HomeMy WebLinkAbout7A, Elmer L. Andersen Memorial Trail Bid�;�. EN HILLS = Re uest for Council Action : q � � � Prepared By: Kristine Giga, Civil Engineer = Council Meeting Date: February 22, 2010 Elmer L. Andersen Memorial Trail Connections Bid Award Budgeted Amount: Estimated Actual Amount: Funding Source: $624,484 (including $458,800 (construction contract) ARRA, SRTS, DNR, engineering) Ramsey County, Boston Scientific, Surface Water Management Fund, Park Improvement Fund Recommendation: 1. Motion adopting Resolution 2010-009 awarding a bid for the Elmer L. Andersen Memorial Trail Connections Project in the amount of $458,800 to American Liberty Construction, Inc. of Rockford, Minnesota. .............................................................................................................................. ........ . , . . . . . . ... . . ........ ..........................». ..........................................�.............._....... ...... ..................................................................,............................. _................................_..................................._........._.................................................................. Supporting Documents: 1. Memorandum from City Staff dated February 22, 2010. 2. Resolution 2010-009. �.� EN HILLS MEMOR.ANDUM DATE: February 22, 201 � TO: Honorable Mayor and City Council Members Sue Iverson, Acting City Administrator FROM: Kristine Giga, Civil Engineer Michelle Olson, Parks and Recreation Manager SUBJECT: Elmer L. Andersen Memorial Trail Connections Bid Award Back�round/Discussion In March and April of 2009, staff combined the Perry Park Pathway and the County Road E-2 Pathway (Safe Routes to School) projects into the Elmer L. Andersen Memorial Trail Connections Proj ect. An application was submitted for Transportation Enhancements (TE) Funding under the American Recovery and Reinvestment Act (A�). The City was successful in receiving funding for this proj ect. Plans were prepared and submitted to Mn/DOT Metro State Aid in November, 2009, for review and approvals. Following their review, Mn/DOT recommended the proj ect for approval to the Transportation Board. Staff was notified in late December 2009, that all approvals were in place and the proj ect could be advertised for bid. Bids were solicited during the month of January 2010. The bids were opened on Thursday, January 28, 2010. Based on the bids received, staff recommends awarding the project. Based on past practice, the City Council has awarded construction contracts to the lowest resp�onsible bidder. In the case of the Elmer L. Andersen Memorial Trail Connections Proj ect, the lowest bidder is American Liberty Construction, Inc., of Rockford, Minnesota. Financial Implications The City received i'ifteen (15) bids for this proj ect. The low bid submitted by American Liberty Construction, Inc., $458,800, is 11 % lower than the construction estimate of $514,346 provided at the June 2009 City Council worksession. The following is a list of the bids received: City Council Meeting \�.Metro-inet.us\ardenhills�PR&PW�Engineering\Council_Actions\2010\2-22-lOMemo ELATrail BidAward.doc Page 1 of 2 BIDDER A,MOUNT American Liberty Construction, Inc. $ 458,800.00 North Pine Aggregate, Inc. $ 482,235.80 T. A. Schifsky & Sons, Inc. $ 495,844.98 Landwehr Construction Company $ 503,722.45 Buck Blacktop, Inc. $ 517,452.49 Northwest Asphalt, Inc. $ 520,102.68 Minger C onstruction, Inc . $ 5 2 6,1 S 3. 6 5 Rachel Contracting, LLC $ 534,777.00 Veit & Company, Inc. $ 537,243.60 Rosti Construction Company $ 548,871.00 Midwest Asphalt Corporation $ 550,718.60 Frattalone Companies, Inc. $ 569,775.80 Sunram Construction, Inc. $ 574,449.11 Forest Lake Contracting, Inc. $ 595,410.20 R.E. Peterson, Inc. $ 646,283.35 Because the low bid was lower than the engi�.eer's estimate, lt 1S anticipated that the construction costs for this proj ect will be paid for entirely with grant monies. Council Action Requested Approval of Resolution 2010-009: awarding the Elmer L. Andersen Memorial Trail Connections Proj ect to American Liberty Construction, Inc., in the amount of $45 8, 800. City Council Meeting \�Metro-inet.us\ardenhills�PR&PW\Engineering\Council_Actions\2010\2-22- l OMemo_ELATrail_BidAward.doc Page 2 of 2 �. EN �IL�,S CI'�Y �F ARDEN HILLS CO�JN�Y flF RAMSE� S'TATE OF MINNES4T� R.�SOI..U'I'IO� �TO. 2010-009 A RES�LLT'TIO1�T AWARDING '�'�IE ELMER L. ANDERSEN MEIV�UR�AL TRAIL C4�TNEC'T�ONS PROJECT �VH�REAS, pu�rsuant to adve�tiserr�en� for bids for the im�rovernent c�f �he City af Arden Hills Elrner L. �ndersen 11�er�orial Trail Connections Project, according to the lan� � and specifica�ions �hereo� on �ie ir� t�e off�ce �f t�e Adrninistraior of said City, said b�ds vvere rece�ved on January 28, 2� 10, at 9: �� a.m., opened and tabulated accordi�g �o law and t�e �ol�ov�ing bids were received complying with t�e advertisernent: AND WHEREAS, it appears �hat American Liberty Construction, Inc. of Rockford, 1Vlin�esota, is the lowest responsible bidder at the tabulated price o f$458,800.00; i�OW T�iEREFORE, BE IT RESOLVED BY �'HE CITY COiJNCIL OF ARDEN �-IILLS, �VIINNESOTA: l. The Mayor ar�d City Administrator are hereby authorized and directed to enter into a con�rac� with A.n�erican Libe�y Construction, I�c. o f �ockford, 1V�innesota, for $458,8t�0.00 in �he name o� the City of Arder� Hills for the abo�e im�rovements according to t�e plans and speci�cations thereof heretofore approved by �he Cit� Co�ncil a�d on f��e i� t�e office of t%e C�ty Adrr�inis�rator. �. The Ci�y Admi�istra�or is hereby a�thorized and directed to r�turn forthwith to ail b�d�lers t�e deposits n�ade with their b�ds, except that the deposits of t�e suc�essfu� bidder ar�d the next lowest b�dder shall be �etained until contracts have been signed. ADUPTE� BY THE CI'TY C�UNCIL OF THE CITY �F ARDEN HILLS THIS 22nd DAY OF FEBRiJARY, 2010. Staniey D. �ar�stead, Mayor ATTEST: Susa� K. Iverson, Acting City A�lminist�-ator