HomeMy WebLinkAbout07-16-07 Item 2A, PTRC Funding Discussion
~
~~HILLS
MEMORANDUM
DATE:
July 10, 2007
AGENDA ITEM: 2.A.
TO: Honorable Mayor and Council
Michelle Wolfe; City Administrator
FROM: Michelle Olson, Parks and Recreation Manager '1YlcP
SUBJECT: Funding Discussion with the PTRC
BACKGROUND
Recognizing that the City has almost no funding currently dedicated to park and trail
development and improvement, the City Council charged the Parks, Trails, and Recreation
Committee (pTRC) with identifying alternative funding sources. The PTRC has spent numerous
meetings researching and discussing possible funding concepts and alternatives. At the June 19th
PTRC meeting, the Comprehensive Plan Update was discussed. After reviewing the 1998
Comprehensive Plan and in particular, the Parks and Trail section, the Committee voiced
concerns that parks and trail development has been severely lacking. The 1998 Comprehensive
Plan identified issues very similar to the priorities and strategies established in 2002 and 2006 by
the PTRC. The PTRC believes that the plan indicates that very little progress has been made in
the past ten years with park and trail development. With TCAAP design standards progressing,
the PTRC feels very strongly that the integration of TCAAP parks and trails and the existing
Arden Hills is crucial. The City is obligated to maintain what they have and to develop missing
links to connect to the development on TCAAP. The existing community is divided by many
major roads, highways, and railroads. These transportation corridors provide excellent regional
access and mobility, but they separate neighborhoods and people from parks. Trail connections
are needed to tie the city together, create a comprehensive system of parks and trails, improve
safety and enhance the feeling of community.
The Park Fund can no longer be utilized for maintenance projects. In 2004, the Legislature
enacted several changes to the parkland dedication statute. The new law (statute 462.358,
subdivision 2b) specified that Park Dedication funds may not be used for ongoing operation and
maintenance. In 2006, this statute was modified to read that Park Dedication funds may be used
only for the acquisition and development or improvement of parks and must not be used for
ongoing operation and maintenance of parks. Therefore, maintenance projects will need to be
funded from the general fund in the future.
\\Metro-inet.us\ardenhills\PR&PW\Parks\Memos\Council Memos\Memo to CC regarding Park Funding Discussion with PTRC07-4.doc
City Council
Parks, Trails, and Recreation Funding Discussion
2
The PTRC has been discussing and researching various funding options for parks and trail
improvements, including an email survey to other City Park Departments and inviting Sue
Iverson, City Finance Director to attend two meetings. After requesting information from other
Cities, it became apparent that there are no clear cut trends as to how to fund park improvements.
However, the options that the PTRC found to be a possibility and should be discussed as future
funding strategies include:
.
Bonding - In order to bond, the City would need to have this funding source
approved by a referendum. This funding source would be utilized for specifically
identified projects. It cannot be used simply to increase a fund balance.
.
Park Referendum - Ifthe PTRC identifies a specific project that they feel is
worthy of a Park Referendum, they would bring forward to the City Council a
recommendation with the reasoning and justification for such a funding resource.
This would also require a resident vote and therefore, it would require a group
effort to help it become successful and pass. This funding source would be
utilized for a specifically identified project.
.
TIF District Funds - Use of funds after a TIP District expires is a possibility.
Once those properties come back on the tax roll, it is possible to allocate those
funds for a specific purpose. We have two TIP Districts, however, one will expire
in a couple of years and the other is further out in the future.
.
Levy Increase - The levy would only produce approximately $25,000 for every
1 % increase. This is not a significant amount of funding. However, City Council
could choose to increase the Park Fund Balance each year.
The PTRC also encourages the City to pursue other alternative funding sources whenever
possible such as:
.
Federal and State Grants - Grants can be extremely competitive and can be
difficult to obtain. Further, repeated efforts to solicit funding from this source
are crucial to success.
.
Cooperative Agreements - The City has attempted to secure cooperative
agreements through MNDOT regarding improvements to County Road E. While
the application for the bridge on County Road E was not successful, there will be
other opportunities for cooperative agreements in the future. However, this will
again depend on the specific project.
