HomeMy WebLinkAbout8A, Resolution Disapproving Municipal Consent for I-694TH51EN HILLS
Request for Council Action
Prepared By: Terry Maurer, Public Works Director
Budgeted Amount:
N/A
Recommendation:
Council Meeting Date: October 25, 2010
A
Resolution Disapproving Municipal Consent for I- 694/TH51 MnDOT Improvement
Actual Amount:
N/A
Adopt the attached resolution disapproving Municipal Consent with conditions for the MnDOT I- 694/TH51
interchange improvement.
Supporting Documents:
1. Memorandum dated October 25, 2010 from Terry Maurer
2. Resolution 2010 -52 with Exhibit A Conditions for Municipal Consent
Funding Source:
N/A
./k.Rej HILLS
MEMORANDUM
DATE: October 25, 2010
TO: Honorable Mayor and City Council Members
Patrick Klaers, City Administrator
Page 1 of 2
FROM: Terry Maurer, Public Works Director
SUBJECT: Mn/DOT I -694 Improvement Project- Municipal Consent Resolution
Background
Mn/DOT is proposing an improvement project for the interchange of I- 694/TH51 in
Arden Hills. In June, Mn/DOT submitted a Mn/DOT approved layout to the City,
requesting City approval (Municipal Consent) of the layout. On August 9, 2010, the City
Council held the public hearing for this project.
Discussion
Following the August 9, 2010 public hearing, City staff met with Mn/DOT and Ramsey
County to review comments heard from City Council members and residents. (At a later
date staff met with the Shoreview PWD as he was not available for the initial meeting)
Items of discussion included traffic /access, pedestrian movements, noise, and project
benefits. Staff requested additional information from Mn/DOT based on the comments
made at the public hearing.
At the September 20, 2010 worksession the City Council asked staff to prepare some
possible conditions for a Municipal Consent resolution. Those were prepared and emailed
to council members late last month. The draft conditions were reviewed and discussed by
the City Council at their October 11, 2010 worksession. At the end of the discussion the
City Council requested to review the revised conditions at their October 18, 2010
worksession. At the October 18, 2010 worksession the conditions were reviewed and
some minor changes were requested by the City Council.
All of the changes made to the conditions by the City Council at the 18 worksession
have been made with the exception of one. Condition #8 has not been changed as staff
has made a field visit and measured the existing available room for a detached trail on
both sides of the road. A detached trail would require a two foot clear zone from the
curbing, ten feet for the width of the trail and a one foot reaction area between the trail
and the bridge columns for a total of 13 feet. There currently does not appear to be 13
feet of area outside of the road on each side for a detached trail so the condition has be
left to request an appropriate area for a ten foot trail on the west side.
City Council Meeting
C: \Users \terry.maurer\Desktop\I -694 Memo.doc
Schedule
Following the public hearing held August 9, 2010, the City has 90 days, or until
November 7, 2010, to approve /disapprove the layout. The last regularly scheduled City
Council meeting before this deadline is today Monday, October 25, 2010.
Council Action Requested
Adopt the attached Resolution No. 2010 -052 Disapproving the Final Layout of I-
694/TH51 with Conditions.
City Council Meeting
C: \Users \terry.maurer\Desktop \I -694 Memo.doc
Page 2 of 2
AIRENHILLS
CITY OF ARDEN HILLS
COUNTY OF RAMSEY
STATE OF MINNESOTA
RESOLUTION NO. 2010-052
RESOLUTION DISAPPROVING THE FINAL LAYOUT OF I- 694/TH51 WITH CONDITIONS
WHEREAS, Mn /DOT is proposing to undertake an improvement to 1 -694 and is requesting
Municipal Consent approving the layout,
WHEREAS, the City of Arden Hills is concerned about the effects the improvement will have on
vehicle and non motorized /pedestrian movements within the City;
NOW, THEREFORE, BE IT RESOLVED BY THE CITY OF ARDEN HILLS, MINNESOTA:
1. The City disapproves the layout of the I- 694/TH51 improvement. Attached is a list of conditions in
Exhibit A necessary for City approval of the layout.
