HomeMy WebLinkAbout10-18-17 JDA Agenda PacketAGENDA
Wednesday, October 18, 2017
5:30 p.m.
Arden Hills City Hall—Council Chambers
1. Roll Call
2. Approval of Agenda
3. Approval of Minutes
a. 9/20/2017 JDA Meeting
4. Public Inquiries/Informational
a. The intent of the Public Inquiries/Informational part of the agenda is to provide interested parties
with an opportunity to speak to the JDA about an issue or concern about a past or future agenda
item. The current agenda for tonight's meeting is structured to ensure that the JDA accomplishes
their business within that agenda. If there is a public hearing scheduled as an agenda item, the
public will be invited to speak to that agenda item. In addressing the JDA, please state your name
and address for the record, and a brief summary of the specific matter being addressed. To allow
adequate time for each person wishing to address the JDA, individuals should limit their
comments to three (3) minutes. Written documents may be distributed to the JDA prior to the
meeting, or as bench copies, to allow a more timely presentation.
5. Consent Agenda
6. Old Business
a. Master Developer Agreement Update
b. Amazon HQ2 submission
c. Optimization Study
7. Public Hearing
a. None
8. New Business
a. Green infrastructure study opportunity with Rice Creek Watershed
District
9. Communications – See attached memo.
10. Development Director Update – Verbal.
11. Administrative Director’s Report – Verbal.
12. Commissioner Updates
13. Adjournment
Joint Development Authority
TCAAP Redevelopment Project
Joint Development Authority
Monday, September 20, 2017
Arden Hills City Council Chambers
Minutes
5:30 pm
Present:
Joint Development Authority: Chair Jonathan Wicklund, Commissioner Blake Huffman,
Commissioner Dave McClung, Commissioner David Grant, Commissioner Rafael Ortega
Also present: Bill Joynes, (Arden Hills); Josh Olson, (Ramsey County), Louis Jambois (Ramsey
County); Lee Mehrkens (Ramsey County); Bruce Kimmel (Ehlers); Jenny Boulton (Kennedy &
Graven); David Perrault (Arden Hills)
Roll call taken.
Approval of Agenda
Chair Wicklund added two items to the agenda, Item 8B - 2018 Meeting Schedule and Item 8C
– JDA Income Statement Report.
Motion by Commissioner Ortega seconded by Commissioner Grant to approve the agenda as
amended. Motion carried.
Approval of August 7, 2017 Minutes
Motion by Commissioner Huffman seconded by Commissioner Grant to approve the minutes as
presented. Motion carried.
Public Inquiries/Informational
None
Consent Agenda
None
Old Business
Master Development Agreement Update
Director Olson provided the JDA with an update on the Master Development Agreement. He
explained the County has had some personnel changes and described the roles of Lee
Mehrkens and Louis Jambois with the County.
Commissioner Grant requested further information on the optimization study. Director Olson
provided the JDA with an update on the optimization study noting a summary report would be
released in early October.
Commissioner Grant questioned if the land transfer was being drafted by the County. Director
Olson explained in late July the impending approval of an early transfer was discussed. This
FOSET was approved by all entities on July 31st which will allow the County to close on the final
30 acres. He reported the County was working on this final transfer and the closing date had
yet to be scheduled.
Commissioner McClung asked when the JDA and City would be briefed on the preliminary
findings within the optimization study. Director Olson stated he could draft a memo.
Public Hearing
None
New Business
Amazon HQ2
Director Olson stated the County was working to prep itself for an Amazon HQ2. He
commented on the RFP and noted this was a sizeable North American call.
Louis Jambois introduced himself to the JDA and noted he was consulting with the County at
this time. He described how the Amazon proposal was causing the County to rethink the timing
of this project. He explained the County intends to pursue Amazon as one of the entrants to
the Rice Creek Commons site. It was noted the Amazon RFP was due on Friday, September
22nd. He believed the size of Rice Creek Commons fit the proposal well, as well as the freeway
and A-line access to the property. It was anticipated a decision would be made by Amazon in
early 2018.
Chair Wicklund understood that Greater MSP and DEED was putting together a response to the
RFP. He asked who was supportive or driving the desire for TCAAP to be the chosen location for
Amazon. Mr. Jambois explained there would be numerous sites from the Twin Cities
metropolitan area chosen for Amazon. From this, Amazon would then have to choose a site.
