A special meeting may be called by the Mayor or by any two Councilmembers.
Reason for meeting: 1. Agenda Items
A. Roundabout Staging Discussion
2. Council/Staff Comments
Adjourn
Requested Date: 09/12/2022
Requested time: Immediately following Regular City Council Meeting
Open meeting X Closed meeting
Signature of person(s) making request:
i
Mayor or Council Member
Council Member
09/08/2022
Date
Date
-This section to be completed by City staff -
Date received: 09/08/2022
Date meeting to be held: 09/12/2022
Time of meeting: Immediately following Regular City Council Meeting
Location: City Hall
All necessary posting and notices have been completed.
Signature of City Clerk
09/08//2022
Date
City of Arden Hills • 1245 West Highway 96 • Arden Hills Minnesota 55112
Phone 651.792.7800 • Fax 651.634.5137 • www.cityofardenhills.org
.-I't
�-AI�EN HILLS
Approved: October 10, 2022
CITY OF ARDEN HILLS, MINNESOTA
SPECIAL CITY COUNCIL WORK SESSION
SEPTEMBER 12, 2022
IMMEDIATELY FOLOWING REGULAR CITY COUNCIL MEETING
ARDEN HILLS CITY HALL
CALL TO ORDER/ROLL CALL
Pursuant to due call and notice thereof, Mayor Grant called to order the City Council
Work Session at 7:35 p.m.
Present: Mayor David Grant, Councilmembers Brenda Holden, Fran Holmes, Steve
Scott, and David Radziej
Absent: None
Also present: City Administrator Dave Perrault; Public Works Director/City Engineer
David Swearingen; Assistant to the City Administrator/City Clerk Julie Hanson; Brian
Johnson, SRF Consultants; and Joey Lundquist, Ramsey County
1. AGENDA ITEMS
A. Roundabout Staging Discussion
Brian Johnson, SRF Consultants, and Joey Lundquist, Ramsey County, introduced
themselves to the City Council and said they were in attendance to provide an update regarding
the roundabout project at County Road E and Snelling Avenue.
Mayor Grant stated that the City is pursuing this project because of capacity which will improve
safety, especially during the PM hours, but it is not strictly because of safety. He said capacity is
the driver, not safety.
Ms. Lundquist concurred that there are no safety issue concerns currently at this intersection.
Mr. Johnson stated they are on track to finish the project's plans by end of year and could go out
for bids in early 2023, with construction starting in the spring of 2023.
Councilmember Holden stated that every time Ramsey County has a construction project in
Arden Hills, there are issues. She said that this project cannot be postponed.
The Council encouraged Mr. Johnson and Ms. Lundquist to do all they can to ensure the
various private utility companies and stakeholders have addressed potential issues so that the
project can stay on track and that there are no surprises.
ARDEN HILLS SPECIAL CITY COUNCIL WORK SESSION — SEPTEMBER 12, 2022 2
A discussion ensued regarding project coordination and the importance of communication
between SRF, Ramsey County, the private utility companies, contractors, and City staff.
Councilmember Holden requested a timeline and asked if such could be required as part of the
bidding process.
Mr. Johnson stated that the contractor works with the utility companies so it can be tricky, but he
and Ms. Lundquist said they should be able to get a time commitment for this project.
Mr. Johnson said there is an open house scheduled for Thursday, October 6 in which information
regarding what to expect for this project will be discussed.
Councilmembers Holden and Scott said most people that live in the project area are not in favor
of this project.
Councilmember Holmes stated that most people do not think this intersection is a problem. She
said they do not see this as a capacity issue, there are not many cars there and that traffic moves
through the intersection fine. Some consider this project a waste of money.
A short discussion ensued about the fact that there are various utilities that will impact this
project.
Mr. Johnson indicated the project footprint has been identified and preliminary right-of-way
staking has been performed as temporary easements will be necessary. He indicated the Ramsey
County's right-of-way agents have met with each property owner that abuts the project.
Ms. Lundquist stated that there will be one driveway closure at the Lindey's property, but they
are working with them for a site redesign.
Mr. Johnson said Lindey's is supportive of the project and the goal is to ensure the business will
continue to thrive during construction.
Councilmember Holden asked about crosswalks at this location.
A discussion ensued regarding how the crosswalks would function in a roundabout setting.
Mr. Johnson indicated that they had met with the property owner located straight across from
Lindey's and that the owner is supportive. He said they have received a few calls from residents
about trail connections and crosswalks and the feedback and been mostly positive.
Mr. Johnson referred to the project layout as provided in the Council packet. He talked about the
change that included the sidewalk extension down Lake Johanna Blvd which will connect back to
the shoulder and eventually connect to the trail.
A discussion ensued regarding additional requests that were brought up by residents such as
crosswalks, connections and striping, and ADA requirements.
Mayor Grant asked for confirmation of the City's costs for this project at $800,000.
ARDEN HILLS SPECIAL CITY COUNCIL WORK SESSION — SEPTEMBER 12, 2022 3
Ms. Lundquist agreed with that figure and stated the project's total cost will be somewhere
around 1.2 to 1.5 million.
Public Works Director/City Engineer Swearingen commented that that estimate does not
include the City's utility improvements.
Mr. Johnson stated that the cost estimate needs to be updated as it does not reflect current bid
prices, and there is a chance it could increase unless the bidding climate changes.
Councilmember Holden asked if the County ever turns a bid down if it is not reasonable.
