HomeMy WebLinkAbout09-24-07 Item 4G, Cummings Park Hard Court Restoration
~
~HlLLS
Request for Council Action
Agenda Item:
..................--..-sudgefed Amo"unE~............,~.~.~1Q9:Q~=__~~!.!~!i!_P!~1~~t
Actual Amount: $6,440 - engineering
Funding Source:__~ __ ____ _ ......_._.___.__~_f'ark Fund.
4.G.
Prepared By: Michelle Olson "11ltf}
Dept.: Public Works
Council Mtg. Date:-------..-.--.-.--.--.......::'::!~ef~~r!i~~!)~~~QQt::::-.-
Final Action Needed By: September 24, 2007
~lllijjPif~~lioii'lRsgIii~f!iitl!i~0!fl1lt<!il1wrii_____________________________________________________________________________________________________.
iMotion to approve a Proposal dated September 10, 2007 and Authorize Staff to Contract with WSB & Associates for engineering services fori
ithe Cummings Park Hard Court Restoration Project in the amount not to exceed $6,400 for basic services. .
~j(fffjR~ii~t!~lTmfu~;fffi?:r~~'[4lliL__~__________._._.,._..,..,..,............."..."."_."_""_______._..._............................"."."___"________._...........".........."."..."._."_"____________,___.__....................__."_.".""______.._.............
iStaff recommends a motion to approve a Proposal dated September 10. 2007 and Authorize Staff to Contract with WSB & Associates for
lengineering services for the Cummings Park Hard Court Restoration Project in the amount not to exceed $6.400 for basic services.
I
,
,
i
i
._.i
r~jJf~mllJg1W~ggIng~m_~lilfficft~lliā¬llil
i X i Memo/Letter: .
i"."-+------- -.-.-.,
! iResolution No.:
Memo dated September 19, 2007 from Michelle Olson, Parks and Recreation Manager.
, : Engineering Recommendation:
r-lA;;~ey Recommendation:
i--"-"--f"---"---------...-.-..............".".-"--"-"-"--------,,-.---
, ,
: X lather:
l..........1...."....".......___.___
I
,
i
,
,
,
."",
!
i iOrdinance No.:
r------t------ ..................."".----
.JiroposarDate(rseptember:fo~.-2007..frt)"m-.WSEr&.ASsoCiiltes~"-------
Staff does not anticipate that this project will need to go out for Iiid. --However;.""if'competlfh,e...q"li'otes-come---fn....ov.er".$5Cf.-ooif;.'the-"'blifc1ing--
process could delay project completion until spring. 2008.
.......".".".""._._______._..J
\\MetroMinet.us\ardenhills\PR&PW\Parks\Memos\Council Actions\Engineering M Cummings Hard Court Reconstruct07.doc
~
~
EN HILLS
MEMORANDUM
DATE:
September 19,2007
AGENDA ITEM 4.G
TO:
Mayor and City Council
Michelle Wolfe, City Administrator
Michelle Olson, Parks and Recreation Manager mcf)
FROM:
SUBJECT:
Approve a Proposal dated September 10, 2007 and Authorize Staff to
Contract with WSB & Associates for engineering services for the
Cummings Park Hard Court Restoration Project in an amount not to
exceed $6,440 for basic services.
BACKGROUND
On July 10, 2006, at a Regular City Council Meeting, the tennis court maintenance plan was
discussed. The City Council made the decision to budget in 2007 for a complete reconstruction of
the Cummings Park Hard Courts. It was concluded that these courts have cracks that cannot be
resolved by simply resurfacing. The pavement needs to be removed and the subgrade needs to be
evaluated and re-graded. Mounds View High School just recently had their courts reconstructed for
similar reasons; the City contributed $8,750 toward that project.
BUDGET
Staff budgeted $35,000 for the Cummings Park Hard Court Project in 2007. Plans and specifications
are needed to ensure accurate quotes and project quality. Staff had anticipated utilizing the City
Engineer for this project. However, due to time constraints it was determined that it would be more
efficient to utilize the recently approved Engineering Pool. Therefore, quotes were solicited from the
four firms in the Municipal Projects Pool. Staff received quotes from all four firms. Amounts
proposed are below:
Plans and Specifications Construction Observation
(Optional)
Bolton & Menk, Inc. $8,990 $55-$120 per hour
Kimley-Hom and Associates $10,300 $90-$115 per hour
McCombs Frank Roos Associates, Inc. $7,500 $65-$112.50 per hour
WSB & Associates, Inc. $6,440 $83.00 per hour
\\Metro-inet.us\ardenhills\PR&PW\Parks\Memos\Council Memos\Engineering - Cummings Park Tennis2.doc
Engineering - Cummings Park Hard Court
9/1812007
Page 2
After reviewing the proposals, staff recommends that we engage WSB & Associates to complete this
work at a labor cost not to exceed $6,440.