.
Sponsorships and Partnerships - Working with local businesses and
community colleges is strongly encouraged. The EDC Committee can help the
City establish working relationships with local businesses. While partnerships are
always welcome and a valuable part of the Parks system, they tend to be project
\\Metro-inet.us\ardenhills\PR&PW\Parks\Memos\Council Memos\Memo to CC regarding Park Funding Discussion with PTRC07-4.doc
City Council
Parks, Trails, and Recreation Funding Discussion
3
specific rather than supportive of general park operations or CIP lists. They are
typically not perceived as a revenue stream to fund CIP projects.
.
Municipal State Aid Fund - MSA funds are an important funding source for
City projects. Streets must meet certain criteria to be designated as MSA routes
and receive MSA funding. Further, we are only allotted a certain number of miles
(6.14) based on total miles of street (approximately 31) and are allocated funds
based on this mileage. If any of the allotted miles are not assigned to a route, the
annual fund apportionment is reduced. MSA funds can be used for trail
development on MSA designated roads. Several projects in the CIP would be
eligible for State Aid funding. Two projects that are listed in the CIP (Attachment
A) as utilizing MSA Funding in the near future should be discussed:
CP Rail Bridge and Countv Road E Bridge - The City Council asked staffto
bring back more information on MSA funding in order to make decisions about
these two projects. A summary of the current MSA balance and proposed MSA
funded projects in the CIP is attached for your review (Attachment B). Staff was
asked to verify that the cost estimates that have been prepared represent the
proposed projects accordingly. The CP Rail Bridge estimate is based on the
excavation of material and construction of structural support underneath the
bridge (i.e. retaining walls), construction ofretaining walls on either side of the
bridge to tie into the roadway elevation, and paving approximately 200 feet of the
trail directly adjacent to the underpass/retaining wall work. The estimate for the
retaining walls north and south of the bridge is conservative, because until a
design is complete, it is uncertain how extensive these walls will need to be. The
City of New Brighton was contacted to discuss the CP Rail on Old Highway 8
and compare that to what is proposed in Arden Hills. This trail was constructed in
1990 and is similar in design to what is proposed in Arden Hills. New Brighton
staff has been unable to locate information on the cost of the project.
The estimate to construct a cantilevered sidewalk along the County Road E bridge
has been reviewed as well. Staff feels comfortable with the current estimate.
However, for each year the project is not completed, the estimate should be
increased by ten percent to account for an increase in construction costs.
POLICY CONCEPT
The PTRC is requesting that the City Council consider establishing a dedicated fund for park and
trail enhancement. This would essentially serve as a Park Improvement Fund. Specific projects
would then be presented to the City Council from a priority list by the PTRC and by staff.
Projects completed and the amount of money utilized each year would depend on various
opportunities and identified needs. This Park Improvement Fund would be utilized for park and
trail development, renewal, and maintenance. The current Park Fund could still be utilized for
projects. However, as noted earlier, it would not be able to be used for maintenance.
\\Metro-inet.us\ardenhills\PR&PW\Parks\Memos\Council Memos\Memo to CC regarding Park Funding Discussion with PTRC07-4.doc
City Council
Parks, Trails, and Recreation Funding Discussion
4
As part of the Blue Cross, Blue Shield Grant, several workshops have been held to promote
active healthy lifestyles. Several of these meetings have been attended by City Staff and PTRC
Members. A strong message from these workshops was that trails should no longer be looked at
simply as a recreational benefit but should also be considered an alternative safe mode of
transportation. The PTRC feels that it is important that the City Council commit to the concept
of promoting active living. In order to accomplish this, the PTRC believes that annual financial
contributions should be considered. This would in turn accelerate the development of the
missing segments of trails, as they relate to transportation in the City of Arden Hills. If
developing this type of fund is a direction the City Council would like to pursue, below are cost
estimates to construct and seal coat a one mile section of pathway:
CONSTRUCT:
Eight foot Bituminous cost/mile = $110,000
Eight foot Concrete cost/mile = $150,000
SEALCOAT:
Eight foot trail cost/mile = $3,000
The listed costs are strictly material costs and do not include the following: Retaining walls,
utility relocations, drainage fixes, signs, striping, driveway reconstruction, ADA pedestrian
ramps, easements, labor and engineering. These estimates are included to facilitate a discussion
on a specific amount that could be allotted each year to the Park Improvement Fund. The PTRC
Strategies for Parks, Trails, and Community Building that were approved in 2006 are included
for your review (Attachment C).
