Howard R. Green Company <br /> CONSULTING ENGINEERS t2T"112L18 <br /> case <br /> TOTAL PROJECT COSTS <br /> WATERMAIN <br /> 20 TH Avenue $227,180.00 <br /> Overhead (38 %) $ 86,330.00 <br /> Sub -Total $313 <br /> SANITARY SEWER <br /> 20 Avenue $281,610.00 <br /> Overhead (38 %) $107,000.00 <br /> Sub -Total $388,610.00 <br /> TOTAL PROJECT COST $702,120.00 <br /> ALTERNATES <br /> Alternate A — East Watermain Extension $45,620.00 <br /> Overhead (38 %) $17,335.00 <br /> Total Project Cost — Alternate A $62,955.00 <br /> Alternate B — SCADA/Telemetry System $ 86,456.00 <br /> Overhead (38 %) $ 32,855.00 <br /> Total Project Cost — Alternate B $119,311.00 <br /> Alternate C — Directional Bore Forcemain $ 27,390.00 <br /> Overhead (38 %) $ 10,400.00 <br /> Total — Project Cost Alternate C $37,790.00 <br /> 2601085- 1803.sept <br />