HomeMy WebLinkAbout04-11-23 Agenda Packet Chair:
Aisha Elmquist (2024)
Secretary:
Renee Marino (2024)
Board Members:
Linda Hansohn (2023)
Tony Peleska (2023)
Kathy Johnson (2024)
Susan Johnson (2025)
Gary Gerding (2025)
Staff Liaison:
David Swearingen
Karth Lake Improvement
District Board
REGULAR MEETING
Tuesday
April 11, 2023
1245 W. Highway 96
Arden Hills, MN 55112
651.792.7800
www.cityofardenhills.org
Agenda
Board Meeting Convenes at 6:30 PM
The public may access this meeting remotely by joining via Zoom.
To join the Zoom Meeting, click this link (or copy and paste it into a new browser):
https://us02web.zoom.us/j/82083667252
CALL TO ORDER/ROLL CALL
1. APPROVAL OF THE AGENDA
2. APPROVAL OF MINUTES of the previous meeting January 10, 2023
3. BOARD MEMBER ELECTIONS: Terms expire for Linda Hansohn and Tony Peleska
4. ELECTION OF CHAIR AND SECRETARY
5. PUBLIC INQUIRIES
6. OLD BUSINESS
6.1. Karth Lake water level modeling and management process progress report. Renée Marino
6.1.1 Background: Hypothesis: a revision to the pump management policy can reduce water level bounce (i.e., range of
high and low levels), which can improve lake quality and its environment while appropriately mitigating risk of damage to
shoreline properties.
Action: Renée to continue working with RCWD to get the hydrologist’s modeling results. On hold: Renée to ask RCWD
and DNR for their response to Como lake level management article introduced by Susan Johnson. Renée to work with the
DNR and David Swearingen to get the gauge relocated in the spring of 2023 to facilitate recruiting other volunteers in
weekly gauge readings. Share 2022 lake level readings and discuss 2023 volunteer expansion.
6.2. Plan for 2023 removal of excess lake weeds and debris. Susan Johnson
6.2.1 Background: Holt has scheduled another lake weed removal day in August 2023 for lake property owners interested
in participating. This is classified as a voluntary effort and not an official board action. However, the board is aware of and
supportive of this effort.
Action: If no new developments, table until mid-summer.
6.3. Plan for 2023 control of invasive purple loosestrife. Renée Marino
6.3.1 Background: After the Purple Loosestrife infestation event in 2022, it will be important to monitor and mitigate new
growth in the near future, since seeds from the plants removed in 2022 will most likely continue to germinate for several
years going forward.
Action: Discuss DNR “Perennial Lifecycle &Treatment Timing” pictograph and further develop the 2023 plan of
response.
6.4. Possibility of initiating a new study to identify status and refresh list of BMPs for future management of Karth
Lake: David Swearingen
6.4.1 Background: The most recent Karth Lake study and BMP identification was performed in 2009. The board would
like to identify a plan to be included in a follow-up assessment of Karth Lake’s current health and opportunities for
improvement (BMPs). David Swearingen described current and future grant opportunities that the City of Arden Hills will
pursue and extended to include Karth Lake.
Action: Discuss progress towards identifying new RCWD point of contact for grant opportunities.
Karth Lake District Board
April 11, 2023 Page 2
6.5. Lakeshore owner outreach and education. Kathy Johnson and Board.
6.5.1 Background: The KLIDB has reached out to KLID members in the past with flyers, events and door-knocking to
increase awareness of what the KLIDB does, provide information to assist members in managing their shoreline and to
recruit new board members. Several lakeshore properties have or are soon expected to have new owners that have not
benefited from past communications and an update on the lake’s current status to continuing owners would be helpful.
Action: Continue development of the 2023 communication plan, identify events, flyer design, website updates, etc. to
support a 2023 outreach.
7. NEW BUSINESS 7.1 Report of water quality results for 2022 and volunteer sampling plan for 2023. Gary Gerding.
7.1.1 Background: The Metropolitan Council has released their summary water quality report for 2022 and detailed report
for 2021. Both are available at this link: https://metrocouncil.org/Wastewater-Water/Services/Water-Quality-
Management/Lake-Monitoring-Analysis.aspx. Karth Lake’s overall health grade dropped from B in 2021 to C in 2022. It
was a B from 2011 to 2021 with the exception of C in 2016 and 2020.