Staff requested that construction observation be included in the RFQ as an optional cost. The City of
Roseville's engineering staff may be able to complete this work, however, that will not be able to be
determined until a more detailed construction timeline is known. Since the number of hours required
for construction observation is dependent on the contractor's schedule, we have provided the hourly
rates for this task. rfWSB & Associates, Inc. would be utilized for this optional service, their rate for
construction observation is $83 per hour.
PROJECT SCHEDULE
Staff has set an aggressive schedule for the engineering and construction of this project, with
completion occurring this fall. Staff does not anticipate that this project will need to go out for bid.
However, if competitive quotes come in over $50,000, the bidding process could delay project
completion until spring 2008.
RECOMMENDED COUNCIL ACTION
Motion to Approve a Proposal dated September 10,2007 and Authorize staff to Contract with WSB
& Associates for engineering services for the Cummings Park Hard Court Restoration Project in an
amount not to exceed $6,400 for basic services.
..
WSB
& Associates, Inc.
Infrastructure I Engineering I Planning I Construction
701 Xenia Avenue South
Suite 300
Minneapolis, MN 55416
Tel: 763-541-4800
Fax: 763-541-1700
September 10, 2007
~
Ms. Michelle Olson
Parks and Recreation Manager
City of Arden Hills
1245 West Highway 96
Arden Hills, MN 55112-5743
Re: Proposal for Engineering Services
Cummings Park Hard Court Restoration
WSB Project No. 0157-070
Dear Ms. Olson:
On behalf of WSB & Associates we are pleased to present this proposal to you as it relates to
plans and specifications for the hard court reconstruction of Cummings Park in the City of Arden
Hills. The improvements include replacement of existing tennis and basketball courts.
WSB & Associates will perform the following services:
Field Survey: We will complete a boundaryltopographic survey over the affected project area
and prepare a base map to be used in final design. The survey will be based on the Ramsey
County Coordinate System. We will also include the approximate location of private and public
utilities based on as-builts provided by the City and through a Gopher-One-Design design locate
(other public and private utilities).
Final Design: This will include preparation of plans and specifications necessary for final
construction. Our documents will include the following:
. Removals
. Site plan including grading and drainage
. Asphalt pavement design and details
. Erosion control plan and erosion permit from Rice Creek Watershed District
. Specific technical specifications
. Engineer's opinion of probable construction cost
We will also provide a recommendation for salvaging or replacing existing nets, posts, fencing
and other applicable items. We will base our recommendation on the quality and function of the
item and provide a cost comparison for installing new materials verses salvaging the existing
items. In addition, we will be available to help solicit quote/bid proposals for the project and
review contractor bids.
Minneapolis I St. Cloud
Equal Opportunity Employer
P:IArdcn HillsU-TR proJlOsal Cumming Palk.()157.1)71i,doc
Ms. Michelle Olson
September 10, 2007
Page 2
Construction Staking: We will complete the construction staking necessary to complete the
project.
Construction Observation (Optional): WSB & Associates will provide construction
observation at the City's request. We have construction observers available who have specific
experience with park projects.
Proiect Timeline, Total Cost, and Deliverables: WSB & Associates will provide the above
scope of services for fee outlined as follows:
Item Schedule Cost
Field Survey September 14,2007 $952
Final Design September 26, 2007 $4,672
Construction Staking October 10, 2007 $816
Total $6,440
Construction Observation (Optional) October 10, 2007 $2,822
We have attached an hourly break down of our costs. Billing for the project will occur on a
monthly basis. All permit fees will be billed as reimbursable expenses over and above our final
design fee.
Kev Personnel: Diane Hankee will be the project manager and the primary contact with City
staff on this project. Jay Kennedy will be in charge of overall quality assurance and quality
control for the project.
Thank you for the opportunity to submit this proposal to you. If you have any questions
regarding the proposal, you can contact either of us at 763-541-4800.
Sincerely,
WSB & Associates, Inc.
C/'\ ~
/ i . J I
~:j!lc:.tU? . j~
Diane Hankee, PE
Project Manager
~~
Principal
Enclosure
P: lArde" Hill.,ILTR pmp(J,ml Cumming ParJ:-OI57-V7{!,d~c
..
WSB
Estimate of Cost
Cummings Park
Hard Court Restoration
City of Arden Hills
& Associales, II/c.
Estimated Hours
, Project Engineering i Construction i 2-Person
Project I Total
Principal Manager Engineer: Tech i Observer i Survey Crew Hours Cost
Task Description ...
I Field Survey . 7 7
.. . $952.00
-----16 ----- . ----- ------- -
2 Final Design 4 16 12 .-- ,--- 48 $~!672.00
, I
3 Construction Staking 6 6 $816.00
Subtotal Cost , I $6,440.00
-- , i
4 COlIstrllctionObservatioll(()pti~nlll) 34 $2,822.00
HourfyCosfs $130.00 $]02.00 $74.00 $102.00 . $83.00 $136.00
Total Direct Labor Costs $520.00 $1,632.00 $888.00 $1,632.00 $2,822.00 $1,768.00 $9,262.00