HomeMy WebLinkAbout4E, Amendment #2 to Kimley-Horn ContractRequest for Council Action
Prepared By: Michelle Olson, Parks and Recreation
Manager, Kris Giga, Civil Engineer
Council Meeting Date: August 31, 2009
Motion to approve amendment number two to the original Kimley Horn contract to complete
an application for the Mn/DOT Metro Municipal Agreement solicitation in an amount not to
exceed $5,850.
Budgeted Amount: Actual Amount: Funding Source:
$32,360 — Alternative #1 $389210 Special Revenue Park Fund
Recommendation:
1. Motion to approve amendment number two to the original Kimley-Horn contract to
complete an application for the Mn/DOT Metro Municipal Agreement solicitation in
an amount not to exceed $5,850.
Supporting Documents:
1. See the attached memo from Michelle Olson, Parks and Recreation Manager and Kristine
Giga, Civil Engineer
2. Amendment #2 from Kimley-Horn
EN HILLS
MEMORANDUM
DATE: August 25, 2009
TO: Honorable Mayor and City Council
Ronald J. Moorse, City Administrator
FROM: Michelle Olson, Parks and Recreation Manager
Kristine Giga, Civil Engineer
SUBJECT: Municipal Agreement Program Application
BACKGROUND
At the May 26, 2009 Regular City Council Meeting, the City Council authorized staff to contract
with Kimley-Horn and Associates to provide engineering services for the County Road E
Pedestrian Improvement Project. This authorization included completing an application for
funding through the 2009 Regional Solicitation of Federal Transportation Projects for the County
Road E pedestrian/bicycle overpass of Snelling Avenue (TH5 1). On June 8, 2009, the City
Council adopted a resolution of support. The application is currently being reviewed by the
Metropolitan Council. While staff anticipates receiving updates on the review process over the
next few months, the funds will not be officially awarded until January.
The Mn/DOT Bridge Office has completed additional structural analysis for the existing bridge
and determined that certain improvements could be made to the existing bridge without
compromising the structural integrity of the bridge. The contract for Kimley-Horn and
Associates includes coordination with Mn/DOT and preliminary engineering for improvements
to the existing bridge. Staff and Kimley-Horn met with the Mn/DOT Bridge Office to determine
what would be required if the City were to pursue a reconfiguration project. Mn/DOT indicated
that, in addition to removal of the existing walks and reconstruction of a sidewalk on one side,
the project would also need to include new railings on the bridge and expansion joint
reconstruction.
Mn/DOT recently announced its solicitation of projects for the Mn/DOT Fiscal Year (FY) 2011
(7/l/10-6/30/1 1) Metro Municipal Agreement Program. The proposed budget for this program is
for Fiscal Year 2011 for a total of 3.2 million dollars. The maximum award available for any
individual project is $550,000 for construction plus 8% for construction engineering and
inspection for a total of $594,000.
P:\Admin\Council\Agendas & Packet Information\2009\08-31-09 Regular\Packet Information\Memo to CC re - Amendment No 2 - Cty Rd
E083109.doc
Muncipal Agreement Program Application
Page 2
The Municipal Agreement Program provides funding to construction projects that are developed
and administered by local agencies and provide a benefit to both the local community and the
trunk highway system. These funds are intended to pay for a portion of the construction costs of
the project. Right of Way, Utility relocation and Design costs are not eligible for funding. The
following categories will be used in prioritizing selections:
1. Support Community Development
2. Improve Safety
3. Improve Mobility
4. Maintaining Existing Infrastructure (Preservation)
This Cooperative Agreement Program is an annual program which provides Mn/DOT funding
for mutually beneficial projects developed and administered by a local government unit. It is a
competitive program and projects will be selected for FY 2011 in January 2010. Deadline for
submittal is September 28, 2009. This is the same program that the City has applied for on two
previous occasions. However, the City has been working closely with the Mn/DOT Bridge
Office, who has suggested that a full deck overlay be considered as apart of the project. The last
maintenance done on the bridge was a limited service overlay in 1994. This type of maintenance
is typically expected to last 10 years. There currently is no scheduled maintenance or funding
for this bridge, and adding a full deck overlay to the project would extend the life of the bridge
and meet the intent of the preservation category.