RECOMMENDATION
The PTRC recommends the following to the City Council:
Short-TermlLong-Term: Establish a dedicated fund for park and trail enhancement (renewal,
development, maintenance and purchase of park and trail amenities). A specific amount would
be allocated to this Park Improvement Fund each year. Specific projects would then be
presented to the City Council from a priority list by the PTRC and staff. As a way to accelerate
development of the missing trail segments within the City system, a Park Referendum or
Bonding could be considered as potential funding sources.
Continuous: Grants, Cooperative Agreements, and Sponsorships should be pursued whenever
possible. Grant funds tend to be project specific and cannot be considered a replacement to a
continuous funding stream, but they are a needed supplement.
\\Metro-it~et.us\ardenhi11s\PR&PW\Parks\Memos\Council Memos\Memo to CC regarding Park Funding Discussion with PTRC07-4.doc
PTRC Fundine: Discussion
Julv 16. 2007
Attachment A:
5 Year CIP Spreadsheet
f'rojectDescrlption
ARDEN HILLS CAPITAL IMPROVEMENTS PROGRAM FIVE YEAR SUMMARY 2006~2011
REVISION DATE: January 18, 2007
Tolal Project Cost Ge7~~~ ~~filal Special Reve~ue Ger;e;;IIFUr.d Pu~lic Salety MnDOT Slate.l\id UtiliIFunds(5\ Comments
Perl< Fu~d Capital Fund Coop. A reeme~t Fur.ds{41 SlormWater Water Sanitary
2006 {Workina CaD.1 fund Balance Jan 1 - 2006 $ 6,213,340 $ 187,882 $ - $ 302,250 $ 95.550 $ 735,528 $ 416,012
2006 Ridgewood N.,;ghbmJlOoo Recon.truclion , 2.058,27g.00 , {1.000.58100) , {200.1lD0.00 ; (551.026.00 , (230,546.00) , (89.31>4.00) Updeled to include CMnge OrtJ8r #2
Recoru;tructLiflStalions#1,1tI1,#12.JtI3 , 35.000,00 , (35,000.00\ , Inee" Costsonl
'0> SeMmidlParkUnder ~ , 32.000.00 ; 32,000.00\ Counl Pro'eGI.Anlici tedEarliostConstruction ,~
CSAHOOLandscain Enhancemenls , 120.407.47 , 120.407.471 , Total ro'elcostsa roximatel $360.000.remainde' idb Ramse Count
s"mita Sewerl&IM~i alionWork Cil For~es) , 25.000,00 , (25000.00\ Need in ul from O&M on actual laoor/effort above normal bud elod labor and materials
Basketball/TennisCourIReMaml~alion. Ro al rtiUsand Floral , 12000.00\ ; 12,000.00\
3153SoorelineLaneDrivewa , 16.000.00 , 16.000.00
Vau Mn TowerAc~essRoad , 17.603.28 , 17.603.28\
AssessmenlPa .lEnler rise Fund Conlr./MnDOT SlaleAid estimatod , 311.000 , , , , 200,000.00 , 501,917 , 68,886 , 84,603 2oo5PMPStaleAid'eimbufSeme~tofS225.0oo IncludedinSlmm'NalerFundeontribulions
Totals for 2006 , (2.316.2811-75) , (843,591.75) . (32,lltIo.OO) , (212,000.00) , , 200,000.00 , (49,1011.{1O) , (161.662.00) , (1)4.761.00)
2007 t'Workina Cao.t Fund Balance Jan 1 - 2007 $ 5,369,748 $ 155,882 $ - $ 502,250 $ (144,659 $ 573,866 $ 351,251
2007PMP.MOIandOvenay , 764,500.00) , 532.000.00) , 200.00000) ; 20.000,001 . {2,50000) , (10.000001
2007Sealcoat , 100,000,00) , 100.000.00)
Old Hi hwa 10Sidewatklm ovements CP Ra~B,id e , 230.000.00 , 50,000.00 , 180,000,00 CoSlto, b,id aworkonl : I'al~ostsincluded as rl of Snell AvenyaReionalTrail " sed in 2010