Ms. Lundquist indicated that yes, the County has turned down a bid in the past and then rebid
later in the year.
A discussion ensued regarding the breakdown of the associated costs for this project.
A discussion ensued regarding the watermain and associated connections in this area.
Mr. Johnson stated the costs could also increase based on how traffic is managed during
construction. He said there are three options: close the intersection completely so that no traffic is
going through the intersection, which is not practical; build the project under full traffic, which is
difficult due to the small footprint; or divert traffic. He said traffic can be diverted by closing
lanes or even constructing a bypass, which would be very impactful to this area.
Mayor Grant stated that options for diverting traffic would be additional costs above the estimate
provided earlier.
Mr. Johnson agreed and stated that for example, a bypass could cost an additional $100,000
versus just dealing with closures.
Councilmember Holden asked how long the project will take if the intersection is closed the
entire time to all traffic besides local traffic.
Mr. Johnson estimated that if most traffic is diverted, it could take 12 weeks (3 months), best
case scenario.
Ms. Lundquist said that if a bypass is constructed, that would add an additional 2 months, for a
total of 5 months to complete the project and would add an additional $100,000 more in costs.
Councilmember Radziej stated he liked the idea of a bypass to keep the traffic moving.
A discussion ensued regarding the various options for handling traffic as presented in the City
Council's packet.
City Administrator Perrault questioned the additional projects that Ramsey County has
scheduled for next year that could impact this project, such as the work on Snelling Avenue from
County Road E to Highway 96.
ARDEN HILLS SPECIAL CITY COUNCIL WORK SESSION — SEPTEMBER 12, 2022 4
Ms. Lundquist said they can coordinate the two projects and work together regarding closures.
Mr. Johnson stated that the various stages of constructing the roundabout and opening lanes
throughout the process would help with this issue.
A short discussion ensued regarding the project on Snelling Avenue to Highway 96. It was noted
this is set to be a mill and overlay project and should not take long to complete.
Councilmember Holden stated she would rather spend the $100,000 if it means the project can
be completed more quickly.
Mayor Grant requested clarification on how additional costs would be split.
Ms. Lundquist indicated the additional costs would be shared and split in the same manner.
A discussion ensued regarding option two, which is constructing a partial bypass, and how the
intersection would function over the course of the project's construction should a bypass be built.
A discussion ensued regarding option three, which includes temporary stages of closures.
Ms. Lundquist stated that right-of-way work and temporary easements would be addressed in
January of 2023 and the bidding process takes about a month. She said a contractor could be on
board by the end of March.
A short discussion ensued about the fact that some utility work can be performed before
construction is fully underway, but some must wait until that time.
Ms. Lundquist said they would like this project to be completed before school starts in the fall
and that since she writes the contracts, she can include dates for the various stages of completion.
The Council indicated that construction hours can be extended to allow additional working hours
above what is allowed in ordinance.
Mayor Grant asked about MSA dollars for this project.
A discussion ensued about how MSA funding functions in general.
A discussion ensued about ARPA funding and other projects in general.
Mayor Grant reiterated that capacity at the intersection is an issue. He asked if the intersection
can accommodate the traffic levels during the PM hours.
Mr. Johnson said the traffic study shows this intersection meets warrants for a traffic signal but
that a roundabout would be more effective. A roundabout would have more capacity.
Mayor Grant asked that they quantify how much more capacity the city is gaining by installing a
roundabout. He asked what percentage is the City buying.
ARDEN HELLS SPECIAL CITY COUNCIL WORK SESSION — SEPTEMBER 12, 2022 5
Mr. Johnson said he did not have this figure off the top of his head but would speak with their
traffic folks and provide a follow-up report.
City Administrator Perrault asked about the grading for this location.
A discussion ensued about the ICE report and various traffic impacts in the area during prior
construction projects in the area.
Councilmember Scott asked how difficult it would be if the City would want to expand the
roundabout to a double lane 20 to 30 years later.
Mr. Johnson said that a single lane roundabout has a lot of capacity and he did not know that this
area would ever need a double lane, since the area is so built up already.
Ms. Lundquist stated there are other cities that had double lane roundabouts that have converted
back to a single lane because they work better.
Councilmember Holmes asked if Ramsey County said that if the City does not pursue a
roundabout now, it would never get one.
Ms. Lundquist confirmed that it could be quite a number of years before the County would come
back to any kind of improvements at this intersection.
Councilmember Holmes stated these are the two reasons to do this project now — to use the
available MSA funds and if the City does not do this now, it will not get done.
Mayor Grant said that and the watermain can be addressed at this time.
Mayor Grant asked Public Works Director/City Engineer Swearingen if the watermain in this
area would need to be addressed at some point, regardless. He also used the example of when the
TCAAP project moves forward.
Public Works Director/City Engineer Swearingen stated yes, this section of watermain would
need to be addressed at some point whether a stop light or roundabout project takes place at this
location, or when the TCAAP project moves forward. He agreed that as it currently stands today,
this section of watermain is redundant.
Mayor Grant stated the City would like to move forward with option 2.
A short discussion ensued regarding the October 6th open house and public engagement.
2. COUNCIL COMMENTS AND STAFF UPDATES
None.
ARDEN HILLS SPECIAL CITY COUNCIL WORK SESSION — SEPTEMBER 12, 2022 6
ADJOURN
Mayor Grant adjourned the Special City Council Work Session at 9:00 p.m.