Commissioner Huffman reported the County Commissioners were speaking with Greater MSP
and DEED in order to draw their attention to the Rice Creek Commons site.
Commissioner Huffman requested Alatus to speak to this potential project. Bob Lux, Alatus,
believed the Amazon opportunity was rare and exciting. He understood that the City and JDA
had created a well thought out plan for the site, but believed it would be extraordinary to
accommodate a corporate campus for Amazon. He explained that Minnesota had a well
trained workforce that was willing and able to make this happen. Tom Shaver, Alatus, reported
he and his staff was working 24/7 with Mr. Jambois and the County in order to meet the RFP
deadlines.
Commissioner McClung was glad the County was playing to win for this opportunity. However,
he understood other parts of the country would also be working to secure Amazon. He asked
how going through this process would enhance the site if Amazon did not opt to locate in Arden
Hills. Mr. Lux stated this activity has prepped Alatus and the County to address another
national scale corporate campus effort.
Chair Wicklund asked if Alatus was willing to keep this project on hold until a decision was
reached by Amazon. Mr. Lux stated this would be an elongated process and he was willing to
put plans on hold as the County and Alatus work through the RFP qualifying process.
2018 Meeting Schedule
The 2018 JDA meeting schedule was provided to the members.
JDA Income Statement Report
The JDA income statement report through July was reviewed in detail.
Development Director’s Report
None
Administrative Director’s Report
None
Commissioner Updates
Commissioner Grant explained he supported the Amazon HQ2 proposal moving forward.
Chair Wicklund agreed and stated he looked forward to hearing more from the County and
Alatus on this endeavor.
Future Meeting Schedule
The next meeting will be Monday, October 2, 2017, at Arden Hills City Hall.
Meeting adjourned at 6:09 pm.
Approved _____________________________________ _______________________
Jonathan Wicklund, Chair Date
Page 1 of 1
Joint Development Authority
TCAAP Redevelopment Project
DATE: October 11, 2017
TO: Joint Development Authority Board of Commissioners
FROM: Administrators Olson and Joynes
SUBJECT: Master Development Agreement Update
TCAAP Joint Development Authority Staff will provide an update on the Master Development
Agreement with Alatus Arden Hills LLC.
AGENDA ITEM 6a
MEMORANDUM
Page 1 of 1
Joint Development Authority
TCAAP Redevelopment Project
DATE: October 11, 2017
TO: Joint Development Authority Board of Commissioners
FROM: Administrators Olson and Joynes
SUBJECT: Amazon HQ2
TCAAP Joint Development Authority Staff will provide an update on the Amazon HQ2.
Attachments: Rice Creek Commons Submittal to GreaterMSP/DEED
AGENDA ITEM 6b
MEMORANDUM
Proposed Location
RICE CREEK COMMONS
Premier property in a thriving
suburban community that can easily
and immediately accommodate
Amazon’s needs.
Well-educated workforce
High visibility and connectivity
Sustainable design
Shovel-ready
ricecreekcommons.com
Proposed Location
RICE CREEK COMMONS
2
September 22, 2017
Shawntera Hardy Michael Langley
Minnesota Department of Employment Greater MSP Partnership
and Economic Development 400 Robert Street North, Suite 1600
332 Minnesota Street, Suite E100 Saint Paul, Minnesota 55101
Saint Paul, Minnesota 55101
Ladies and Gentlemen:
We are pleased to present Rice Creek Commons as a potential site for Amazon’s Second Headquarters (HQ2).
With an educated labor force, existing infrastructure, vibrant culture, welcoming and diverse community, an
excellent quality of life, affordability, diversity of housing, and a stable business environment, Minnesota
and specifically Rice Creek Commons is the logical choice for Amazon’s HQ2.
The Rice Creek Commons site is a well-located, premier 427-acre property with extraordinary potential
to immediately execute a well-planned development from the ground up. Considerable time, energy and
funding has already been invested in preparation for an opportunity such as this, and the timing is perfect.
As a shovel-ready site, Rice Creek Commons is currently in a unique position (both locally and nationally)
to have immediate and future capacity to meet all of the building and site needs identified in Amazon’s
HQ2 RFP. In addition, the selection of Rice Creek Commons for Amazon’s HQ2 and long-term benefit
of adding 50,000 jobs has greater potential significance for the northeastern MSA than anywhere else
in the Minneapolis/Saint Paul metropolitan area.