8. NEXT MEETING
9. ADJOURN
Draft Minutes for Karth Lake Improvement District Board
Regular Meeting 6:30 PM, Tuesday, January 10, 2023
1. CALL TO ORDER/ROLL CALL
The meeting convened at: 6:30 PM.
Present:
Board Members: Aisha Elmquist, Chair; Renée Marino, Secretary; Gary
Gerding; Kathy Johnson; Linda Hansohn; Susan Johnson
Staff Liaisons: David Swearingen, Public Works Director
2. APPROVAL OF AGENDA: The agenda was approved as written.
3. APPROVAL OF MINUTES: The minutes of the previous meeting on October 11,
2022 were approved as written.
4. PUBLIC INQUIRIES: None.
5. OLD BUSINESS
5.1. Karth Lake water level modeling and management process progress report.
Renee Marino
5.1.1 Background: Renee Marino’s Hypothesis: a revision to the pump
management policy can reduce water level bounce (i.e., range of high and low
levels), which can improve lake quality and its environment while appropriately
mitigating risk of damage to shoreline properties.
Action from 10/11/22 Meeting: Renee to continue working with RCWD to get
hydrologist modeling launched. David Swearingen to check on constraints for
DNR gauge repositioning. Renee to work with DNR to get the gauge relocated in
the spring of 2023 and to include other volunteers in weekly gauge readings.
Renee to ask RCWD and DNR for their response to Como lake level management
article introduced by Susan Johnson.
Discussion: Matt Kocian of RCWD responded after our last meeting to say that
the hydrologist has started on the modeling and may reach out to Renée with
questions if he has any. Renée has not heard further. Regarding the Como Lake
article, Renée has not reviewed or shared it with others so this issue, as well as the
DNR gauge relocation topic will be deferred until the next meeting.
5.2. Plan for 2023 removal of excess lake weeds and debris and control of invasive
purple loosestrife. Susan Johnson and Board
5.4.1 Background: Holt has scheduled another lake weed removal day in 2023
for lake property owners interested in participating. After the Purple Loosestrife
infestation event in 2022, it will be important to monitor and mitigate new growth
in the near future, since seeds from the plants removed in 2022 will most likely
continue to germinate for several years going forward.
Action: Discuss 2023 plan and identify volunteers for 2023 efforts.
Discussion: Susan Johnson requested that this be addressed as two separate topics
because they are different in nature. Specifically, she understands that the removal
of excess lake weeds and debris is not a specific board action but, rather, a
voluntary program in which participation has been decided by individual property
owners. Historically, about 50% have chosen to participate. Had it been a board
action, the cost of removal would have been assessed to all members by property
tax levies with no option to opt out. As a board, we recognize that weed removal
is important and beneficial to the health of the lake and encourage it. Since it is
beneficial but not necessary, it is not considered it to be an official board action.
For purposes of documenting this issue in the minutes, Susan described an
alternative approach that has been considered in the past to address voluntary
efforts related to the lake. Namely, the board has considered the creation of a
Karth Lake association legal entity, but concluded that organizing and managing
such an association would be costly, difficult and unlikely to succeed.
Rather than establishing an association, board members have found that the Arden
Hills Foundation has been a valuable vehicle for voluntary donations of funds
designated for specific voluntary projects in and around Karth Lake. Proposals for
each project are submitted to the Foundation and have regularly been approved.
By contrast, the removal of invasive species such as Purple Loosestrife, Curly-
leaf Pondweed and Eurasian Watermilfoil should not be optional. According to
the DNR, if identified, such species should be removed. Anything that would be a
danger to the health of the lake should be considered to be a board issue,
consistent with the KLID mission of advising the city on its management of the
health of the lake.
The Purple Loosestrife removal efforts in August of 2022 were met with nearly
unanimous cooperation by property owners to remove identified plants or
allowing volunteers to remove the plants. The DNR has enforcement mechanisms
for removal of invasive species, but the positive experience of 2022 suggests
these plants can be managed through cooperation rather than enforcement.