ADOPTED BY THE CITY COUNCIL OF THE CITY OF ARDEN HILLS THIS 25 DAY OF OCTOBER,
2010.
ATTEST:
Patrick D. Klaers, CITY ADMINISTRATOR
Stanley D. Harpstead, MAYOR
Exhibit A
Conditions for Municipal Consent of I- 694/TH 51 Layout
October 25, 2010
1. The City requests that the revised traffic data outlined in the MnDOT letter dated
September 14, 2010 be added to the approved layout.
2. The City requests that MnDOT show the beginning and ending points of the
possible noise wall on the proposed layout. MnDOT has estimated the
construction cost at $1,525,000 with MnDOT funding $1,050,000 and the City
funding $475,000. The City requests that MnDOT commit to paying any
construction cost over the estimated $1,525,000. In the event that the construction
cost is less than estimated the City requests that their share be prorated.
3. The City requests that MnDOT commit that fill generated on the project will first
stay on the project and be used for sound mitigation berming in all areas where
noise walls are not proposed. Additional fill material, if it exists, should be used
for berming along both sides of I -694 west of the project limits.
4. The City requests that MnDOT prove that the traffic modeling for the I- 694/TH51
improvement considered the entire region and the effect the proposed grade
separated intersection of TH 10 /CR96 with the loss of some movements will have
on the entire transportation system. Furthermore, the City wants MnDOT
modeling to document that the proposed improvement will cause no harm and
actually provide benefit to the county and local road system beyond Hamline
Avenue, County Road F, Lexington Avenue, County Road E and Lexington
Bridge over I -694.
5. The City requests that MnDOT commit that there are no city costs associated with
the proposed improvements necessary on interstate, county or local
system(including changes that might be required on County Roads E, F, Hamline
Avenue, Lexington Avenue or the junctions between) to construct the I- 694/TH51
interchange shown on the proposed layout with the exception of noise walls.
6. The City requests that MnDOT work with Ramsey County staff to identify
necessary improvements to the Lexington Avenue /County Road F intersection,
assist in estimating the costs of such improvements and encumber funding from
the Cooperative Agreement funds or other appropriate fund source in a year
agreed to by the County in consultation with the cities of Arden Hills and
Shoreview.
7. The City requests that MnDOT agree to work with Ramsey County to identify
any potential changes that could be made to the Lexington Avenue Bridge and
adjoining intersections that would improve their operation and make such
improvements prior to the completion of the I -694 interchange.
8. The City requests that MnDOT change the layout as necessary to provide the
required spacing and appropriate (barrier) separation for a 10 foot wide
bituminous trail on the west side of old Snelling Avenue /old TH 10 as it passes
under I -694.
9. The City requests that MnDOT construct a non motorized /pedestrian bridge
across TH 10 to connect North Snelling Avenue to the trail connection under I -694
identified in #8 above.
10. The City requests that MnDOT show on the approved layout a 6 foot wide
concrete sidewalk on the west side of Hamline Avenue from Floral Drive to
County Road F and on the south side of County Road F towards Lexington
Avenue to the existing and/or planned sidewalk.
11. The City request that MnDOT include as part of the proposed bridge structure
crossing I -694 a non- motorized/pedestrian facility that will provide for
movements from the west side of Hamline Avenue to the west side of TH51.
12. The City requests that MnDOT clearly state that the existing area on TH51
available for non-motorized/pedestrian movements will not be lessened in the
future with the proposed improvements.
13. The City requests that MnDOT commit to including the design standards laid out
in the Architectural and Aesthetic Design Guidelines for the I -694 Corridor from
the Mississippi River Crossing in Fridley to the I -694 Interchange in Oakdale,
July 2002.
14. The City requests that MnDOT affirm the intentions for 2015 reconstruction of
the County Road E bridge over TH51 and consider the possibility of moving this
construction up in time to match the balance of the regional construction (for bid
economies of scale and logistics). The City may be able to advance the funds
necessary for this construction given a firm repayment in 2015.