								    							  	REVISED EXHIBIT B - March 10, 2014
<br />								     	Cost Share Estimate
<br />							  	Joint Powers Agreement for 21 st Avenue
<br />								  	Dated September 17, 2013
<br />									     	Lino Lakes
<br />									     	Oversize/		Lino Lakes     	Lino Lakes     	Centerville
<br />			    	Cost Item		   	Total Cost     	Overdepth	  	Base	    	Total	    	Total
<br />	   	Street Improvements		     	$    	454,620		     	$     	298,932   	$     	298,932   	$     	155,688
<br />	   	Sanitary Sewer			    	$    	135,583   	$		63,000   	$		36,292   	$		99,292   	$		36,292
<br />	    	Watermain (Lino Lakes)		  	$    	138,494   	$		48,000   	$		90,494   	$     	138,494
<br />	   	Watermain (Centerville)		   	$     	24,724							    	$		24,724
<br />	   	Storm Sewer					$     	88,550		     	$		44,275   	$		44,275   	$		44,275
<br />	   	Wetland Mitigation			 	$     	68,543		     	$		34,271   	$		34,271   	$		34,271
<br />	     	Subtotal				   	$    	910,514   	$     	111,000   	$     	504,263   	$     	615,263   	$     	295,250
<br />	   	Engineering Estimated		    	$ 155,000.00	 	18,895.93		85,842.54   	$     	104,738	 	50,261.53
<br />	   	Project Cost				 	$  1,065,514   	$     	129,896   	$     	590,106   	$     	720,002   	$     	345,512
<br />	   	Subtotal for agreement		   	$  1,065,514					  	$     	720,002   	$     	345,512
<br />	   	Internal Costs for Legal\Admin  (7 %)    	$     	63,736   	$	 	7,770   	$		35,298   	$		43,068   	$		20,668
<br />	   	Total Cost				  	$  1,129,249					  	$     	763,070   	$     	366,179
<br />	    	Notes:  Street Improvement estimates include allocation of $114,526 for Bank frontage as follows:
<br />							 	Bank Share    	$		50,000  one half to Lino Lakes
<br />							 	Bank Share    	$		64,527  to Lino Lakes
<br />	   	Advance from Centerville			    	90%							    	$  310,960.71