In 2023, Purple Loosestrife removal efforts may be hindered by the ability to
identify the plants before they bloom in late summer. However, a DNR pictograph
linked to from the City of Arden Hills’ website shows how to identify and
eradicate the plants before full bloom. Last year’s effort was a crisis response.
This year’s effort can be more deliberate. Planning for that effort can be addressed
in the next meetings.
5.3. Sediment Growth: David Swearingen
5.3.1 Background: Karth Lake’s sediment levels have risen through the years.
Several steps have reduced the rate of new sediment inflow including installation
of grit chambers on all street sewer inflows including within the BMP#1 Phase I
structure. Board members asked whether sediment growth could be measured
going forward. David discussed how the city is measuring sediment growth in
several filtration ponds in Arden Hills and suggested that a similar measurement
system might be developed for Karth Lake.
Action: Continue to discuss the possibility of measuring and monitoring sediment
growth going forward.
Discussion: David Swearingen said the city hopes to get funding to perform a
sediment growth study of Karth Lake in 2025 in preparation for the 2026 PMP
(Pavement Management Program) of Amble Drive and adjacent roads. The city’s
2024 PMP for the Colleen Drive area includes a sediment study of related
drainage ponds and dredging work. This will be the first time the city will
combine pavement and drainage/dredging work, so should help prepare for the
Karth Lake work. The sediment growth study of Karth Lake would likely include
a bathymetric (lake depth) survey and a design depth. This may result in a
recommendation for dredging some areas of Karth Lake.
The city cleaned grit chambers around Karth Lake last fall. They noted that some
are old and should be upgraded to an improved design in the 2026 PMP.
Further steps on hold pending study grant proposal opportunities in late 2023.
5.4. Open Meeting Policy. Susan Johnson and David Swearingen
5.4.1 Background: The City of Arden Hills’ position as of the April 2022
meeting was that, going forward, all KLID board meetings should be in-person
only and not offer a remote attendance option. The board was concerned that such
a policy could prevent board members and the public with immuno-compromised
health status from attending. Steve Scott presented this issue at the City Council
meeting on October 10, 2022. The City Council agreed that Zoom attendance at
the October 11, 2022 meeting would be allowed. The longer term policy would be
fully explained later. This issue is therefore not resolved.
Discussion: Per Susan Johnson, Minnesota’s open meeting laws relate to allowing
the public to observe meetings remotely but does not apply to board members.
The City of Arden Hill’s policy is compliant with Minnesota’s open meeting
laws, but does not guarantee that board members can attend remotely, except if
the board member is in a public place that allows others to physically join them.
That defeats the purpose of keeping an immuno-compromised board member safe
from harm. Board members can attend remotely only during a time of emergency
if the board member has a medical reason that necessitates remote attendance.
Since COVID-19 is no longer considered to be an emergency, the latter condition
no longer applies. Susan plans to work with legislators in an effort to remove the
phrase from the open meetings statute that this policy can only be done during a
state of emergency. As written, she feels that the policy violates the Americans
with Disabilities Act (ADA), so amendment to the open meeting statute might be
possible. Aisha Elmquist said the Council on Disability Rights might be a good
organization to connect with on this issue. Linda Hansohn said that if someone
were homebound but wanted to participate in the board, it might be undemocratic
to prohibit their participation.
This topic is resolved for now until relevant laws are amended.
5.5. Possibility of initiating a new study to identify status and refresh list of BMPs
for future management of Karth Lake: KLIDB and David Swearingen
5.5.1 Background: The most recent Karth Lake study and BMP identification
was performed in 2009. The board would like to identify a plan to be included in
a follow-up assessment of Karth Lake’s current health and opportunities for
improvement (BMPs). David Swearingen suggested that current or future grants
received by RCWD might be extended to include Karth Lake.
Action: Continue to discuss new lake study funding possibilities.
Discussion: David Swearingen noted that Kyle Axtell no longer works with the
RCWD. There was some discussion of identifying a new point of contact for the
City.
RCWD has received funding from the Minnesota Pollution Control Agency
(MNPCA) to address flooding resiliency. Since Karth Lake will flood if not
pumped, David feels a proposal to apply some of the MNPCA funding to study
Karth Lake would be appropriate.