Furthermore, a public-private partnership between Ramsey County, the City of Arden Hills, the Joint
Development Authority, and Alatus, which make up the development team, has been established to maximize
the value of this investment and deliver a world-class destination that is dynamic, economically strong, well-
designed, well-integrated, and appropriately dense and diverse for long term growth and stability. Amazon is
a bold, forward-thinking organization, and its aspirations for HQ2 perfectly align with our shared vision for Rice
Creek Commons: an endeavor to redefine suburban living for the 21st Century by embracing the best aspects
of both suburban and urban design.
As you review the enclosed submission, please note that we have responded to Amazon’s RFP primarily
with respect to those requirements/preferences that can be addressed by Rice Creek Commons. We have
deliberately not addressed matters pertaining to the Minneapolis/Saint Paul metropolitan area generally, such
as quality of life, culture/diversity and financial incentives, assuming that those matters will be addressed by
you and us, working together, in the final submission to Amazon.
The Minneapolis/Saint Paul metropolitan region is well-positioned to compete on a national scale for this
unparalleled development opportunity, and we welcome the opportunity to be a part of Minnesota’s larger
submission to Amazon.
Victoria Reinhardt Robert C. Lux David Grant
Chair, Board of Commissioners President Mayor
Ramsey County Alatus LLC City of Arden Hills
Proposed Location
RICE CREEK COMMONS
3
EXECUTIVE SUMMARY
Amazon’s Site Requirements and Preferences
A development-prepped, 100-acre site
• 427-acre, shovel-ready site in a first-ring suburb.
• Publicly owned site with high visibility from I-35W.
• Alternative Urban Areawide Review (AUAR) has been approved to allow additional density on the site.
• Unique zoning and regulatory body exists solely to oversee and streamline the development process.
• Master plan is flexible and may be adapted to reflect market conditions and development opportunities,
such as this.
Site must be 30 miles from population center
• Located 10 freeway miles from the downtowns of both Minneapolis and Saint Paul.
Travel logistics
• Minutes away from international airports.
• 30 minutes from the Minneapolis/Saint Paul International Airport.
• 7 minutes from the Anoka County Regional Airport.
• 10 minutes from the Saint Paul Downtown Airport.
• Adjacent to major highways/arterial roads.
• Adjacent to Interstate 35W to the east and immediately north of Interstate 694.
• Easily accessible due to nearly $200 million in recent and future investments to nearby highway
interchanges and $19 million committed to building a new boulevard through the site.
Access to mass transit
• Extension of the A-Line bus rapid transit line could be accommodated to connect the site to the regional
transit network.
Utility infrastructure
• Well-connected to the Twin Cities’ utility infrastructure and has the bandwidth to
support Amazon’s development.
Building Requirements
500,000 square feet in the initial phase I (2019)
• 427-acre, shovel-ready site can easily accommodate this initial phase.
Up to 8 million square feet in future plans
• 427-acre, shovel-ready site can easily accommodate Amazon’s future space needs.
Sustainability and energy efficiency
• Developer team is committed to environmentally responsible development.
• Pursuing the creation of a 40-acre solar installation adjacent to the site.
• Envisions net-zero energy office and residential neighborhoods made possible by utilizing
the geothermal energy generated from ongoing deep-water treatment at the site.
Proposed Location
RICE CREEK COMMONS
4
Rice Creek Commons is the premier
redevelopment site in the Minneapolis/
Saint Paul metropolitan region.
Ramsey County purchased a 427-acre parcel of the former
Twin Cities Army Ammunition Plant(TCAAP) in Arden Hills
with the goal of revitalizing a long-dormant industrial area
into a vibrant residential, commercial and retail area. The
site was rebranded Rice Creek Commons, in reference
to the section of Rice Creek which flows through the
development and will provide the setting for beautiful
walking and biking paths to augment other recreation
opportunities planned for the site.
Rice Creek Commons is located in Arden Hills,
Minnesota, a first-tier suburb of Minneapolis
and Saint Paul.
Development Team
The development team consists of
Ramsey County, the City of Arden Hills,
the TCAAP Joint Development Authority
(JDA), and Alatus.
Ramsey County purchased the 427-acre site from the U.S. Army and controls 100% of the site for development
purposes. While geographically the smallest county in Minnesota, Ramsey County is the most densely
populated and second-most populous county, with 510,000 residents. It is comprised of 18 cities and one
township in the heart of the Minneapolis/Saint Paul metropolitan area. Saint Paul, the state capital, is the
County’s most populous city. Ramsey County is rated “AAA” by Standard & Poor’s and Moody’s.
