Request for Council Action
Prepared By: Kristine Giga, Civil Engineer
Council Meeting Date: January 12, 2009
Hold Public Hearing for 2009 PMP- Glenarden Neighborhood Improvement
Budgeted Amount:
$2,340,000
Estimated Actual Amount:
$1,948,815
Funding Source:
PIR, Enterprise Funds,
Special Assessments
Recommendation:
1. Hold Public Hearing for 2009 PMP- Glenarden Neighborhood Improvement
Supporting Documents:
1. Memorandum from Civil Engineer Kristine Giga dated January 8, 2009.
~
MEMORANDUM
DATE:
January 8, 2009
TO:
Mayor and City Council
Ron Moorse, City Administrator
FROM:
Kristine Giga, Civil Engineer
SUBJECT:
2009 Pavement Management Program-
Ordering Plans and Specifications
BACKGROUND
On January 12, 2009, a public improvement hearing will be held for the 2009 PMP project. Once
the hearing is closed, the next step in the process is for the City Council to order the
improvements and preparation of plans and specifications.
DISCUSSION
The following is a brief summary of proposed improvements; for more detail, please reference
the feasibility report.
Street Improvements
The following table summarizes existing and proposed street widths for each street.
Existing Street Width Proposed Street
Location (Pavement Edge to Width (Face of Curb
Pavement Ed~e) to Face of Curb)
Arden Place 30' - 3 I ' 28'
Glenarden Court 24' - 25' 24'
Glenarden Road 25' - 32' 28'
IF orest Lane 25' - 30' 28'
Skiles Lane (Snelling Ave to Glenarden Rd) 24' - 28' 28'
Skiles Lane (Glenarden Rd to End) 24' 24'
Snelling Frontage Road 22' - 23' 24'
During final design, the project team will evaluate the possibility of narrowing certain street
segments, Skiles Lane between Old Snelling Avenue and Glenarden Court in particular, to
\ \Metro-inet.us\ardenhiHs\PR&PW\Engineeling\Council_ Actions\2009\1-12-09Memo _ 2009PMP _ OrderPlansSpecs.doc
2009 PMP
1/8/2009
Page 2
reduce tree impacts. At the December 8, 2008, City Council meeting, staff was asked to look
into street width design standards that had been established in 2001. The following lists the
recommended street widths for various street classifications.
Communitv Street:
Provide access to the residences, institutions and businesses on that street, providing a
route through the neighborhood or business district for residents of other neighborhoods.
(6.0 miles throughout City)
Street Width: Case Specific, (32 ft. minimum)
Neil!hborhood Street:
Provide access to residences on that street and provide a route through neighborhood for
residents on other streets. A large proportion of trips have neither an origin nor
destination on that street. (4.5 miles throughout City)
Street Width: 30 ft. minimum
Residential Street:
Primarily serve adjoining residents with little or no through traffic. Almost all trips have
either an origin or destination on that street. (18.5 miles throughout City).
Street Width: 28 ft. minimum
Special Cases:
Definition: Streets which do not fit into any of the three above descriptions and have a
very low usage, (1-3 residences), streets which provide secondary access (i.e. alleys) or
streets defined by extreme limitations due to narrow ROW, topography etc. (0.3 miles
throughout City)
Street Width: Case Specific
The streets in this neighborhood are considered residential streets. Staff is recommending 28'
street width throughout the neighborhood, excepting Snelling Frontage Road, which has homes
along one side of the street only, and areas where impacts to trees could be reduced by a
narrower street.
Utilitv Improvements
Watermain
No major water main repairs are proposed as a part of this project. There have been few water
main breaks in the area in last 10 years. It is anticipated that some gate valves and hydrants may
be identified as needing replacement during final design.
Sanitary Sewer
No major sanitary sewer improvements are proposed. A few segments of pipe will be replaced,
where lining or other trenchless technologies cannot be applied because of sags in the pipe.
Manholes with structural deficiencies will be rehabilitated in an effort to reduce inflow and
2009 PMP
1/8/2009
Page 3
infiltration. Chimney seals and solid manhole covers will also be placed on all sanitary sewer
manholes.
Storm Sewer
The existing storm sewer system will be improved and expanded throughout the neighborhood.
Best management practices, such as rain gardens, infiltration swales, and other features will also
be incorporated into the project in order to meet the Rice Creek Watershed District's water
quality requirements.
