HomeMy WebLinkAbout04-30-07 Item 7E, County Road H Interchange Improvement
~
~HILLS
Request for Council Action
Prepared By:
Dept:
Council Mtg. Date:
Final Action Needed By:
MW
--Atrministration-
April 30, 2007
April 30, 2007
Agenda Item:
Gollrtty ~~<lc:l__~-'_rt!~~~hCl"~ge Improvement Project
Budgeted Amount: N/A
Actual Amount: N/A
Funding Source:
7.E.
I. Approve First Amendment to the Preliminary Development Agreement with RRLD, LLC;
2. Approve Reso]ution No. 07-5] Relating to Financing of Project; Establishing Intent with Respect to
Reimbursement
- -------- ------
Staff recommends approval of First Amendment to the Preliminary Deve]opment Agreement with RRLD,
LLC and Reso]ution No. 07-51 Re]ating to Financing of Project; Estab]ishing Intent with Respect to
Reimbursement
=$'upp6rting DocoolejJtS,C {aifai'!i:edf C.
X Memo/Letter: Memorandum from City Administrator dated April 30, 2007
x Resolution No.: 07-51
Ordinance No.:
Engineering Recommendation:
Attorney Recommendation:
x Other:
First Amendment to Preliminary Development Agreement with RRlD, LlD
\\metro-inet\ardenhiJIs\Admin\City Administrator\Misc\200712-12-07 Cover Sheet RE 800 MHz payment.doc
~
~HILLS
MEMORANDUM
DATE:
Apri] 30, 2007
AGENDA ITEM 7.E.
TO: Mayor and City Council
FROM: Michelle Wolfe, City Administrator~
SUBJECT: County Road H Project:
Approval of First amendment to Preliminary Development Agreement
Approval of Resolution No. 07-5], Re]ating to Financing of Project; Establishing
Intent with Respect to Reimbursement
BACKGROUND
The City of Arden Hills is currently conducting a Master Planning process for TCAAP
redevelopment. As part of that project, several transportation improvements will be needed. In
terms of phasing and priority, it has been determined that improvements to the County Road H
Interchange will be the first improvement needed for the project. The City has been working
with the developer (RRLD) to identify funding options for this and other anticipated projects.
DISCUSSION
The strategy for County Road H funding is to attempt to secure federal funding. In order to
actually receive funding in time to meet the anticipated construction schedule (2008
construction), it is necessary to begin pre-design engineering. RRLD is willing to fund the pre-
design engineering work, however, is requesting that the City take steps to ensure that these
expenditures have the ability to be reimbursed if other funding is secured at a later time.
The anticipated budget for this work is $425,000. In order to meet the 2008 construction
timeline, pre-design work would need to begin May], 2007. Further delays will likely make any
construction in 2008 difficult to achieve. The benefit of starting the bridge work in 2008 is that
it a1]ows the possibility of substantial project completion and function at the end of2009.
There are two actions requested of the CounciL The first is to approve a First Amendment to the
Preliminary Development Agreement (PDA) with RRLD (attached). As Council is aware, the
approved PDA includes language regarding developer reimbursable costs. (Section 5(t) 2). This
expenditure for County Road H pre-design would become an additional item on Exhibit E of the
PDA. This means that if the PDA is terminated before its expiration, or the term expires with or
without an MDA, and the City within two years after the effective date of termination or
expiration enters into a definitive development agreement with another developer, then the City
will reimburse the developer for this cost under the terms described in Section 5 (f) (2) and
Exhibit E. The First Amendment to the PDA also states that the City will reimburse the
developer for pre-design costs if the City receives grant funds from the federal government, State
of Minnesota, Ramsey County, or Metropolitan Council during the term of the PDA.
The second requested action by Council is to approve Resolution No. 07-51 (attached.) This
resolution is proposed in order to establish the pre-design funds as eligible for reimbursement
should other funds be secured for the project. This resolution refers back to the First
Amendment of the PDA.
ACTION REQUESTED
1. Motion to Approve First Amendment to the Preliminary Development
Agreement between the City of Arden Hills and RRLD, LLC.
2. Motion to Approve Resolution No. 07-51 Relating to Financing of Project;
Establishing Intent with Respect to Reimbursement
Attachments
MW
\\metro-inet\ardenhills\Admin\City Adminislrator\Memo\2007\4-30-07 Memo RE c.R. H.doe
FIRST AMENDMENT TO
PRELIMINARY DEVELOPMENT AGREEMENT
TillS AGREEMENT is made and entered into as of this day of ,2007 by
and between the CITY OF ARDEN illLLS, a Minnesota municipal corporation (the "City"), and
RRLD, LLC, a Delaware limited liability company (the "Developer").