StormPOndMainteMneeP,o' ct , 50.000001 , 50.1lD0,OO lncludes ROffiOval ot S~I De sits for Existin Cit Ponds
Sanitar &werl&1 M~i alionWork , 100,100.00 , '00.100.001
BaskalbatlrTennis Cou'IReMabil~alio~_Cummi , , 35.000.00 , 35,000,00
Erner enc VehiclePreem tion ,ernainderof ..m , 26.000.00 , 26.000.00
" ece 1900 Waler Tanker , 105.000.001 , 105.000.00 ,
Assessment Pa IEnla, rise Fund Co~tr./ MnDOT 5tala Aid estimated , 296.000 , , , , 190.076.00 , 261506 , 96.675 ; 108,786
Totals for 2007 , (1.410,600_00) . 1441,000.(0) , (85.000.00) , (200.000_00) , . (15.924.00) , 211,503.00 , 94.175.00 . (1.312.001
2008 (Workina Can.\ Fund Balance Jan 1 - 2008 $ 4,928,748 $ 70.882 $ - $ - $ 486,326 $ 66,849 $ 668,041 $ 349,939
2008PMP-Reconstrucl , 2.245,000.00) , 1.330,000,00) . (200.ooo.ilO) , 500,000.00) . 200000.00) , 15,000.00)
Count Road E Sidewalk 1m olffimenls Brid eSa mentNo'lhO tion , 376700,00 , 327,000.00 ; 49.700.00 9<id e Se menl South 0 lion. 534B,000 $299~CO<l r,,$.47kStaJeAid)
Count Road E Sidewalk 1m ovemams NOflhWal~ , 302,90000 , 302,800.00 SouthWalkSl48.300 StateA.;d1
Sanila,ySawert&lMiligalionWork , 100,100.00) , (100.100.00)
S!oTmPondMainloMnceProjecl , 50,000,00 , 50,000.00)
Re",,~SoulhWale,Tower 179,440.001 $copo basad upon resulls olinspect",n by KTATatOl. tne. (December. 2005 ) includes $24.300 for fanca
, 79.440.00 , and200/0forenineeri Screen and radin worl<oomlatedh O&M. not ;ncluded;~ cost
6a.~..tball/Tennjs CourlReMabililalion Ha7.elnll( , 15.000.00 ; 15,000,OQ
'" Tra,Sinaa , 25.000.00\ , 25.0oo.0Q\
5-10Picku , 25.000.00 , 25.000.00
AssessmentPa ./En1er rise Fund Conlr.lI.tnOOT Slate Aid estimaled , 440,000 . ; , , 190,076.00 , 295.340 , 150,651 , 164.073
Totals for 2008 , (3,219,140.00l . ~15,OOO.(0) , (45.000.00) , (2t5.000.00) , , 1152,524.00) , (254.660.00) . (128.7-69.00l , 48,973.00
2009 (Workin!-1 Cap.) Fund Balance Jan 1 ~ 2009 $ 4,013,748 $ 45,882 $ - $ 323,802 $ 187,811 $ 539,252 $ 398,912
2009PMP-Recons1ruGt , 1.233,800,00 , 683.900.001 ; 200.0DllOO) . 250.000.00) ; 50,000.001 . 150,000001
2009 Sealcoal , 77,000.00 , {77.00000) Includ~s 2,500forsea:Coatir>9 of Fir.. StalJOn;;<1 pafkinglol
Sto,m Pond Maintenance Pro'aot , 50,00000 , 50.000.00 I neludes Removal ot S~I De sits from Existin Crt Ponds
Sanilar Sewerl&IMili alionWo,k , 100,100,00 ; I tOO, 100.00\
6askelbalI/Tennis Courl ReMabilitalion Cilat13re , 15.000.00\ , 15.000.00
F.2504x4T,uek , 30.000.00 , 30,000.00
Grouoo.Maslarw/B'OOf11 , 30.000.00 , 30,000.00
FfaelsidePicku One Ten wi Hoisl , 35.000.00\ , 35.000.00
Re,,"ce.letlerTruck , 130.000.00 , 130.000.00
Asses"",,,,,tPa./Enle rise Fund ConlrJMnDOT State Aid ""timated . 347.000 , , , , 190,076.00 , 310,319 , 180.015 , 200.3fj5
Totals for 2009 , (1.701.Qotl.no) . 1638.900.00) . , (215,000_00) , , 19n.076.tlO , 1n.319.00 , 130.015.00 , 50,265_00
2010 IWorkina Card Fund Balance Jan 1 ~ 2010 $ 3,374,848 $ 45,882 $ - $ - $ 513,878 $ (177.492 $ 669,267 $ 449,177
2010 PMP. Re<:onstruct , 2.19$,000.001 , 700.000.00 , 200.(0000) , 800,00000) ; 350,00Q,00 , 130.000.00) , (15.00000) 5'00.000 of State Aid to be appli8dlo Stofm 3ewarCost.