As mentioned earlier, the 2026 PMP project will be written to include a study of
drainage to Karth Lake in 2025. The city plans to apply for RCWD’s $300 K.
annual water quality budget (a funding source for the BMP#1 project) to help
fund this 2025 study. This study should encompass multiple topics including rain
gardens, grit chambers, the BMP#1 drainage from the walking path to the lake,
sediment growth and the retaining wall replacement.
6. NEW BUSINESS
6.1. Plan process for next election of KLID Board Members and Officers whose
terms have expired.
6.1.1 Background: The terms for four board members expire in 2023: those for
Aisha Elmquist, Renee Marino, Linda Hansohn and Tony Peleska. The process
for announcing the April 2023 election and requesting candidates to fill open
positions involves the drafting of a letter to Karth Lake Improvement District
members (which are, by definition, Karth Lake shoreline property owners). The
City of Arden Hills then sends that letter to members by regular mail.
Action: Agree on the process and general content for drafting this letter to KLID
members.
Discussion: Only 2 positions are open: Linda’s and Tony’s. Renée’s and Aisha’s
terms are through 2024, not 2023 as stated on the agenda (the website is correct).
The main focus is to be inclusive and attract new participation. Kathy said about
4-5 houses on the south side of the lake will be sold soon, as the owners have died
or are no longer living there. Many current board members got involved soon
after moving in. There was a general discussion about how to identify new
homeowners so the board could reach out to them. The city has a tool to quickly
pull a mailing list of addresses, but it not pulled on a regular basis. Homeowner
names can also be accessed from the interactive property tax maps, but there is no
automated way to be notified of a new owner. Communication within the
education topic below could also help increase awareness for 2024 elections.
Although the preference is to attract new board members, Linda is willing to
continue on the board if she is needed. Aisha agreed to reach out to Tony to see if
he could do the same.
For the 2023 elections, we should prepare a new letter to KLID members that
David Swearingen can send to property owners. Renée to send last year’s letter to
the board for their input, then Kathy Johnson agreed to draft the new letter and
Renée to finalize and send to David.
6.2. Identification and onboarding of new City Council liaison and other
communications with City Council.
6.2.1 Background: Several new members were elected to Arden Hills’ City
Council in November 2022. A new liaison will likely be appointed by Mayor
David Grant to the KLID board. Last year’s onboarding of liaison Steve Scott
included a walking tour around the lake. At the last board meeting, the idea of an
annual tour of the lake was discussed and broadly supported.
Action: Discuss possible ways to educate new City Council members and the new
liaison about Karth Lake and the history and prospects for its management.
Discuss the possibility of a 2023 walking tour of the lake, including when, for
what audience and by whom.
Discussion: The new City Council liaison has not yet been appointed. Hold this
topic until that happens. The City Council has a big learning curve right now, but
the KLIDB might want to make a presentation to the City Council at some point
in the future. The last one was made over 10 years ago. This topic is on hold.
6.3. Education of lakeshore owners about disposal of leaves into lake.
Discussion: This topic should be expanded to a broader educational and outreach
goal and help increase interest in the KLID. A communications plan could include
face-to-face door-to-door outreach, a flyer, events, the website and other methods.
Gary shared a previous flyer. Kathy agreed to start drafting a new flyer. Any flyer
could be linked from the website. This topic will be addressed further at our next
meeting.
7. NEXT MEETING: Tuesday, April 11, 2023 at 6:30 PM at City Hall.
8. ADJOURN
Seed matures
then plant dies
Seeds in
seed pod
Flower detail
Flowering
Bolting
stem grows
Stem sprouts from root crown
Seedling
Germinating seed
PERENNIAL LIFECYCLE &
TREATMENT TIMING
mda.state.mn.us/weedcontrol
DIG ROOT
Remove seedling and root.
FOLIAR SPRAY
Spray leaves.
CUT AND TREAT
Cut stem at the base and
spray.
MOW
Mow before seed set to
prevent seed dispersal.
WEED TORCH
Burn seedling stage.
BIOCONTROL
Release designated biocontrol
agents on large populations.
Monitoring and repeated
management is necessary
for long term control of
established infestations.
PURPLELOOSESTRIFE
Lythrum salicaria