. MINUTES
Informational Meeting of
T.H. 51 and snelling Avenue Median closing
Monday, November 23, 1992, 3:00 p.m.
Present were: Dorothy Person, City Administrator-Arden Hills;
Dan Winkel, Public Works Superintendent-Arden Hills; Dick
Roessler, Chair-Public Safety/Works Committee-Arden HillS, Jean
Lemberg, Member-Public Safety/Works Committee-Arden Hills, Brad
Lemberg, Arden Hills resident and President of Independent
Consulting Engineers, Inc. ; Janeen Kajer, resident; Jim Tolass,
Ramsey County Public Works; Dan Soler, Ramsey County Public
Works; Tom O'Keefe, MnDOT representative; Terry Maurer, city
Engineer-Maurer Stewart Associates; Dale HickS, Councilmember-
Arden Hills; Dick wedell, Ramsey County Commissioner Elect;
JoAnn Growe, Councilmember-Arden Hills; Beverly Aplikowski,
Councilmember Elect-Arden Hills.
Councilmember Dale Hicks convened the meeting.
Tom O'Keefe from MnDOT indicated that he works for the local
initiatives portion of MnDOT in that he is responding the citizen
request for information and alternatives for the Closing of Trunk
Highway 51 near Lydia and snelling Avenue. O'Keefe indicated
that per his October 23, 1992, letter the closing is a permanent
. closure in the minds of MnDOT. The closure of the intersection
as exists currently is a permanent closure. However, he had
prepared for concept alternatives for the city to consider and
possibility recommend MNDOT their preferred alternative.
1- Frontage road from Old snelling to Lydia. This is the
preferred MnDOT alternative due to the safety issue in
eliminating three entrances/exits onto T.H. 51-
2. Reconfiguring the intersection of Old Snelling, Hamline
and T.H. 51, turning this into a right angle and
opening again this intersection with a signal light.
3. Widening the County Road E bridge.
4. Continue with a permanent closure of the median.
The County representative Jim Tolass indicated that the traffic
studies at county Road E has shown that in January, 1991, 7,680
cars were travelling on county Road E at that intersection and in
March, 1992, the traffic count was 7,718. Therefore, no major or
substantial effect of the closure of T.H. 51 has been seen by the
County.
citizens indicate that there may be more traffic due to a
potential townhouse development.
Ramsey County indicated that work may be needed on the bridge.
. However, there are no plans at this time. Brad Lemberg indicated
that ADT may be acceptable. During rush hours and extremely busy
time periods, the bridge is difficult to travel.
MnDOT indicated if there is a frontage road that they will not
obtain the right-of-way. The local governmental entity would be
responsible for all costs of this frontage road. ...h.1(! ~U / r/ADh~
a~Ut(1.LL I]tf,y.
. , .
. MINUTES - Informational Meeting of
T.H. 51 and Snelling Avenue Median closing
Monday, November 23, 1992, 3:00 p.m.
Page Two
Jean Lemberg inquired about the costs and whether increased MSA
miles are a possibility. However, the State indicated those do
not seem to be potentials at this time but could be taken into
account given other changes.
Further discussion indicated a serious concern about wetlands in
that area, on the frontage road area, and also the need to
purchase land from Northwestern College in order to link to the
drive area.
Discussion also followed regarding County Road E bridge and
whether this was an alternative that needed to be considered.
General discussion agreed that this alternative was expensive and
did not address the concern of access onto Old snelling.
Primary discussion centered on changing the angle of the Old
Snelling and Hamline on the east side of T.H. 51 and
signalization of the intersection. The State indicated that the
City would be responsible for approximately one-fourth of those
. costs with one-half paid by the State and the other one-fourth
funded by the County on the Hamline side.
Further discussion identified that the frontage road is the most
costly. The reconfiguring of Hamline, Old Snelling Avenue, and
T.H. 51 with a traffic signal is not in the 5-year plan of the
County or State which may represent additional changes in their
systems.
County Commissioner Elect Wedell indicated a need for addressing
concerns of opening 1-694. The State indicated that current
planning designs exist for the reconfiguration of the T.H. 51 and
1-694 intersection and ramping.
Councilmember Hicks indicated the discussion regarding the
request from citizens on the reconfiguration of Old Snelling,
T.H. 51, and Hamline be identified as the potential priority
would be forwarded to Council. It is understood that the City
needs to initiate this discussion with the county and State in
order to move forward at that time. This issue will be brought
up at the City Council meeting.
It was also agreed by the group that a separate discussion needs
to follow regarding what alternative for diversion of traffic on
county Road E or the effect of that traffic on the County Road E
. bridge and the adjacent travel lanes to that bridge on each side
of the road.