As part of their current contract, Kimley-Horn is working on a cost estimate for the approved
modifications to the existing bridge. This analysis is not complete. However, in order to provide
an idea to City Council regarding estimated costs for this application, Kimley-Horn has indicated
that a bridge reconfiguration project of this magnitude would likely cost less than $550,000,
which is the maximum amount that is awarded through the Municipal Agreement Program.
STAFF RECOMMENDATION
Kimley-Horn is already working on multiple elements of the requirements that would be needed
for the application as part of their preliminary engineering tasks. Therefore, staff is
recommending that Kimley-Horn provide assistance in the Municipal Agreement Application
Preparation. Included with this memo is amendment number two (2) to the original County
Road E contract that proposes the additional services for a fee of $5,850.
COUNCIL ACTION REQUESTED
Motion to approve amendment number two to the original Kimley-Horn contract to complete an
application for the Mn/DOT Metro Municipal Agreement solicitation in an amount not to exceed
$5,850.
If the City Council has significant questions regarding this item, it can be tabled to the
September 14, 2009, City Council meeting for further discussion.
AMENDMENT NUMBER TWO (2) TO THE AGREEMENT
BETWEEN THE CLIENT AND KIMLEY-HORN AND
ASSOCIATES, INC.
AMENDMENT NUMBER TWO (2) DATED AUGUST 25, 2009 to the agreement
between The City of Arden Hills, ("Client") and Kimley-Horn and Associates, Inc.,
("Consultant") dated June 12, 2009 ("the Agreement") concerning County Road E Bridge
Pedestrian Improvements project (the "Project").
The Consultant has entered into the Agreement with Client for the furnishing of
professional services, and the parties now desire to amend the Agreement.
Therefore, it is mutually agreed that the Agreement is amended to include Additional
Services to be performed by Consultant and provisions for additional compensation by the Client
to the Consultant, all as set forth in Exhibit A hereto. The parties ratify the terms and conditions
of the Agreement not inconsistent with this Amendment, all of which are incorporated by
reference.
CLIENT:
CONSULTANT:
CITY OF ARDEN HILLS KIMLEY-HORN AND ASSOCIATES, INC.
By: _
Title:
Date:
By: _
Title:
Date:
Rev. 11-08
Exhibit A to Amendment Number Two (2),
dated August 25, 2009.
Scope of Work
The scope of work included in the Agreement shall be amended as follows:
A. Mn/DOT Municipal Agreement Application Preparation
The scope of proposed improvements under Task 1, Existing Bridge Modification, shall
be amended to include Task 1.7, Municipal Agreement Application Preparation. The
application will include the following:
• Request cover letter describing the project, identifying the requested amount, and
detailing the benefits to the trunk highway and local roadway.
• Geometric layout of the proposed improvements. Kimley-Horn's services do not
include preparation of a Mn/DOT staff approved layout that may be required as a
part of the project development if the project is selected.
• Cost estimate.
• Signed local agency resolution stating that the City is requesting funding and if
funding is provided the City will complete the project. We will prepare a draft
resolution for City staff to take to the Council.
• One page summary of the project listing the reasons for the project, benefits, and
proposed costs.
We will also address one round of comments from Mn/DOT regarding the application.
Schedule
The application will be prepared for submittal to Mn/DOT Metro District State Aid on or by the
submittal deadline of September 28th, 2009.
Fee
Consistent with the Agreement, Kimley-Horn will provide the scope of services on a labor fee
plus expense basis. Labor fee will be billed according to our 2009 standard hourly rate schedule,
which is subject to annual adjustment. An amount equal to 6.0% of Kimley-Horn labor fee will
be added to each invoice to cover certain other expenses such as in-house duplicating, local
mileage, telephone calls, facsimiles, postage, and word processing. All permitting, application,
and similar project fees will be paid directly by the Client. The following is a summary of our
estimated cost for the additional work identified in this Amendment.
Task
Estimated Fee
A. Municipal Agreement Application Preparation $ 55500
Reimbursable Expenses $ 350
Total $ 59850
The fee to complete the additional services included in this amendment is $5,850 including
reimbursable expenses.
Rev. 11-08