Snellin AvenueRe ioMtT,a;1 . ElOO,OOO.OO , 800.000001 Research possib~~y of grants to fund lhis proiect Ce"didale for federal/unds"
Sanilary Sewe, 1&1 MiligalionWork , 100.100.00 ; 100,100.001
6askotbalI/Tennis Courl Rehabilitalion Cilateare , 15,000,00 . 15.00000)
F.3S00nel@Picku wi Dum , 82,000.00 , 82,000,001
ToroGrOUndsmaslerw/B(oorn , 32,000,00) , 32,000,00
Tractorw1621 Plow , 100.000.00 , 50.000.00) ; 50,000,001
Skid Sleer Loader/Soow SIOW<lr . 28,000.00 . (28,000.00)
As.essrnentPa ,/Enle' ,ise FundConlr./MnDOT SlaleAid estimated ; 529,000.00 , , 180.076.00 , 300.000,00 , 175,00000 ; 115.000.00
Totalsfor2010 , (3,332.100.00) , (1,143.000.00) , , (21S,000.00) , , ; (609.924.00) , (50.000.00) ; (5,000.001 , 59.000.00
2011 (Working Cap.) Fund Balance Jan 1 _ 2011 $ 2,231,848 $ 45,882 $ - $ - $ 103,954 $ 227,492 $ 664,267 $ 509,077
2011 PMP.R6Construct/M~laooOva,ia , 811000.00 , 498.000.00 . 200,000,00 , 50.000.00) , (50000.001 . 115.000.001
2011 Sealcoal . 120,000.00 . 120,00000\
SanilarySewe'I&IMi~ alionWor~ , 100,100,00 ; il00.'00,OOI
6asketballfTennisCourlRehabilitalion Cilateara , 15,000.00) . 15.000,00\
Groundsmastarw/6room , 34,00000\ ; 134000,00
9,ushCh; , , 50,000,00 , 50,000.00
F.250 D;asel Truck . 30,000,00 . 30,000.00
F.4500neToniPlaw , 62,000.00 . 102,00000
AssessmanlPa .I Enle ri,eFundConlr./MnOOTSweA.id e,t;matcd , 354000,00 ; , 190.07ij.()0 , 300,000.00 , 175.000.00 , t75.000,00
Tolalsfor2011 , (1.222,100.00) , (43-6.000.00) , , {215.000,001 , , ; 190,076.00 , 250,000,00 , 125.000.00 , 59,900.00
2012 Workina Cap.} Fund Balance Jan 1 ~ 2012 $ 1,793,848 $ 45,882 $ - $ - $ 294,030 $ 22,508 $ 789,267 $ 568,977
Unassi nedPro'ects
Wesl Round Lake Road Reconstruclion , 1500.000,00 , 1,100,000.00\ , ; 200.000,00 ; 50.000.00 , 150.000.00 Polentialto be Full Fundedb Oovelo ar'Amounl,nGeneraIFundinGludasS350.000fromTIF
WesIRaundLa~eTra' . 120000.00 , 120.00000\
CounlRoadDTral . 150000.00 . 150.000.00 T,me w.th Ramsa Count Roadim rovements
Le,i ton AverlUeT,ailresu,facin , 50000.00 , 50.000.00 Coslsun~nown allhishma
Sanita S""",rSa ,; and Aceass ROad at eSJt7 . 150,00000 , '50,000.001
(estJmated cost lor conWuction and 'nsp~ctianin 2009, ij20K,n 20010 dollars); iI done a. 2 projects.
