HomeMy WebLinkAbout08-20-07 Agenda Item 2C, Discussion Regarding Hwy 10 and 96
~
~
EN HILLS
MEMORANDUM
DATE:
August 20, 2007
AGENDA ITEM 2.C.
TO:
Mayor and City Council
Michelle Wolfe, City Administrator
Greg Hoag, Public Works DirectorJ;!rA-
FROM:
SUBJECT:
US Highway 10 and CSAH 96
At the August 13, 2007 City Council Work Session, discussions were held regarding the
Highway 10 and County Road 96 project. Staff would like to continue the discussion on this
. project. We were working from a list of six questions and we were only able to discuss fIve of
the questions before the meeting adjourned. In addition, Councilmember Holmes had some other
questions that she wanted to address. (See all questions on page two). Staff would also like any
other City Council feedback related to this project.
With a Special Legislative Session to deal with transportation issues tentatively scheduled after
Labor Day, we feel it is important to move this project to the preliminary design phase as soon as
possible to be able to procure any special transportation funds that may become available. In
addition, there is a legislative committee that will be conducting tours related to projects
submitted for the 2008 capital improvement bonding process. The schedule has not been
determined but typically the tours are conducted in September and October. Continued
eligibility for state funds will likely depend on whether or not we have an approved concept plan
for the project.
For easy reference, I am attaching a copy of Mark Benson's July 27, 2007 memo regarding the
project development process for Highway 10 and 96.
Page 2
Highway 10 & 96 Discussion Qnestions:
1) Should the City of Arden Hills support a grade separated intersection at Highway 10 and
County Road 96?
2) Should Arden Hills support the continued reconstruction of CR96 the section to the west of
North Heights Church, continuing west to the City limits at I-35W?
3) Should the TCAAP property have access to Highway 10?
4) If there is a grade separated intersection at 10/96, should the connecting (turning) traffIc
between these two highways be directed through TCAAP or on the west side ofTHIO? Are
there options you feel exist but have not been properly explored?
5) If there is a more limited access on to THIO, how should access to the tip of the triangle be
accomplished?
6) What elements of noise remediation should the Council direct the preliminary design
engineers to consider in their studies?
Additional Questions Prepared by Councilmember Holmes*:
1. Compare costs to move the manufactured home community vs. costs to move Scherer
Brothers (obviously using reasonable estimates);
2. ConfIrm and give more information re: cost of moving manufactured homes. The way
I read this material, there is a limit to how much is reimbursed for homes. Need more
information on this.
3. Need engineering studies re: access between 10 & 96 through TCAAP rather than
mobile home park.
4. See if Army/AHA TS would allow access to TCAAP - even before building of the
community center. This would allow access to 96 and Hamline
5. Does a bike/pedestrian/car bridge from TCAAP to Scherer Bros. and mobile home
park make any sense re: a costlbenefIt analysis?
* At the conclusion of the work session discussion on Monday, August 13, Councilmember
Holmes indicated that most of her questions had been addressed during the discussion, but that
perhaps additional follow-up is needed on number four (4) above.
~
SEH
MEMORANDUM
TO:
Michelle Wolfe - City Administrator, and members of the Arden Hills City Council
FROM:
Mark Benson
DATE:
July 27, 2007
RE:
Project Development Process for Highway 10/County Road 96
SEH No. A-RY AC00704.00
At several recent meetings the public has raised questions related to design details and specific timelines
associated with the project development process for improvements to the Highway 10 and County Road
96 intersection (10/96)_ In many cases, the level of detail being requested is not available at this point in
the study process. However, the next phase of the project development process will be the appropriate
time to resolve and answer these types of inquiries. The purpose of this memorandum is to explain the
traditional highway development process that is required in order to advance a project ofthis type and
magnitude.
With any major transportation project a state and federal environmental review process must be followed.
The purpose of this effort is to ensure that a project is developed in a manner that meets the purpose and
need, while at Ihe same time resulting in the least amount of social, economic, and environmental (SEE)
impacts. For the 10/96 intersection project, an Environmental Assessment (EA) has been determined to
be the required document to satisfy both the stale and federal environmental review requirements. An EA
is a full disclosure document that presents the impacts of the preferred alternative and compares them to
thai of a no-build alternative. In addition, the EA will conclude whether or not an Envirorunentallmpact
Statement (EIS) is required due to the level of significance of the impacts.
Shown below is the project development process.