RECITALS
WHEREAS, the City and Developer entered into that certain Preliminary Development
Agreement dated March 30, 2007 (the "PDA"); and
WHEREAS, the parties have determined a need to amend the PDA as further described
herein;
NOW, THEREFORE, in consideration of the covenants and obligations of the parties
hereto, the City and the Developer hereby agree as follows:
1. Section 5 of the PDAis amended to add anew paragraph (g) as follows:
(g) The City and Developer have determined that the Development may require certain
improvements to the intersection of County Road H and Interstate 35W (referred to as the "County
Road H Project"). The City proposes to apply for grants from the federal government, the State of
Minnesota, Ramsey County and the Metropolitan Council to pay all or part of the costs of the
County Road H Project. However, in order to proceed with that project on a timely basis, the
Developer agrees to undertake and pay all costs of pre-design (and similar preliminary work that is
usual and customary for road and interchange projects) for the County Road H Project. The City
will promptly reimburse Developer for such preliminary costs if and to the extent the City receives
grant funds from any sources named above. Any Developer expenditures under this paragraph are
in addition to, and not part of, the City Reimbursable Costs described in Exhibit D. However, if and
to the extent Developer is not reimbursed for any County Road H Project pre-design costs during
the term of this Agreement, such costs incurred by Developer will be Developer Reimbursable
Costs, subject to all the terms and conditions of Section 5(f)(2) and Exhibit E of this Agreement.
The City has no obligation to reimburse Developer for any County Road H Project costs except to
the extent provided in this paragraph and Section 5(f)(2).
2. Exhibit E of the PDA is hereby modified to add as Item 8: Pre-design for County
Road H Project.
3. The PDA remains in full force and effect and is not modified except as expressly
provided herein.
IN WITNESS WHEREOF, the City has caused this Agreement to be duly executed in its
name and behalf and the Developer has caused this Agreement to be duly executed in its name and
behalf on or as of the date first above written.
CITY OF ARDEN IDLLS, MINNESOTA
By:
Its Mayor
By:
Its City Administrator
2
RRLD, LLC, a Delaware limited liability
company
By Ryan Companies US, Inc., a Minnesota
Corporation
Its Manager
By:
Its Vice President
3
~
~HILLS
CITY OF ARDEN HILLS
COUNTY OF RAMSEY
STATE OF MINNESOTA
RESOLUTION NO. 07-51
A RESOLUTION RELATING TO FINANCING OF PROJECT; ESTABLISHING
INTENT WITH RESPECT TO REIMBURSEMENT
BE IT RESOLVED, by the City Council of the City of Arden Hills (the "City"), as
follows:
WHEREAS, as part of the potential redevelopment of the Twin Cities Army
Ammunition Plant ("TCAAP") site in the City, the City anticipates the possible need for
certain improvements to the interchange of County Road H and Interstate 35W (the "County
Road H Project"); and
WHEREAS, the City intends to seek funds from the federal government, the State of
Minnesota, Ramsey County and the Metropolitan Council to provide funding for the County
Road H Project; and
WHEREAS, the City has also entered into a Preliminary Development
Agreement dated March 30, 2007 (the "Preliminary Agreement) with RRLD, LLC (the
"Developer"); and
WHEREAS, the Developer is willing to pay the cost of pre-design work for
the County Road H Project under terms of a First Amendment to the Preliminary
Development Agreement (the "First Amendment") to be entered into upon approval of this
Resolution.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City
of Arden Hills as follows:
1. The City proposes to undertake the County Road H Project, and directs the
Developer to pay costs of pre-design and similar preliminary work that is
usual and customary for road and interchange proj ects.
2. The City will reimburse Developer for such preliminary costs from proceeds
of grants received for such work, to the extent provided in, and subject to all
the terms and conditions of, the Preliminary Agreement as amended by the
First Amendment.
3. City staff, consultants and the Mayor and City Administrator are authorized
and directed to take all actions and execute any documents necessary to carry
out the intent ofthis resolution.
ADOPTED BY THE CITY COUNCIL OF THE CITY OF ARDEN HILLS
THIS 30TH DAY OF APRIL, 2007.
Stanley D. Harpstead, Mayor
ATTEST:
Michelle A.Wolfe, City Administrator