ReconstrucleiflStations#1.#II,#12,#13 . 700,000.001 . , 700,000.00\ 11&13firotl&12second
SCA.DASstemlnSlallalion , 200,000,00 ; 25.000.00 , (175.000.00
" ace Pia Structure-ValentinePa,k , 55,000.00 . 55,000,00
Valentir;eParklm rovame~ls CostsunMownallhist,me
Gatewa SinsClevetandlCoRdOlexi 1000/96 lus2-3addilionallocalion , 180,000.00 , 180,000.00 Clavelaoo!Count RoadOs na5hma\edatS30.000
South Waler Tower Exteriof Coali aooeao , 150,000.00 , 150,000.00 Basedu neslima'eF'omKTATalor.lnc Dec~mber, 2005. neednolant",;aledbeFo,e2012
FondingSource
Notes
1 General Capital Fuoo includesPIR Fund, NonassessableSlreelFund, & Capilal Equipment Thislund is d,awn down for Initial project disbu,semenls (enginee'in 8er.dconstructio~conlractor)and Funded bV resLdent and business assassrnenl paymenls
2. Assumed IMt 5200,000 will be drawn from the general ruM anrlUaUy fo' streel improvemams
3 IncludosTIF Dislric12 (Round Lake Business District) and TIF Disl,ict 1 (Collage Voiles) . About 5200.000 TIF ~alanceava~ablefor projects
4 Slale Aid Fund balance assumes annual disbursemenl from MnDOT af $lGO,076 !>.ased upon cu,",,,,,t leveb over the pasl10 years. Funds roceived ffam Stale Aid are applied la tho General Fund or the Storm Water Fund, when appticable
5 Util~y Enterprise fund balances assume a net operating surplus aach yea' which i.direct<><llowards QP proiects. Enle,prise fund balan""s do toke ;~to accounl the anticipaled revenue from increased utility,ales which wero basod upon the 'tudy Too
Ufility ntes naad to be r......"amined ef rc.structu,ed if we ,,",sire Ie haY<> a h;ghecfund bala""" than is eurrcnlly p,ojected. Alternalively. W<I aitho, havo to SMlk other ,eY<>nue ,ouree or ~ul ba~k On projocts.
Current Ul~~y rate study goes thrau8h 2009. Rales fo, 2010 and 2011 aro e.timaws only
Addjfjonalcomments'
Itshoytdbenotedlhaffundbalaneewillandt:an~hangoradj""llyiftheprojectCosls changeorthc Cityfatls shorl on revenUe eollection or spending mO<El tha n-ilntic;patodon,epaj",.
PTRC Fundine: Discussion
Attachment B:
MSA Funding Spreadsheet
Julv 16, 2007
I-
a
0
c
2
E
-0 2 -0 -0 -0 -0
",- '" '" '" '"
-000 co co co co
"'0-0
Eo C E E .s E
.- ~:::l ~ ~ ~
tit--LL 00
<1>"'- '" '" '" '"
00 '" C .'!l .'!l .'!l .'!l
._ ffi- Q)
c-o E c c c c
.Q 2 Q) .Q 0 0 0
- '" '" co ~ ~ 'g
~ .9- 9 " " " "
..Q .2 <( .Q .Q .Q .Q
roc Q) OJ OJ OJ OJ
- '" > - 15 - -
Q-c:P 0 0 0
-ro~ C C C C
'" 5.c ~ => => => =>
" o It= 0 0 0 0 0
-
0 E20 E E E E
z <((1)0 <( <( <( <(
" ............... ..... .......... ..... ..... .....'" "'''' ..... .....