The City of Arden Hills has land-use authority over the site. Arden Hills is a first-tier suburb of both Minneapolis
and Saint Paul, and is a vital, attractive community of 9,600 people. Arden Hills serves as home to large
corporations, small to medium-sized businesses, and two private universities. The city was chosen as one of the
50 Best Suburbs in America in 2014 by Business Insider.
Ramsey County and Arden Hills created the JDA to solely oversee the redevelopment of Rice Creek
Commons and streamline the development process. The JDA selected Alatus as master developer in May
2016. Alatus and its team members Inland Development Partners and Tradition Development Corporation
are acknowledged leaders in multi-family as well as mixed-use, commercial, and single-family residential real
estate developments.
Proposed Location
RICE CREEK COMMONS
5
Amazon HQ2 RFP Decision Drivers
and the Rice Creek Commons Site
Rice Creek Commons has the unique ability to fulfill all of the ideal site and building
requirements, including future growth needs, as defined by Amazon in its RFP.
Site Requirements
Proximity to Population Center
Rice Creek Commons is conveniently located 10 freeway miles
from the downtowns of both Minneapolis and Saint Paul.
Proximity to International Airport
MSP International airport
Rice Creek Commons is located 30 minutes from the Minneapolis/Saint Paul
International Airport, one of the top ranked airports nationally. The airport is a Delta hub, thus travelers
can reach almost any domestic destination by air within three hours. The airport ranks second per capita in
passenger departures nationally. It is considered the fastest airport in the U.S., with the highest rate of on-time
departures.
Regional airports
Rice Creek Commons is located seven minutes from the Anoka County Regional Airport, which has undergone
a series of improvements recently, including lengthening and widening its two runways. The airport supports
more than 68,000 takeoffs and landings annually, and can accommodate medium-sized corporate jets.
The site is also located 10 minutes from the Saint Paul Downtown Airport, which can serve up to the largest
corporate jets. The airport has three runways and is the only reliever airport in the Metropolitan Airports
Commission system with a runway longer than 5,000 feet. The 6,700-foot runway can accommodate Gulfstream
jets that can reach Asia, Europe, and South America on a single tank of fuel, making international corporate
travel easy. The airport is adding new amenities, including a restaurant. More than 64,000 takeoffs and landings
occur at the airport annually.
Proximity to Major Highways and Arterial Roads
The site is adjacent to Interstate 35W to the west and immediately north of Interstate 694. It is bordered on the
north by County Road I and on the south by U.S. Highway 10 and County Road 96. I-35W connects directly to
downtown Minneapolis to the south and U.S. Highway 10 connects through I-694 and I-35E to downtown Saint
Paul to the southeast.
Rice Creek Commons is connected to the external road network in three locations: County Road I,
County Road H, and Highway 96. Within the site, the development team has designed a boulevard
that can carry 40,000 cars per day. Local streets within the development have been planned to be pedestrian-
and bicycle-friendly.
Proposed Location
RICE CREEK COMMONS
6
Access to Mass Transit
In 2016, Metro Transit opened the A-Line bus rapid transit line, a high-frequency bus line that connects
two Twin Cities light rail lines. It is anticipated that the A-Line service will be extended to serve Rice Creek
Commons and will connect the site to the regional transit network.
Extending the line to Rice Creek Commons would add approximately 10 stations to the line and provide transit
opportunities for thousands of residents, students and businesses. The extension would connect the nearby
University of Northwestern and Bethel University, as well as major employers, including Land O’Lakes and
Boston Scientific, to the broader public transportation system.
Building Requirements
Phase I Initial Square Footage
This site is shovel-ready and can accommodate Amazon’s Phase I building square footage needs immediately.
Total Square Footage
Because the site is 427 acres, the site has the capacity to support Amazon’s total future square footage needs
of more than 8 million square feet.
Time to Operations
Master Plan
The development team has worked together to develop a master plan that seamlessly
blends residential and commercial development to maximize the potential of the site. The
master plan draws on best practices in international urban and suburban development
to create a community for people of all ages to live, work, shop and play. This type of
development will ensure that Amazon is able to recruit and retain a quality employment
base.
The master plan is a series of three documents – the TCAAP Redevelopment Code, the
TCAAP Regulating Plan, and an amendment to the Arden Hills 2020 Comprehensive Plan.