FINANCIAL IMPLICATIONS
The estimated total project cost for the improvements is $1,948,815.33, including engineering
fees. Consistent with the Assessment policy, an additional 37% overhead for the street
improvements has been included, which was used to calculate preliminary assessment rates. The
overhead is broken down as follows:
City Administration
Design Engineering
Construction Engineering
Legal
Fiscal
Interest During Construction
Assessment Roll Preparation
Contingencies
TOTAL
2.5%
10.0%
10.0%
2.0%
3.0%
4.5%
1.0%
4.0%
37.0%
The City's portion of the project costs are currently budgeted from the PIR and Utility Enterprise
Funds (sanitary sewer, surface water and watermain funds). A project cost summary is listed
below.
Pro.ieet Cost Summary
Roadway Improvements* $ 1,564,639.33
Watennain Improvements** $ 20,228.00
Sanitary Sewer Improvements** $ 42,146.00
Storm Sewer Improvements** $ 321,802.00
Total Pro.ieet Costs $ 1,948,815.33
* includes 370/0 overhead
** includes 300/0 engineering & contingency
Amount received from assessments $ 782,319.66
Amount funded by the City (including assessment of City parcel) $ 1,166,495.67
2009 PMP
1/8/2009
Page 4
ASSESSMENTS
As detailed in the feasibility report, the preliminary assessment roll includes 91 residential
equivalent units (REV). The estimated assessment rate per RED is $8,596.92.
RESIDENT COMMENTS/CONCERNS
At the neighborhood meeting, several comments and concerns were raised by the residents. The
most common were driveway material, drainage, and assessments.
Residents were concerned about the City standard of concrete aprons at each driveway,
especially if the rest of the driveway is not concrete, and the aesthetics once the project is
complete. While concrete aprons are recommended to help improve drainage and keep run off
within the street, they are not required. Staff recommends constructing concrete aprons only
where necessary to manage drainage concerns; the remaining driveways would be replaced in-
kind.
Residents throughout the neighborhood expressed specific drainage concerns. The project team
will work individually with these residents during final design.
Many residents were also concerned about the timing of this proposed assessment, given the
current economy. The City Council will have an opportunity to discuss these concerns prior to
adopting the preliminary assessment roll and ordering the assessment hearing, which is
scheduled for late spring. However, the Council may want to consider extending the payment
period from 10 years, as stated in the assessment policy, to 15 years.
RECOMMENDED COUNCIL ACTION
At this time, staff recommends the adoption of Resolution 2009-002: Ordering Public
Improvement and Preparation of Plans and Specifications for the 2009 Pavement Management
Program. Minnesota Statutes state that the adoption of this resolution requires a four-fifths vote.
~
~HILLS
CITY OF ARDEN HILLS
COUNTY OF RAMSEY
ST ATE OF MINNESOTA
RESOLUTION NO. 2009-002
A RESOLUTION ORDERING IMPROVEMENT AND PREPARATION OF PLANS
AND SPECIFICATIONS FOR THE 2009 PAVEMENT MANAGEMENT-PROGRAM
WHEREAS, a resolution of the City Council adopted December 8, 2008, fixed a date for
a Council hearing on the proposed improvement of the following streets:
Arden Place, from Old Snelling to Glenarden Road,
Glenarden Court, from Skiles Lane to Glenarden Road,
Glenarden Road, from Old Snelling to cul-de-sac,
Forest Lane, from Old Snelling to Glenarden Road,
Skiles Lane, from Old Snelling to Glenarden Road,
Snelling A venue N, from Arden Place to cul-de-sac, and
WHEREAS, ten dayst nlailed notice and two weekst published notice of the hearing was
given, and the hearing was held on January 12,2009, at which all persons desiring to be heard
were given an opportunity to be heard thereon,
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF ARDEN
HILLS, MINNESOTA:
1. Such improvement is necessary, cost-effective, and feasible as detailed in the feasibility
report.
2. Such improvement is hereby ordered as proposed in the Council resolution adopted January
12, 2009.
3. Bolton & Menk, Inc. is hereby designated as the engineer for this imprQvement. The engineer
shall prepare plans and specifications for the making of such improvement.
ADOPTED BY THE CITY COUNCIL OF THE CITY OF ARDEN HILLS THIS
12th DAY OF JANUARY, 2009.