" 0>0>0> "l ~~ 0> 0> 0>0 00 0>0>
C triariu:i ~ ~~ r.....:r.....: Mcri cia trim
III " "" '" "'''' 0> 0> .....'" '" '" '" '"
OJ ............... co ~N N N "'<0 tqtq '" '"
llJ u5LIJm oi cir.....: ..:..... r-:N" N N ..:.....
o>~co ..... "'N ~;; 00> 00 00 co
"0 ""'N " ,,~ "'N ~~ "''''
c "''''''' '" "'''' "'''' "t
=>
u..
<(
CI)
::;;
c 0 0 0 0 0 0
0 0 0 0 0 0 0
'" <0 <0 <0 <0 <0 <0
III 0> ..... ..... ..... ..... .....
" ". 0 0 0 q o.
.Q N ci ci ci 0 0
OJ 0> 0> 0> 0> 0> 0>
~ ~ F ~
OJ '" '" '" '" '"
=>
c
c
<(
<('E 00 00 0 0 0
00 00 q q 0
CI) " cici cia 0 0 ci
::;; E 00 00 0 '" '"
" 00 .....0> 0
"0 '" 00 O>N 0
"
- ~ OON " 0 0
III => ~'" "'''' co
E.Q '" '" '"
.- E
- .-
'" "
wo::
0-- 00 00 00 00
(3 10 00 00 qq
"0 00 cici 00
w " 0 00 00 00
I 1;;U oq .....0> 00
l- E- 0<0 <ON otio
:;;g "'N .....0 0>0
~ "'.- N'" "'''' ~co
w 2 '" "'''' N'"
C/)
I- <L '"
0
W .<::
--, to
a 0
0:: Z
0-- C
0 Q)
w E
0 g""
Z (I) '"
:::J ",5: iD
LL
<( .g€ 0>
(I) 'C 0 I
2 f!JZ <(
,..c (I)
-"'-'" 0
Z rom .8
w ~ ~
2 0 Q) '" u:;
~ -0 -0
:::J ~ wen I
0 ww I~
a
0 I -0 -0
-0 '" '" ~
C9 ~ 0 0 Icl~
Z ~l~
;z 1:> .m c c
0:: I .~ .....0::0-- 0) c c en 0== ~ N
a 0 00--> 0 => => 0 "r"'"ID(5 ~ ~
5: ~ ~()W 0 0 0 0 oCC 0 0
<L N 00 N N(I)(I) N N
PTRC Fundinl! Discussion
Julv 16, 2007
Attachment C:
Strategies for Parks, Trails, and Community Building
STRATEGIES FOR PARKS, TRAILS, AND COMMUNITY BUILDING
STRATEGIES FOR PARKS
I. Disk golf course/Bocce golf course
The PTRC is exploring the idea of a disk golf course or bocce golf course because these
activities provide another way for citizens to eujoy our parks. The estimated cost is $7,500,
locatiou to be determined
2. Fenced dog park
While a fenced dog park has been proposed as a potential strategy, it appears that Ramsey
County is discussing the idea of adding a dog park to Tony Schmidt Regional Park.
Discussion of this option should follow that decision. Staff estimates the cost of this
development at $15,000.
3. Improve warming house conditions at Freeway Park and Hazelnut Park.
These parks see increased use during the winter months and the current warming houses are
inadequate. The condition ofthe warming houses has been addressed by Council action.
4. Study the feasibility of improving Valentine Park.
The park floods every spring due to the fact that it is at a lower elevation than Lake
Valentine. The play structure, warming house, and baseball field are routinely flooded.
Replacement ofthe play structure has been delayed several times due to these issues.
Information on costs and benefits of improving the park, and consideration of other options
for providing a park for the neighborhood, will lead to a future recommendation.