Highway 10/County Road 96
Project Development Process
July 2007
Planning Phase
~""
p.~E
.aU'
--
(8 Monlhs)
Preliminary Design Phase
--
(16 Months)
Final Design and
Right-of-Way Acquisition
Bidding and
~ Construction
Establish Project
Purpose and Need
.. Resolve Neighborhood Issues
.. Prepare Final Construction Limits
.. Refine Preliminary Design
.. Relocate Homeowners/Business
Develop Concepts
.. Conduct Impact Assessment for
Refined Design and No-Build
.. Prepare Final Construction Plans
Choose Preferred
Concept
.. Prepare StatefFederal
Environmental Assessment
- Conduct Noise Analysis
- Delineate Wetlands
- Prepare Relocation Plan
for Affected Homeowners
- Analyze other Social,
Environmental, and
Economic Impacts
Short Elliott Hendrickson Inc., 3535 Vadnais Center Drive. St. Paul, MN 55110-5196
SEH is an equal opportunity employer I www.sehinc.com J 651-490.2000 I 800.325.2055 I 651-490.2150 fax
~ Acquire Remaining Required Property
. Develop Construction Staging Plan
. Obtain Construction Pennits
Project Development Process for Highway 10/County Road 96
July 23, 2007
Page 2
As illustrated in the graphic on the previous page, there are four primary phases to a typical highway
improvement project; I) planning phase, 2) preliminary design phase, 3) final design/right-of-way
acquisition phase, and 4) construction phase. The 10/96 project is currently in the first phase (planning)
where the purpose and need for a project is substantiated and conceptual drawings are developed to solve
the identified problem. The second phase (preliminary design) is where the process becomes more
rigorous and delails studied and resolved. There are two principal components of the second phase; one is
to assess the project SEE impacts, and the other is to refine the design to avoid and/or minimize SEE
impacts. This phase in the project development process must be completed and a public hearing held
before any land can be purchased. Typically this phase requires 8 months or more to complete. Specific
to 10/96, there are two particular issues that will require extensive study during the preliminary design
phase; the issue of highway noise and the need to determine an approach to relocating several affected
residents within triangular area bordered by 1-35W, Highway 10 and County Road 96. Both of these
issues are normally studied and resolved during the environmental review process.
A detailed noise analysis will be conducted to determine the current noise levels at residential areas near
the proposed 10/96 improvements and what the future noise levels are projected to become with and
without the proposed improvements_ This information will be used to compare noise levels within the
project area with state and federal noise standards. Where standards are exceeded, noise mitigalion
studies will be conducted. This will ultimately include the analysis of the feasibility and cost
effectiveness of noise walls. 1 would suggest that the limits of this noise study extend south of County
Road 96 to 1-694 so that current noise issues along Highway 10 can also be studied at this time. The noise
mitigation study results will be used by the City, Mn/DOT, and Ramsey County to determine if noise
abatement should be included in the project.
The relocation study will first determine every effort available to minimize the number of relocations
necessary through the project design. This study will encompass the entire triangular area bordered by 1-
35W, Highway 10 and County Road 96. Once the number of relocations is delermined a study of
available housing will be conducted. It is expected that the stick built homes and any businesses will be
handled in accordance with the Uniform Relocation and Real Property Acquisition Act. For the
manufactured homes a more extensive up front effort is anticipated due to the number of potential
relocations. Initially we will determine the number of available lots (vacant or for sale) within Arden
Manor. In addition, the owner of Arden Manor will be consulted to determine if additional lots could be
created through expansion within the development. The relocation study will next begin an outward
search to inventory the surrounding manufactured home communities to determine the available vacant
lots and manufactured homes for sale. The results of this effort will be documented and made available to
the public. In addition, an extensive outreach effort will be undertaken to explain the findings along with
the relocation process that will be followed ifthe project is advanced to the next phases.
The EA will include documentation of the above special studies along with a full review of all the SEE
impacts normally studied. The EA must be reviewed and approved by the City, Mn/DOT and Ramsey
County. The EA will be published and distributed for public/agency review and a public hearing will be
held during the required 30-day comment period. Once the comment period is over a Negative
Declaration on the need for an EIS and a Finding of No Significant Impact will need 10 occur prior to
proceeding with Final Design and Right-of-Way acquisition.
Project Development Process for Highway 10/County Road 96
July 23, 2007
Page 3
As shown on the project development process graphic, the right-of-way process is assumed to take 16
months and will occur concurrently with final design. In total the first three phases of the process
typically take over 2 years to reach the point that construction of the improvements could occur.
We felt that eXplaining this process to the City Council was important to clarifY how comprehensive and
long in duration this next phase is. This pre-established project development process ensures that any
impacted homeowners will be given adequate time to relocate should the project process conclude a build
decision and if funding is obtained for the improvements. It is important to emphasize that completing
the preliminary design phase does not obligate the City to build the project. Rather, it helps all project
stakeholders to better understand the project impacts, it assists in securing project funds because it shows
whether or not the project is feasible to construct, and finally it allows necessary right-of-way to be
acquired if the city decides to proceed with the improvement project.
mdb
c: Greg Hoag - Public Works Director