<br /> 21st Avenue Assessment <br />City of Centerville Portion <br />Project.component Construction Engineering Total Assessment Assessment <br /> Costs Costs Project Ratio Amount <br />Street Construction $45,059 $21,782 $66,841 25% $16,710 <br />Curb & Gutter $19,311 $9,335 $28,646 75% $21,485 <br />Storm Sewer $16,525 $7,988 $24,513 50% $12,257 <br />Total Cost $80,895 $39,105 $120,000 $50,451 <br />Cost per Benefitted Property $16,817 <br />Arcade Asphalt "$16,e17 14% <br />ADL Automotive $16,817 14% <br />Noble Welding $16,817 14% <br />City of Centerville $69,549 58%" <br /> - <br />Total Project Cost $120,000 100% <br />Not~: <br />1. Curb & Gutter costs calculated at 30% of Street Construction Cost <br />2. Enaineering costs divided proportionally amonQ components <br /> <br />9/23/2003 <br /> <br />2:47 PM <br /> <br />21st Avenue <br />