Additionally, an Alternative Urban Areawide Review (AUAR) was approved by the City of
Arden Hills to allow additional density on the site. The site is zoned for office, mixed-use
commercial, and residential development.
The Development Team recognizes that the site’s master plan is flexible and may be
adapted to reflect market conditions and development opportunities, such as this. While
we have created an innovative vision for this site, we know that Amazon wants to build
the corporate campus of their dreams, not ours. We are committed to being flexible
to accommodate Amazon’s needs. Major advantages for the selection of Rice Creek
Commons for Amazon’s headquarters are that (1) the entire site is owned by Ramsey
County; (2) no parcel assemblage will be required; and (3) the entire site is shovel-ready and can accommodate
Amazon’s 100-acre needs immediately.
All of these completed actions (particularly the AUAR) expedite the site’s ability to respond to
Amazon’s RFP and development timing demands.
Watch a video about the current Rice Creek Commons master plan at ricecreekcommons.com
NOTE: We would be happy to create an Amazon-specific video in consultation with DEED and
GREATER MSP if we are selected as one of the sites for submission on October 19.
Proposed Location
RICE CREEK COMMONS
7
Additional Key Decision Drivers
Sustainability
Supporting environmentally responsible development has been a top priority for the development team.
The JDA adopted an Energy Integration Resiliency Framework, which sets forth a vision to create the largest
net-zero energy redevelopment in the state. Ramsey County has a purchase agreement with the U.S. Army for
a 40-acre parcel of land adjacent to Rice Creek Commons and is pursuing the creation of a solar installation
that would generate eight megawatts of electricity, enough energy to power all commercial and residential
developments at the site. Estimates show the installation has the potential to reduce greenhouse gas
emissions by more than 7,500 tons annually, roughly the amount produced by 1,432 cars each year.
Additionally, the development team envisions net-zero energy office and residential neighborhoods at
Rice Creek Commons, made possible by utilizing the thermal energy generated from ongoing deep water
treatment at the site. Instead of a traditional HVAC system, office and multi-family buildings would be heated
and cooled by thermal energy captured from groundwater. We expect that this may meet some, if not all,
of Amazon’s heating and cooling needs.
Ultimately, this project is about transforming a vacant parcel of land into a community asset, and the
development team is committed to prioritizing sustainable features in the development, sharing a
commitment to the environment and exploring solutions such as solar energy, geothermal heating,
and cooling, water conservation, composting, and other demand-side management strategies.
Utility Infrastructure (Connectivity)
Located in a first-ring suburb, Rice Creek Commons is well connected to the Twin
Cities utility infrastructure and has the bandwidth to support Amazon’s development.
The Rice Creek Commons site is located at the northwest boundary of CenturyLink’s
primary service area, which provides the highest level of fiber service capability.
There is a direct fiber optic path to the Rice Creek Commons site from a primary
CenturyLink office located 3.4 miles away. Diverse Path Capabilities (e.g., system
redundancies) from separate services areas are easily attainable. This system
redundancy has been made available for the Wells Fargo data center, which is
located one mile north of Rice Creek Commons.
Local Labor Pool
The following statistics relate to an area within a five-mile radius
of RCC and are as of January 19, 2017, from ESRI Business Analyst:
• 5,680 business
• 94,500 employees
• 60,772 households
• 153,469 residents
• 30% have some college, 42% have
bachelors, graduate, or professional degrees
• Of those employed (95%), 71% have “white collar” jobs
• $70,000 median household income
Proposed Location
RICE CREEK COMMONS
8
The Rice Creek Commons Site
History
The Twin Cities Army Ammunition Plant (TCAAP) was constructed in 1941-
1942 to manufacture small arms ammunition for American and Allied forces
during World War II, and remained in production until 1945. At its peak, the
plant employed 26,000 people – more than half of whom were women. The
plant closed after the U.S. declared victory over Japan, but was intermittently
reactivated to produce small arms ammunition during the Korean and
Vietnam wars. It became inactive in 1976. Ramsey County purchased the
Twin Cities Army Ammunition Plant with the intent to clean, redevelop and
reestablish the property as the economic engine it once was – this time with
homes, businesses and retailers.
