick Klaers, City Administrator
FROM: Jill Hutmacher, Community Development Director
SUBJECT: Rice Creek Commons (TCAAP)
Summary
At the April 20, 2015, City Council work session, staff believes that the City Council provided
the following direction:
1. Adjust the density in the NB-1 Subdistrict to allow lot sizes of approximately 85 to 90
feet wide by 150 feet deep;
2. Limit multi-family to 450 units and adjust acreage accordingly;
3. Combine the NT-1 and NT-2 Subdistricts with an allowed density range of 6 to 12 units
per acre;
4. Adopt the Town Center layout for Fit Test Option #2 which expands the retail area and
the green space along the pedestrian corridor, but adjust acreages and densities for the
Town Center and Neighborhood Transition Districts as noted above; and
5. Allow the location of subdistricts in the Hill and Creek Neighborhoods to be moved
provided that it occurs at the time of plat application for the entire neighborhood and
provided that the proportional size of subdistricts do not change.
Meeting Objectives
1. Confirm City Council consensus direction on the results of the April 20, 2015, City
Council work session meeting.
2. Establish an approval schedule.
Discussion
The attached graphic compares the draft and revised land use plans with estimates of actual built
unit yield. In most cases, it is difficult to achieve maximum allowable units in an actual
development plan due to irregularly shaped parcels and the needs of roads, parks, and storm
water infrastructure. The revised land use plan chart reflects the City Council direction noted
above.
AGENDA ITEM – 1A
MEMORANDUM
Page 2 of 2
Lot Sizes in the NB-1 Subdistrict
Michael Lamb, Kimley-Horn, provided information on lot sizes in the NB-1 Subdistrict. A gross
density of 2.75 units per acre would allow lot sizes of 90 feet by 151 feet, or 85 feet by 161 feet.
Limit of 450 Multi-Family Units
The City Council has heard from multi-family and senior residential developers that those
housing products are typically built at a density of approximately 40 units per acre. If multi -
family units are limited to no more than 450, the acreage for multi-family development should be
reduced from 17 to 11.25 acres.
Adjustments to Town Center
Fit Test Option #2 adjusted the layout of the Town Center to allow a larger green space along the
pedestrian corridor and a larger retail area to allow for parking required by a commercial mixed-
use building. The Council supported this layout which removes 4.9 acres of residential
development area. Of the remaining 49.6 acres for residential development, the attached graphic
allocates 11.25 acres for multi-family and 38.35 acres for Neighborhood Transition.
Draft Approval Schedule
In order for private development to begin in 2017, the Spine Road, the County Road H
interchange, and trunk utilities need to be constructed in 2016. In order for that to happen, final
design work needs to begin by early summer. The City should not proceed to final design of
utilities without some sort of assessment agreement with Ramsey County, and Ramsey County is
not able to enter into an assessment agreement without an estimate of revenue from land sales
and fees. Much of the work that remains to be done rests on the completion of the TRC.
The following draft approval schedule allows infrastructure design and construction to continue
as planned.
Council provides direction on changes to TRC Work Session, May 11
Preliminary Approval of TRC Regular Meeting, May 26
Discussion of Comp Plan Amendment Work Sessions, June 8 & 15
Public Hearings Planning Commission, July 8
Approval contingent on Met Council Regular Meeting, July 13
Final approval Regular Meeting, Nov 30
Notes on draft approval schedule:
1. The Comprehensive Plan Amendment (CPA) cannot be completed until the TRC has
been at least preliminarily approved. Any changes to land uses or densities after the
preliminary TRC approval will require duplicative work on the CPA.
2. Any changes to the draft CPA should be made prior to public hearing notices being
posted which would occur approximately June 24 according to the draft schedule above.
Attachments
Comparison of Land Use Plans to Potential Residential Yield; April 27, 2015
Comparisons of Maximum Density Allowed by Land Use Plan with Potential Built Unit Yield
April 27, 2015
Maximum Density Built Unit Yield
Draft Land Use Plan Fit Test Option #1
January 20, 2015 March 30, 2015
Zone
Maximum Gross
Density Acreage
Maximum
Units Zone
Maximum
Gross Density Acreage
Maximum
Units
NB-1 2 25.1 50 NB-1 2 25.1 50
NB-2 4 11.0 44 NB-2 3.4 11.0 37
NB-3 6 5.4 32 NB-3 4.3 5.4 23
Subtotal 41.5 127 Subtotal 41.5 111
NB-1 2 14.6 29 NB-1 2 14.6 29
NB-2 4 23.5 94 NB-2 3.4 23.5 80
NB-3 6 24.1 145 NB-3 4.7 24.1 114
Subtotal 62.2 268 Subtotal 62.2 223
NT-1 9 15.0 135 NT-1 7.4 15.0 111
NT-2 12 22.5 270 NT-2 8.6 22.5 193
TC 40 17.0 680 TC 39.9 17.0 680
Subtotal 54.5 1085 Subtotal 54.5 984
Total 158.2 1479 Total 158.2 1318
Maximum Density
Revised Land Use Plan
April 20, 2015
Zone
Maximum Gross
Density Acreage
Maximum
Units
NB-1 2.75 25.10 69
NB-2 4 11.00 44
NB-3 6 5.40 32
Subtotal 41.50 145
NB-1 2.75 14.60 40
NB-2 4 23.50 94
NB-3 6 24.10 145
Subtotal 62.20 279
TC 40 11.25 450
Subtotal 49.60 910
Total 153.30 1334
Note: For the Revised Land Use Plan, the Fit Test Option #2 layout
was used which expands the retail space (1.3 acres) and the green
space along the pedestrian corridor (3.6 acres). The acreage for NT
and TC Districts were revised per Council direction on April 20, 2015.
Town Center
Hill
Creek
460
Creek
Hill
Town Center
NT 12 38.35
Creek
Hill
Town Center
Actual Unit Yield is 89% of
Maximum Units allowed in
Land Use Plan
Assuming a Built Unit Yield of 89%
to 95% of Maximum Units allowed
in the Land Use Plan, Actual Built
Unit Yield would be 1,187 to 1,267
units.