HomeMy WebLinkAbout78-050
,
>
.
.
~
Extract of Minutes of Meeting
of City Council
City of Arden Hills
Ramsey COunty, Minnesota
Beld; August 28, 1978
Pursuant to due call and notice thereof, a regular meeting
of the City COuncil of the City of Arden Hills, Minnesota, was
duly held in the City Hall in said City on Monday, the 28th day
of August, 1978, at 7:30 o'clock p.m.
The following melllbers were present: Mayor Crepeau and
Councilmen Hanson, Wingert, crichton and Woodburn; and the
following were absent: None.
Also in attendance were: Charlotte McNiesh, City Clerk
Administrator~ James S. Lynden of Stringer, Donnelly, courtney,
Cowie Ii Robleder, City Attorney; Donald Christoffersen of Short,
Elliot, Hendrickson, City consulting Engineer~ Donald Lamb, City
Treasurer, and Peter S. Popovich of Peterson, Popovich, Knutson
& Flynn, City Bond Consultant.
The City CleJ:k Administrator presented an affidavit
showinq publication of notice of hearing on the proposed assess-
ment for Improvement No. SS-W-P-77-2 in the New Brighton
Bulletin on August 10, 1978, which affidavit was examined,
found satisfactory, and ordered placed on file. The Clerk
Administrator also exhibited a Certificate of Mailing Notice
of Rearing to all affected property owners.
MAYOR CUPEAU: At this time I would ask the engineer,
Mr. Don Christoffersen, to explain the improvement.
MR. CHRISTOFFERSEN: This improvement includes the con-
struction of sanitary sewer, watermain, streets and drainage
on two separate plats - the Edgewater SOuth and the Heights of
Johanna Lake Additions. They are located generally north of
County Road 0 and east of Cleveland Avenue as shown on the
second drawing on the wall. The streets include concrete
curb and gutter and bitUlninous paving.
MAYOR CREPEAU: At this time would our fiscal consultant,
Mr. Peter Popovich, explain the financing of this project 77-2.
MR. POPOVICH: The total improvement cost is $116,770.00.
There is a total of 31 lots in the two plats. All of them
will receive an assessment of $3,887.00 each except one lot
which receives only sewer and water services. That lot will be
assessed at $160.00. The project will be 100% assessed.
There was no feasibility bearing because it was 100% petitioned
for. The assessments will be spread over a 20 year period of
time co1ll1llencing in 1979 with an 8% carrying charge unless a
prepayment is made within the next 30 days after the adoption
of the roll tonight, or by paying interest to the end of the
year in any year sbould they not pay within the next 30 c'lays.
The Mayor announced that the meeting was open for the
consideration of objections, if any, to said proposed assess-
ment. All persons present were then given the opportunity to
present oral objections, and all written objections theretofore
filed with the City Clerk Administrator were presented and
considered, and all such objections were tabulated as follows:
There were no written communications and no one appeared
to be heard.
councilman Crichton then introduced the following resolu-
tion and moved its adoption:
RESOLtrrION NO. 7cf..M
RESOLtrrION ADOPTING AND CONFIRMING
ASSESSMENTS FOR IMPROVEMENT NO. SS-W-P-77-2
BE IT RESOLVED by the City council of the City of Arden
. Hills, Minnesota, as follows:
.
l. The amount proper and necessary to be specially
assessed at this time for Improvement No. SS-W-P-77-2 against
every assessable lot, piece or parcel of land affected thereby
has been duly calculated upon the basis of benefits, without
, '
.
regard to cash valuation, in accordance with the provisions of
Minnesota Statutes, Chapter 429, as amended, and notice bas
been duly mailed and published, as required by law, that this
Council would meet to hear, consider and pass upon all objec-
tions, if any, and said proposed assessment has at all times
since its filing been open for public inspection, and an
opportunity bas been given to all interested persons to pre-
sent their objections, if any, to such proposed assessments.
2. This Council, having heard and considered all objec-
tions so presented, and being fully advised in the premises,
finds that each of the lots, pieces and parcels of land
enumerated in the proposed assessment was and is specially
benefited by the construction of said improvement in not less
than the amount of the assessment set opposite the description
of each such lot, piece and parcel of land, respectively, and
sucb amount so set out is hereby levied against eacb of the
respective lots, pieces and parcels of land therein.
3. The proposed assessments are bereby adopted and
confirmed as the proper special assessments for each of said
lots, pieces and parcels of land respectively, and the assess-
ment against each parcel, toqether with interest at the rate
of 8\ per annum accruing on the full amount thereof from time
to time unpaid, shall be a lien concurrent with qeneral taxes
upon sucb parcel and all thereof. The total amount of eacb
sucb assessment shall be payable in equal annual principal
installments extending over a period of twenty (20) years,
the first of said installments, together with interest on the
entire assessment from the c'late bereof to December 3l, 1979, to
be payable with general taxes for the year 1978, collectible
in 1979, and one of each of the remaining installments, to-
gether with one year's interest on that and all other unpaid
installments, to be payable with general taxes for eacb
consecutive year thereafter until the entire assessment is
paid.
4. Prior to certification of the assessment to the
County Auditor, the owner of any lot, piece or parcel of land
assessed hereby may at any time pay the whole or at least sot
of such assessment, with interest to the date of payment, to
the City Treasurer, but no interest shall be charged if
such payment is made wi thin 30 days after the c'late of this
resolution.
.
5. The City Clerk Administrator sba1l, as soon as may
be, prepare and transmit to the county Auditor a certified
duplicate of the assessment roll, with each installment and
interest on each unpaid assessment set forth separately, to
be extended upon the proper tax lists of the County, and the
County Auditor shall thereafter collect said assessments in
the manner provided by law.
.
.
The ootion for the adoption of the foregoing resol~tion
was duly seconded by Councilman Wingert and upon vote being
taken thereon, the following voted in favor thereof: All~
and the following voted against the same: None, whereupon
said resolution was declared duly passed and adopted.
~
~fZ1)~
~~