HomeMy WebLinkAboutCC 10-21-2002
.
.
.
~
~~!iILLS
MEETI.\1G MINUTES
APPROVED
CITY OF ARDEN HILLS, MINNESOTA
CITY COUNCIL WORK SESSION
MONDAY, OCTOBER 21, 2002, 4:45 P.M.
CITY HALL COUNCIL CHAMBERS, 1245 WEST HIGHWAY 96
CALL TO ORDER
Mayor Probst called the meeting to order at 4:47 p.11l. Present: Council Members
Beverly Aplikowski, David Grant, Gregg Larson, and Lois Rern.
Also present: City Administrator, Joe Lynch; Director of Operations and
Maintenance, Tom Moore; Director of Community Services, Aaron Pan-ish;
Superintendent of Operations and Maintenance Jim Perron; City Engineer, Greg
Brown; and Personnel Direetor/Deputy Clerk, Cynthia Young.
2.A OPERATIONS & MAINTENANCE: Karth Lake Pumpioe
Engineer Brown detailed the flow of travel of the water related to the Karth Lake
issue. He said there was concern from the Wyncrest Circle homeowners that
pumping may have caused moisture problems in their basements. He explained
that URS had checked out the physical restraints of the area stating the pipe is
much lower than the basement(s) in question. He said the water is high, and the
DNR did approve the pumping permit. Mr. Brown eXplained that the pumping
commenced two weeks earlier. Mr. Brown said all the manholes and storn1 lines
were in good condition. He noted that no drainage pipes were plugged.
The Work Session audience ineluded several residents with property which abuts
Karth Lake, and also neighbors who felt their property was affected by the
pumping and high water levels.
ARDEN HILLS CITY COUNCIL WORK SESSION MINUTES
OCTOBER 21, 2002
2
.
The Council members stated that the lake levels in Arden Hills were all at high
levels, not just Karth Lakc.
Councilmember Larson suggested the City continue the pumping procedure for a
short time, then stop. He said no empirical evidence of damage to property or
basements of homes had been introduced. Councilmember Larson said the
sentiment was to avoid pumping to the goal. Rather, pump to two foot level, stop
and assess the situation over the winter season, then spend more time on a
permanent solution.
Councilmember Aplikowski suggested that the pumping procedure should
continue until the next Council meeting, and the drainage pipes should be checked
for blockage.
Councilmember Grant stated the City should continue pumping, and look to a
longer term solution in the spring, but currently pump to levcls no lower than the
Ordinary High Water level (OHW).
. Councilmember Rem said she was not convinced the City should to go back to the
full pumping rate, stating half rate speed seemed to be working. She noted one
factor missing with this issue was the need for representation from the DNR and
the Rice Creek Watershed District. She recommended pumping continue for seven
more days at half rate, stop, and re-visit the issue mid-winter. She also
recommended the City televise the lines.
The Council received {attached several letters and a petition from Arden Hills
residents concerning the Karth Lake Pumping issue.
Mayor Probst suggested the City continue to pump at CLment levels and make a
decision at the Monday, October 28, 2002 City Council meeting.
The Council consensus was to continue pumping at hal f rate pace, televise the
stonn sewer, the City Engineer viOrk with Ms. Jacobson and any other rcsidents
regarding problems, and revisit the situation at the Monday, October 28, 2002
Council meeting.
.
ARDEN HILLS CITY COUNCIL WORK SESSION MINUTES
OCTOBER 21,2002
3
.
3.B COMMLNLTY SERVICES Guidaut Update
Dircctor Pan-ish stated that Guidant had submitted an application for a preliminary
plat and master plan PUD. He noted the Planning Commission held a public
hearing and made a recommendation to the Council on October 2, 2002 to approve
the preliminary plat with the recommendations as found in the October 15, 2002
staff report. He explained that Guidant proposed the following response as it
relates to the park dedication issue:
I. Provide an easement for the existing City trail that crosses onto the Guidant
Campus;
2. Provide public access to the trail systcm being developed within the Guidant
Campus;
3. Contribute $350,000.00 toward the constmction of a combination warming
house/activity center/picnic pavilion.
