Stantec Consulting Services Inc.
<br /> 2335 Highway 36 West
<br /> AOL St Paul MN 55113
<br /> Tel: (651) 636 -4600
<br /> Fax: (651) 636 -1311
<br /> Stantec
<br /> February 21, 2013
<br /> Honorable Mayor and City Council
<br /> City of Centerville
<br /> 1880 Main Street
<br /> Centerville, MN 55038 -9794
<br /> Re: 2013 Street and Utility Improvements Project
<br /> Project No. 193801520
<br /> Bid Results
<br /> Dear Honorable Mayor and City Council:
<br /> Bids were opened for the Project stated above on February 20, 2013. Transmitted herewith is a copy of the
<br /> Bid Tabulation for your information and file. Copies will also be distributed to each Bidder once the Project
<br /> has been awarded.
<br /> There were a total of 9 Bids. The following summarizes the results of the Bids received:
<br /> Contractor Total Base Bid
<br /> Low Northdale Construction Co., Inc. $1,533,650.86
<br /> #2 Redstone Construction Co., Inc. $1,582,281.72
<br /> #3 Burschville Construction, Inc. $1,592,253.80
<br /> #4 C & L Excavating, Inc. $1,624,674.22
<br /> #5 Frattalone Companies $1,640,649.87
<br /> #6 T.A. Schifsky & Sons, Inc. $1,641,671.73
<br /> #7 Valley Paving, Inc. $1,751,384.65
<br /> #8 Meyer Contracting Inc. $1,990,492.20
<br /> #9 Dresel Contracting, Inc. $2,292,563.00
<br /> The low Bidder on the Project was Northdale Construction Co., Inc., with a Total Base Bid Amount of
<br /> $1,533,650.86. This compares to the Engineer's Estimate of $1,500,644, which includes the feasibility
<br /> study estimate, plus the upgraded water main sizing. Overall, this means the bids came in approximately
<br /> 2.2% over the estimate. These Bids have been reviewed and found to be in order.
<br /> However, there are some larger discrepancies when the costs are broken down a bit.
<br /> Improvement /Area Feasibility Report Bid Difference
<br /> Streets
<br /> Centerville Heights $368,243 $308,606 ($59,637)
<br /> Center Oaks 2 $675,129 $852,943 $177,813
<br /> Net Street Improvements $1,043,372 $1,161,549 $118,177
<br /> Water Main
<br /> Center Oaks 2 (8" WM) $193,522 $217,494 $23,972
<br /> Upgrade to 12" WM $40,000 $0 ($40,000)
<br /> Net Street Improvements $233,522 $217,494 ($16,028)
<br />
|