Ramsey County completed soil remediation in November 2015. The Minnesota Pollution Control Agency
issued a Certificate of Completion in July 2016 through its Voluntary Investigation and Cleanup Program to
verify that soil had been restored to residential standards – the highest remediation standard attainable. The
U.S. Environmental Protection Agency is expected to remove the site from its Superfund list for soil in 2018,
which means, with demolition and remediation complete, the largest large-scale redevelopment opportunity in
the Twin Cities is shovel-ready.
Green Space
The entire site design includes an interwoven network of parks and trails that not only provide open space for
all types of recreation, but also perform important environmental functions such as stormwater management
and natural habitat restoration.
A section of Rice Creek flows through the Rice Creek Commons development. In 2016, Ramsey County
collaborated with the Rice Creek Watershed District, U.S. Army Corps of Engineers, and Minnesota
Department of Natural Resources on an innovative project to transform Rice Creek back to its original,
meandering path and stabilize its banks with native plants and trees. The project resulted in nearly 2,000 new
feet of stream, a restored floodplain, and the creation of high-quality wetlands. Site plans call for Rice Creek to
serve as a premier feature of a 50-acre natural resources corridor that winds through the site, providing both a
natural asset and regional stormwater treatment.
Additionally, 24 acres of park space is planned internally on the site, and the county is building a bike and
pedestrian trail on the eastern edge of the development that connects to the Rice Creek North Regional Trail
and the Highway 96 Regional Trail. Future employees and residents will have access to miles of linked trails,
making active living an easy choice.
Bike and Pedestrian Infrastructure
Rice Creek Commons will be a walkable community, featuring a network of trails, green corridors, and
pedestrian-friendly streets. More than four miles of bike and pedestrian trails will be built on the site.
Additionally, the site is adjacent to a 202-acre Regional Trail Corridor that connects the site to the Twin
Cities area network of pedestrian and bicycle trails. The Minneapolis/Saint Paul region has been nationally
recognized for being a bicycle-friendly region.
Proposed Location
RICE CREEK COMMONS
9
Local Market Highlights
The following are some of the amenities in the immediate vicinity of Rice Creek Commons which will make this
site an attractive and welcoming community for Amazon:
• The northeast region of the Twin Cities metropolitan area offers affordable to luxury housing options, both
rented and owned. This housing product diversity, ranging from workforce housing to executive-level
homes, will be able to support Amazon’s employment needs now and in the future.
• There are more Fortune 500 Companies (18) per capita in the Minneapolis/Saint Paul metropolitan area than
any other region. Several Fortune 500 corporate headquarters campuses are located within a few miles of
Rice Creek commons, including Medtronic, St. Jude Medical, Boston Scientific, and Land O’ Lakes.
• Minneapolis/Saint Paul is the 9th most inventive metropolitan area worldwide. It is the birthplace of game
changers like the pacemaker and supercomputer. (Organization for Economic Cooperation and Development)
• Arden Hills is home to 14 parks and more than 26 miles of trails that connect to a regional trail system
with more than 240 miles.
• The Mounds View School District, which is consistently rated among the best in Minnesota, is the
school district for Rice Creek Commons residents.
• With a highly educated population, the northeast metro is uniquely positioned to provide a local
employment base for Amazon:
• The Twin Cities is a national magnet for young professionals, with the highest employment
rate for 19-34 years olds in the country.
• 49% of residents within a five-mile radius of the site have a bachelor’s degree or higher.
• 70,000 four-year college students study within a 10-mile radius of the site.
• 661,000 employees live and 33,000 businesses are located within a 10-mile radius of the site.
Proposed Location
RICE CREEK COMMONS
10
Public Investments and Incentives
Project goals
The goals of the Development Team generally include:
• Tax base growth
• Job creation
• Transit and mobility opportunities
• Energy and environmental resiliency
• Housing diversity
• Natural resources protection
• Community vitality and interconnection
• Enhanced recreational features
Previous and committed investments
Ramsey County and its partners want to work with the state and GREATER MSP to create a coordinated,
coherent and comprehensive local, regional and state incentive package to be offered to Amazon.
In order to achieve the orderly and timely redevelopment of Rice Creek Commons, the following investments
have already been made or committed to for the project:
Invested to date
• Ramsey County invested $30 million in the demolition and remediation of the site to residential standards.
• Anticipating thousands of people living and working at Rice Creek Commons, $34 Million has been
invested at Interstate 35W and Highway 96 and Interstate 35W and Country Road H. A new roundabout
was built at the Country Road I entrance to the site.
• Since 2013 nearly $200 million has been invested or is planned to be invested in infrastructure
improvements near Rice Creek Commons.