STRATEGIES FOR TRAILS
Trail development has lagged behind the City's investment in park facilities for a number of
years. The PTRC recommends development of an arterial or "core" trail system that provides
access to all areas of the community and in addition, provides needed access to the trail systems
in adjacent communities and to the regional trail system. The proposed trail segments also
become an integral part ofthe overall transportation network.
i. Tony Schmidt Park Railroad underpass
This improvement has been scheduled for construction this year and will provide improved
access to the Park from neighborhoods to the north utilizing already completed portions of
the Arden Hills trail network. It will also form a strong connection with other recommended
arterial trails, especially the anticipated Ramsey County trail connecting Tony Schmidt with
Long Lake Regional Park
PTRC Strategies for Parks and Trails
Page 2
2. Perry Park trail down to lift station road.
This trail connection will link Perry Park to the Tony Schmidt Railroad underpass. The City
will apply for a DNR Local Connection Grant for this trail segmeut. The grant has a 50%
match up to $100,000. The total estimated cost is $38,500.
3. West side of Old Snelling from Highway 51 on the south to County Road E on the north.
This portion of highway is tentatively scheduled for improvement during 2010. Building the
proposed trail as part of that project has obvious advantages. This trail segment is a key link
in the major north-south arterial through the city which will eventually connect the existing
Arden Hills with the new TCAAP development. This trail may be eligible for municipal
state-aid funding. In the future, this trail could be extended to Lydia along the west side of
Highway 51.
4. South side of County Road E from Old Snelling to Connelly
This very important trail links the eastern and western portions of the City, connects two
existing parks, provides access to businesses for people living west of Hwy. 51 and is an
important part of a longer east-west arterial traversing the city from west to east.
5. East side of Old Snelling from County Road E to Highway 96
This is a continuation oftrail segment 3 and would iuclude reworking ofthe railroad
underpass north of Lindey' s as well as some form of grade separation when the Highway 10
and 96 intersection is reconstructed.. This segment is crucial to improved circulation
between the existing and new portions of Arden Hills.
6. North side of Lake Johanna Boulevard from County Road E on the west to Old Snelling on
the east.
Development of this trail segment would complete the southern east-west arterial through the
city. It is heavily used now - year round - by residents, as well as students from Bethel and
Northwestern Colleges and Mounds View High School. That use is likely to increase with
the growing popularity of Tony Schmidt Park and the County's completion of the trailljnk
under the railroad (Segment I). Ramsey County has requested that the Metropolitan Council
designate Tony Schmidt as a regional park which will further increase its visitor use. As a
result, Arden Hills may be eligible for regional park funds to improve this trail and provide
safe access to the park.
7. Traffic signals at County Road E and Old Snelling
This intersection becomes a major connector in the arterial trails system and trails approach
and leave the intersection from different sides ofthe street.. For this reason, and because of
the increasing volume of traffic using the intersection, traffic signals are needed.
PTRC Strategies for Parks and Trails
Page 3
8. South side of Highway 96 from North Heights Church on the east to Old Highway 8 and
Long Lake Regional Park on the west.
This trail segment completes the northem east-west arterial through the city by linking with
the existing trails along Highway 96. It would provide better access to city hall and the
development in TCAAP as well as providing safe access to the land and water-based
recreational opportunities afforded by Long Lake Regional Park, the Rice Creek trail system
leading to the Mississippi River, and Tony Schmidt.
9. Elmer L. Andersen Trail Designation
The PTRC will be working with Ramsey County Parks and Recreation to determine the exact
location and length of what will be recommended as the Elmer L. Andersen Memorial Trail.
A naming guideline policy will also be presented to City Council for their consideration for
approval.
10. Safe Routes to School Trail along County Road E2 - including connection to Venus Avenue
The City, County, and School District will partner to apply for a grant through the Federal
Safe Routes to School Grant Program. The segment oftrail that is being considered is the
south side of County Road E2 from Old 10 to New Brighton Road and the connection across
the street in the Ramsey County Open space - connecting the neighborhood. There is no
cash match for this grant. However, it is a reimbursable grant.
STRATEGIES FOR COMMUNITY BUILDING
Annual Events-suggestions/examples:
Spring:
Summer:
Fall:
Winter:
Flower Planting
Celebrating Arden Hills
Buckthorn eradication
Kid's ice fishing contest, snowman building
STRATEGIES FOR APPROPRIATELY MAINTAINING EXISTING PARKS AND TRAILS
Maintenance of existing Parks and Trails in the City should be provided on a regular and
anticipatory basis.