Director Parrish requested Council's input and direction.
. Councilmember Larson said he was not supportive of the proposal, stating his
concern was that the dollars spent on Cummings Park is not in line with the Park
Comprehensive Plan.
Councilmember Grant said he did not agree with Councilmember Larson.
Councilmember Aplikowski asked what a new building cost.
Director Moore stated he expected bids in at $350,000.
Director Parrish said he thought Guidant was less inelined to provide park fee,
when they are also making such significant public improvements.
Mayor Probst said when this issue initially came up, he felt uncomfortable with the
calculation of the park dedication fee, and suggested further discussion regarding
re-routing trails.
.
Administrator Lynch said the basic premise of the park dedication fee is to deal
with potential demand on parks, donate money on an annual basis, over the years.
.
.
.
ARDEN HILLS CITY COUNCIL WORK SESSION MINUTES
OCTOBER 21, 2002
4
Councilmember Larson stated he was not supportive of dropping $350,000.00 in
one park, when other shelters arc needed in the City.
Councilmember Rem asked if PTRC had reviewed the proposal.
Director Moore answered yes, and asked if there was a way to accomplish the idea
that this park is NOT Guidant's parle
After further discussion, the Council conscnsus was to "move down the Guidant
path", and commit to the $350,000.00.
3.B TECHNOLOGY MASTER PLAN
Director Parrish explained that staff prepared a Master Technology Plan for the
Council's consideration. He noted the plan sought to outline the strengths,
weakncsses, threats and opportunities relative to technology in the City. Mr.
Parrish said the plan had been reviewed by the City Management Team and other
staff members along with the Websitc Taskforce.
The Council briefly discussed the strengths of the document, citing the specific
strategic initiatives, and dirccted staff to bring forth an approval document at the
next Council meeting.
3.C I-35W BUILD-OUT STL'DY
Director Parrish presented the I-35W Build-Out Study, and requested Council
comment.
Mayor Probst suggested the Council dialogue conceming the I-35W Build-Out
Study to the November Work Session.
4.A 2003 Non-Bargaining Emplovee Benefit Renewal
Personnel Director/Deputy Clerk Young presented the Council with a summary of
the non-bargaining unit employees 2003 benefit, 2000-2002 benefit history, and a
summary of the salary and benefits costs. Ms. Young requcstcd Council review
and provide comments.
.
.
.
ARDEN HILLS CITY COUNCIL WORK SESSION MINUTES
OCTOBER 21, 2002
5
No comments from the City Council indicated any amendments to the 2003 Non-
bargaining Employee Benefits.
4.B 2003 Council Retreat
Ms. Young explaincd that she and the City Administrator had met with Marilyn
Condon of M.M. Condon and Associates to discuss the idcntification of thc nccds,
project outcomes and action plans for the 2003 Council Retreat. Ms. Young said
the first step in the process was that Ms. Condon would meet [infOlmally] with the
Couneilmembers, individually. She noted that Ms. Condon would then prepare
ideas set forth in those meetings as the basis for a 2003 Retreat Agenda.
The Councilmembers agreed to the approach and the consultant and requested staff
alert Ms. Condon that they wanted to arrange the informal meetings after the
Novcmber 5,2003 General Election.
4.C Emplovee Recognition Committee
Ms. Young reviewed the currcnt employee recognition staff voluntccr rostcr, and
also mentioned that the employees had been working on a staff newsletter. She
noted that the staff committee would be presenting a formal recommendation to thc
Council at its organizational meeting in January, 2003, but requested direction
from the Council at this time for Operations and Maintenance Worker Michael
McKinney, who retires October 31, 2002.
The City Council directed staff to purchase a gift equal to $10.00 for each ycar of
service by Mr. McKinney and also prepare a plaque honoring him for thirty-one
years of service to the City of Arden Hills.
After receiving brief Council comments, Mayor Probst adjourned the meeting
at 9:45 p.m. /1
Respectfully submitted, Cynthia Young - Personnel D'/'ectortJ,1eputy Clerk