Committed to future investments
• Ramsey County has committed $19 million to build a new county road will serve as the main access point
through the site.
Proposed Location
RICE CREEK COMMONS
11
Appendix: Major Highways and Arterial Roads
Proposed Location
RICE CREEK COMMONS
12
Appendix: Local Amenities and Infrastructure
Proposed Location
RICE CREEK COMMONS
13
Appendix: Site Area
Page 1 of 3
Joint Development Authority
TCAAP Redevelopment Project
DATE: October 11, 2017
TO: Joint Development Authority Board of Commissioners
FROM: Beth Engum, Ramsey County Project Manager
Josh Olson, JDA Administrative Director
SUBJECT: TGRS Optimization Study
This memorandum has been prepared at the request of the Joint Development Authority at their
meeting on September 20, 2017 to update the Authority on the status of the TGRS Optimization Study
process.
The TCAAP Groundwater Remediation System (TGRS) began operating in 1987, largely within the 427-
acre Rice Creek Commons (RCC) redevelopment site, to treat contaminated groundwater resulting from
the manufacturing of munitions dating back to the 1940s. The TGRS was installed by and is the operating
responsibility of the U.S. Army. The TGRS removes volatile organic compounds (VOCs) primarily
trichloroethylene (TCE) from the groundwater. TCE is a chemical compound used as an industrial
solvent Groundwater is extracted from the aquifer via 11 active wells and sent to the water treatment
plant on the east side of the site via an underground network of pressurized pipes. TCE is removed from
the water via an air stripping process and the clean water is pumped underground to a gravel pit located
northeast of the site on Arden Hills Army Training Site (AHATS) where treated water infiltrates back into
the aquifer.
Since it was installed, the TGRS has made significant strides towards cleaning up the groundwater,
removing hundreds of pounds of VOCs over the last 20+ years. The level of VOCs in the groundwater, as
measured from monitoring wells onsite and downstream, is less than when the system began pumping.
Variability exists in the level of VOCs still detected depending on which monitoring well is tested and
whether the water is being pumped from the bedrock or overlying sands, among other possible reasons.
This raises questions relative to the Army’s obligation to regulators in removing VOC contaminants from
the groundwater:
• Are the extraction wells located in the correct locations and are they pumping at the correct
depth?
AGENDA ITEM 6c
MEMORANDUM
Page 2 of 3
• What modifications would need to be implemented to optimize the removal efficiency of the
system?
Ramsey County, City and/or a future developer do not have decision making authority over TGRS
mitigation actions. This continues to reside in the long-term relationship with the Army and regulators.
The Army’s answer and regulators concurrence to these questions could impact the use of the property.
In 2015, the emerging contaminant 1,4-dioxane (1,4-DX) was identified in the well network at TCAAP
and in neighboring municipal water supply wells. This compound was historically added to TCE as a
stabilizer and was not considered a contaminant of concern at TCAAP. In 2013, 1,4-DX became a concern
when the Minnesota Department of Health promulgated a Health Risk Limit (HRL) for 1,4-DX of 1 part
per billion. This concentration was exceeded in multiple wells on TCAAP and in municipal wells that
service the City of New Brighton. Neither the TGRS nor the existing treatment system operating in the
City of New Brighton effectively remove 1,4-DX from groundwater. The City of New Brighton is currently
modifying their municipal water treatment plant that removes 1,4-DX. This is considered at the point of
use as the system does not treat the aquifer itself. The TGRS is a remediation technique at the point-of-
source.
Analysis of available data and collection of additional data is necessary to answer these questions and
assess options with respect to evaluating and managing 1,4-DX. These are the primary goals of the
Army’s Optimization Study.
In March 2017, the Army, with the help of their consultant Pika-Arcadis, kicked off the Optimization
Study. Study steps included:
1. Review existing data (i.e. groundwater flow patterns, depth of bedrock, historical TCE
concentrations and mass removed from extraction wells) to form a Conceptual Site Model
(CSM) for the deep groundwater.
2. Perform Vertical Aquifer Profiling (VAP) at 7 existing wells (3 on RCC, 4 offsite)
3. Install 3 new wells (on RCC) and perform VAP
4. Update CSM with new data
5. Preparation of a report summarizing the results of the study with recommendations
From the beginning, it was made clear by the Army that the study scope included evaluation the existing
data, limited collection of new data, and preparation of a summary report with recommendations.
