<br /> Unit Qu antity Quantity
<br />No. Item Unit Quantity Price This Period To Date Amount
<br /> BASE BID B - PEDESTAL SPHEROID
<br /> CONSTRUCTION:
<br />6 SOO,OOO GALLON STEEL FLUTED COLUMN
<br /> WATER TOWER- TOTAL BASE BID A LS $837,19S.00
<br /> Breakdown of Base Bid B
<br />6a Design Drawings LS 1 $25,000 100.0% $25,000.00
<br />6b Foundation LS 1 $210,000 100.0% $210,000.00
<br />6c Steel Fabricated to Site LS 1 $235,895 100.0% $23S,895.00
<br />6d Field Erect10n LS 1 $138,000 100.0% $138,000.00
<br />6e Field Painting LS 1 $190,000 18.7% 18.7% $3S,500.00
<br />6f Field Electrical LS 1 $30,000 $0.00
<br />6g Cathodic Protection LS 1 $8,300 $0.00
<br /> Total Breakdown $644,395.00
<br /> FOUNDATION PILING - BASE BID B - PEDESTAL
<br /> SPHEROID PILING:
<br />16 9-5/8" DIA. CAST-iN-PLACE CONCRETE TEST PILE EA 2 $1,600.00 2 $3,200.00
<br />17 9-S/S" DIA. CAST-IN-PLACE CONCRETE PILING,
<br /> DRIVEN LF 2080 $17.00 2061 $35,037.00
<br /> TOTAL FOUNDATION PILING $38,237.00
<br /> SITE WORK:
<br />20 SALVAGE AND REINSTALL CHAIN LINK FENCE LF 24 $29.15 24 $699.60
<br />21 SALVAGE, STOCKPILE, AND RESPREAD TOPSOIL LS 1 $100.00 1 $100.00
<br />22 REMOVE WATER MAIN LF 114 $10.00 114 $1,140.00
<br />23 REMOVE STREET SWEEPING MATERIAL CY 220 $5.00 $0.00
<br />24 SILT FENCE, REGULAR LF 600 $3.00 588 $1,764.00
<br />25 6' HIGH CHAIN LINK FENCE LF 135 $18.45 $0.00
<br />26 20' WIDE DOUBLE SWING GATE EA 1 $1,030.00 $0.00
<br />27 TYPE 41 BITUMINOUS FOR DRIVEWAYS TN 40 $40.00 $0.00
<br />28 TYPE 31 BITUMINOUS BASE COURSE TN 50 $40.00 $0.00
<br />29 AGGREGATE BASE, CLASS 5, 100% CRUSHED TN 700 $20.00 $0.00
<br />30 GEOTEXTiLE FABRIC, TYPE V SY 360 $2.00 $0.00
<br />31 CONNECT TO EXISTING WATER MAIN EA 2 $500.00 2 $1,000.00
<br />32 16" PVCWATER MAIN LF 270 $45.00 286 $12,870.00
<br />33 16" DIP WATERMAiN, CLASS 52, INCL. POLY LF 115 $40.00 110 $4,400.00
<br />34 aM DIP WATER MAIN,CL 52,INCL POLY WRAP LF 10 $25.00 18.5 $462.50
<br />356M GATE VALVE AND BOX EA 1 $650.00 2 $1,300.00
<br />36 12" GATE VALVE AND BOX EA 1 $1,500.00 1 $1,500.00
<br />37 16" GATE VALVE AND BOX EA 1 $4,000.00 1 $4,000.00
<br />38 CAST IRON FITTINGS LB 2065 $2.00 3089 $6,178.00
<br />39 INSTALL HYDRANT EA 1 $1,800.00 1 $1,800.00
<br />40 OVERFLOW MANHOLE EA 1 $2,500.00 1 $2,500.00
<br />41 15" RCP STORM SEWER lF 120 $30.00 104 $3,120.00
<br />42 15" RCP FLARED END SECTION EA 1 $500.00 1 $500.00
<br />43 CLASS III RIPRAP, PLACED AT FLARED END
<br /> SECTION CY 5 $100.00 5 $500.00
<br />44 MNDOT SEED MIX 70A AC 0.2 $5,000.00 $0.00
<br />4S WOOD FIBER BLANKET SY 500 $5.00 $0.00
<br /> TOTAL SITE WORK $43,834.10
<br /> TOTAL BASE BID B $644,395.00
<br /> TOTAL FOUNDATION PILINGS $38,237.00
<br /> TOTAL SITE WORK $43,834.10
<br /> TOTAL WORK COMPLETED TO DATE $726,466.10
<br /> MATERIALS ON HAND:
<br /> None $0.00
<br /> TOTAL STORED MATERIALS $0.00