Implementation of Optimization Study recommendations is not included under the current Pika-Arcadis
contract nor is it currently funded by the Army.
The Army formed a workgroup of various stakeholders that included representatives from the MPCA,
EPA, Ramsey County, Alatus, the Cities of New Brighton and St. Anthony, and Army consultants. The
workgroup was convened four times during the course of the study (October & December 2016, March
& August 2017) in order for the Army’s consultant team to apprise workgroup members on their
progress and answer any questions.
At the August 2017 workgroup meeting, the Army stated that a summary of the study findings would be
issued sometime in October. We’ve received updated word from the Army that report will be circulated
in November. We will share the report as soon as it is available.
Page 3 of 3
Since 1,4-DX was identified on TCAAP and throughout the study the County has sought answers to the
following questions:
• Will existing extraction or monitoring wells be removed within RCC?
• Will new extraction wells or monitoring wells be added within RCC?
• Will the existing TGRS piping change in size and/or location?
• Will new TGRS piping be added?
• Will changes be made to the existing water treatment plant building?
• Will new facilities be added to the existing treatment facility or will new treatment facilities be
created to address 1,4 dioxane?
• What, if any, regulatory steps are required based on Army modifications to the TRGS system?
What is the timeline for these regulatory steps?
Ultimately the County, JDA, and developer are seeking greater clarity regarding the Army’s long-term
obligations to remediate groundwater on the site and how those obligations may impact the final design
and implementation of infrastructure as well as timing of development.
Copies of the TGRS Optimization Study will be provided to the JDA, when completed, and placed on a
meeting agenda for further discussion at that time.
Page 1 of 1
Joint Development Authority
TCAAP Redevelopment Project
DATE: October 11, 2017
TO: Joint Development Authority Board of Commissioners
FROM: Administrators Olson and Joynes
SUBJECT: Green infrastructure study opportunity with Rice Creek Watershed District
County Staff will provide an update on a Rice Creek Commons Green Infrastructure and Stormwater
Reuse Feasibility Study
AGENDA ITEM 8a
MEMORANDUM
Page 1 of 2
Joint Development Authority
TCAAP Redevelopment Project
DATE: October 11, 2017
TO: Joint Development Authority Board of Commissioners
FROM: Sara Thatcher, Goff Public
SUBJECT: Rice Creek Commons Communications
Communications teams for Ramsey County, the City of Arden Hills, and Alatus continue to coordinate
media requests. In September, Ramsey County pitched reporters after submitting a proposal to
GREATER MSP and the Minnesota Department of Employment and Economic Development to locate
Amazon’s second headquarters at Rice Creek Commons.
The following articles were published:
• Race for new Amazon HQ is altering TCAAP plans in Arden Hills – Star Tribune; September 20,
2017
• Twin Cities Join Forces to Get New Amazon HQ in Minn. – WCCO-TV; September 22, 2017
• Ramsey County's Amazon HQ bid adds St. Paul riverfront parcels to ammo site – Star Tribune;
September 22, 2017
• Amazon.com, take a look at St. Paul and Arden Hills for HQ2, county says – Pioneer Press;
September 22, 2017
• Ramsey County offering two tricky sites for Amazon HQ: Arden Hills and St. Paul riverfront –
Minneapolis/St. Paul Business Journal; September 25, 2017
• Twin Cities leaders submit more than a dozen sites in Amazon sweepstakes – Minneapolis/St.
Paul Business Journal; September 26, 2017
• Amazon Sites Submitted, but List Kept Secret – KSTP; September 26, 2017
• Minnesota's pitch for Amazon's second HQ picks up steam – Star Tribune; September 29, 2017
• Ramsey County's bid for new Amazon HQ is more about being noticed – Star Tribune;
September 29, 2017
• Arden Hills site submitted as potential Amazon headquarters – Lillie News; October 2, 2017
• Amazon may bring second headquarters to Arden Hills – White Bear Press; October 3, 2017
AGENDA ITEM 9
MEMORANDUM
Page 2 of 2
• In the race for Amazon HQ2, Twin Cities has a good start, consultant says – Pioneer Press;
October 6, 2017
Over the past several months, we have also received dozens of inquiries about residential housing and
commercial properties through the website and are working with Alatus to maintain a list of people who
have expressed interest in purchasing property at Rice Creek Commons. We will communicate with
these people once we have firmer information about the development timeline.